1 cmaa owners’ forum may 2010 american airlines ken bower, md facilities
TRANSCRIPT
1
CMAA Owners’ Forum
May 2010American Airlines
Ken Bower, MD Facilities
2
AMR Capital Planning
An annual forecast of all capital needs They are grouped into one of the following categories: 1) business critical, 2) has a quick ROI, 3) a regulatory requirement or 4) improves the customer experience
Capital spending falls into the following six asset categories
– Aircraft
– Facility
– Interior A/C Modification
– Other A/C Modifications
– Ground Equipment
– Computer
3
PROPOSED PROJECTS 2010
Project Name Asset Type 2010 $,000 Dept Location
BOS Admirals Club Facility $ 2,200 MKTG BOS
BWI GSE & Cargo Relocation Facility 1,050 Cargo BWI
HDQ Campus Furnishings Facility 7,500 CRE HDQ
HDQ FTA Central Plant Analysis Facility 388 CRE HDQ
HDQ TCC Refurbishment and Remodel (3 Yr Plan) Facility 1,000 CRE HDQ
JFK Admirals C Club Expansion Facility 4,100 MKTG JFK
JFK Concourse B Scanners Facility 900 DCS JFK
JFK Expand FIS Recheck Facility Facility 1,344 DCS JFK
JFK Hangar 10 Fire Alarm Facility 400 DCS JFK
JFK Interstitial Level Ventilation Facility 600 DCS JFK
JFK Master Plan Baggage Facility 335 DCS JFK
JFK Relocation to Nippon Cargo Facility Facility 7,124 DCS JFK
LAX Prelim A&E In-Line Bag Screening System Facility 3,235 DCS LAX
LAX Priority Check-in Facility 260 DCS LAX
LGA Admirals Club Executive Center Facility 500 DCS LGA
LGA Admirals Club Refurbishment Facility 1,500 DCS LGA
LGA Brick Restoration Facility 300 DCS LGA
LGA Concourse D Security Checkpoint Facility 800 DCS LGA
LGA Concourse D Upgrade Facility 2,475 DCS LGA
LGA Escalator Facility 4,100 DCS LGA
4
PROPOSED PROJECTS 2010
Project Name Asset Type 2010 $000 Dept Location
LGA Fire Alarm Replacement Hgr 1,3,5 Facility $ 380 DCS LGA
LGA Prelim A&E Fees In-Line Bag Screening Facility 822 DCS LGA
LHR Admirals Club Facility 9,937 MKTG LHR
MIA Capitalized Management Costs Facility 400 CRE MIA
MIA Communications Infrastructure Facility 196 CRE MIA
MIA Conveyor & Airfield Equipment Facility 512 DCS MIA
MIA Early Bag Storage System Facility 312 DCS MIA
MIA Flagship Lounge Facility 995 MKTG MIA
MIA North Terminal Expansion - CRE Facility 1,495 CRE MIA
MIA Program Contingency Facility 640 CRE MIA
MIA Regional Commuter Facility Facility 570 DCS MIA
MIA Sabre Infrastructure & Equipment Facility 609 DCS MIA
ORD- Baggage Handling System Upgrade (BHS Computer) Facility 206 DCS ORD
ORD Hanger 1&2 Fire Protection Facility 5,650 DCS ORD
ORD Jet-bridges Facility 5,200 DCS ORD
RNO Right Sizing Facility 150 DCS RNO
SFO Admiral Club Refurbishment Facility 1,077 MKTG LHR
SFO Terminal Move Facility 240 DCS MIA
TUS SWRO UPS Replacement Facility 176 CRE ORD
YYZ Admirals Club Relocation Facility 150 MKTG ORD
5
Departmental Guidelines
If a firm is interested in doing work for American…it will go through a comprehensive prequalification process
– Complete our standard qualification form and get that in front of the right person
– Include all pertinent company information, i.e. staff, financials, experience, etc
AA requires that all qualified firms must have:
– Airport experience
– Project type of experience
6
Departmental Guidelines
We only use AA standard contracts
Normally, Initial project funding will provide for design services through the Design Development Phase
– A&E agreement : compensation based upon DLM
– cost estimate / schedule
Estimate is basis for creation of construction funding document used to gain company approval.
– Over $25M …..must be approved by BOD
7
Departmental Guidelines
AA Project Manager Responsible for development of project’s business plan, i.e. project implementation/delivery
For those projects that exceed $10M, AA will typically secure additional resources to assist the Project Manager
– Project auditor/accountant
– Contract project manager
For those projects that exceed $50M we will secure supplemental staff via:
– Program Manager
– Construction Manager
– Extended A&E Services
8
Recipe for Project Delivery
Selecting a project delivery method is a lot like ordering off a menu at a NY diner
Everyone here is aware that there are numerous methods and that the language and terms used for each can be confusing
Design-Bid-Build: The most tried and true way to contract for a project. Owners hires architect to design and prepare contract documents, general contractor then bid on the documents with the successful bidder being awarded a contract to build it.
– Considered by American to be the safest option
– In theory, it may be the slowest way to execute a project
9
Recipe for Project Delivery
Design-Bid-Build: (cont)
– It is price driven and prices may reflect an artificially low bid/s
– Owner must have in-house expertise and resources to play the game
– Provides owner with desired checks and balances
Design –Build: Owner elects to secure services for design and construction from a single entity.
– Faster project completion
– Enhanced communications between A/E & contractor
– Fewer administrative duties
– A/E under contractor…owner loss of control over designer
10
Recipe for Project Delivery
Design –Build: (cont)
– No checks and balances
– Requires owner’s in house staff resources with an additional challenge
Construction Management: A method of delivery with the most variations There are three basic ways to use with the manager acting as an advisor, an agent or at risk constructor
– CM-Advisor : Contractual relationship is with owner to oversee the designer and contractor
* Something goes wrong…CM says “sorry” as he is not financially at risk
* Additional cost to owner
* More appropriate for large projects and owners without in-house resources
* No guarantees to owner
11
Recipe for Project Delivery
Construction Management: (cont)
– CM-Agent : Contractual relationship is with owner acting as its agent , CM administers the construction throughout the planning design and construction phases of the project.
* Usually empowered to act in behalf of the owner, but, CM is not financially at risk for anything that may go wrong
– Owner still holds separate contracts with designer and general contractor and/or various prime subs
– CM not responsible for means or methods
* Additional cost to owner
* More appropriate for large projects & owners w/o in-house resources
* No guarantees to owner
12
Recipe for Project Delivery
Construction Management: (Cont)
– CM-at -Risk: Perhaps the most popular model with most owners The CM is hired by owner and engaged during the initial stages of design and ultimately becomes the general contractor
* Owner gains expertise of builder early in the project’s development.
* Removes any ‘mystery’ of pricing for the contractor
* Cost and schedule of the project are guaranteed
Program Management: The PM serves an ‘owners representative’ in all aspects
– Any company with restricted resources or is lacking in-house expertise
– True PM is also completely free from any conflict of interest
13
Recipe for Project Delivery
So how many project delivery methods are there?
– Traditional ‘Design-Bid-Build ‘and …
– The ‘Team Approach’
You can use any term you want….general contractor, design-builder, construction manager, program manager or any other names ….…
– They all simply help describe how you want to assign design and construction responsibilities….and
– They all work off of the customary owner-architect-contractor relationships
14
What AA’s Menu Looks like
So which project delivery system is best….from one owner’s perspective it is the one that :
– Has the right People (integrity, confidence and trust)
– Completes the project within Budget
– Completes the project on Schedule
– Has the ability to cost effectively Manage Change
– Produces uncompromising Quality
– Delivers a Safe work environment
– Provides for DMWBE participation
– Provides the Resources necessary to get the job done
15
This Owner
Selected the wrong Delivery Method
16
17
Intro
Thank you……………… I do recall that there was a pre-AMR life for me …but time has blurred the details?
Following the suggested framework…I will start by touching upon AMR’s programs and plans related to capital construction
Slide 1 AMR Capital Planning
18
AMR Capital PlanningTalking points
The following two slides represent the majority of the projects that actually made the 2010-2011 Capital plan
Each department, division, station compiles its list of projects along with a brief description/scope of work…..this is often referred to as the “wish list”
Process begins each September and is completed in January when the final project list is reviewed with the BOD
19
Talking points slides 3/4
Over 90% of the projects in any given year will be under $10M
The majority of the capital dollars spent in any given year will be spent at our “corner posts”…..
– DFW….MIA….ORD…..New York…..LAX
This list reflects a projected CRE capital spending of $65M in 2010 and $42M in 2011
In comparison we spent in:
– 2005….$275M
20
A&E Selection Process
RFP’s are issued by the responsible project manager
Proposals are requested by invitation only and are evaluated and rated based upon a number of subjective as well as a number of quantitative measures:
– People & related experience
– Consultants & related experience
– Hourly rates and total fee must be competitive
– DMWBE participation with a goal of 22%
21
CRE Departmental Guidelines
Bid Threshold
– Less than $25K…..local project (CRE not required)
– $25k to $50K……CRE managed & can sole source the work
– Excess of $50K……CRE managed and competitively bid
AMR uses Standard Contracts for professional services and construction
* Stipulated Sum
* Time and Material (GMAX, Cost Plus, Unit Price)
22
CRE Contractor Selection Process
AA Project Manager responsible for establishing list of contractors to be invited to bid.
– All firms must have been prequalified
* Previous experience with:
– American
– work on airport
– projects of similar type and size
– References: Firm and staff
– Financial strength
– Willingness to sign standard contract