Page 1: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

1

China country report on I&C status and recommendations to IAEA

Jiang HongThe 22nd Meeting of the IAEA TWG – NPPIC

on May 20-22, 2009, Austria Center Vienna (ACV), Vienna, Austria

Page 2: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

2

1. Nuclear Power in China

2. Activities ongoing

3. Issues and Topics to IAEA

4. Experts and Contributors

Presentation Outlines

Page 3: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

3

NPP in operationNPP Name Unit

No.Reactor

TypeNominal Power (MWe)

Construction Start Date

Date of First Connection to

the Grid

Qinshan NPP Phase I CN-1 PWR 310 1985-03-21 1991-12-15

Guangdong Daya Bay NPP

Unit1 CN-2 PWR 984 1987-08-07 1993-08-31

Unit2 CN-3 984 1988-04-07 1994-02-07

Qinshan Phase II NPP

Unit1 CN-4 PWR 650 1996-06-02 2002-02-06

Unit2 CN-5 650 1997-04-01 2004-03-11

Guangdong LingAo NPP

Unit1 CN-6 PWR 990 1997-05-15 2002-02-26

Unit2 CN-7 990 1997-11-28 2002-09-14

Qinshan Phase III NPP

Unit1 CN-8 CANDU 720 1998-06-08 2002-11-19

Unit2 CN-9 720 1998-09-25 2003-06-12

Jiangsu Tianwan NPP

Unit1 CN-10 PWR 1060 1999-09-20 2006-05-12

Unit2 CN-11 1060 2000-09-20 2007-07

Nuclear Power in China

Note: Refer to 2007 TWG report for I&C systems applied in existing NPPs.

Page 4: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

4

Challenges to Chinese NPP I&C industry: By 2007, 11 units in operation, but 5 types of reactor

among them:1. 300MW PWR

2. 600MW PWR

3. 900MW PWR

4. 700MW CANDU

5. 1060MW VVER

Lack of human resource and knowledge accumulation:• Engineers spreading out concentrating at different I&C system

specific to each type of reactor, thus experiences narrowed.

• Much more knowledgeable experts needed to support regulator.

No time to recall, digest and “asking why” before being driven to a new era.

Nuclear Power in China

Page 5: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

5

Policy and Planning: Policy changed from “properly development” to

“actively promoting”. By the year 2020, NPP installed capacity will

targeting at 40 GWe, accounting for 4% of total installed electric power supply nationwide. And NPP of 18 billion KWe under construction in addition.

Recent study on national NPP program planning shows, 75 GWe, accounting for 5% of Total capacity is expected by 2020, still far from world average level 17%.

Nuclear Power in China

Page 6: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

6

NPPs in construction and to be built in 2009

Nuclear Power in China

Projects Province Total Capacity (MW) FCDLinao II (unit 3,4) Guangdong 2x1080 2005.12Qinshan II ext. (unit 3,4) Zhejiang 2x650 2006.4Hongyanhe I (unit 1-4) Liaoning 4x1080 2007.8Ningde I (unit 1,2) Fujian 4x1080 2008.2Fuqing I (unit 1,2) Fujian 2x1000 2008.11Yangjiang I (unit 1-6) Guangdong 6x1080 2008.12Fangjiashan (unit 1,2) Zhejiang 2x1000 2008.12Sanmen I (1,2) Zhejiang 2x1250 (AP1000) 2009.4Changjiang (unit 1,2) Hainan 2x650 2009.10Haiyang (unit 1,2) Shandong 2x1250 (AP1000) 2009.9Taishan (unit 1,2) Guangdong 2x1700 (EPR) 2009.8Rongcheng (HTR-PM) Shandong 200 2009.9

Note: All new built after 2006 installed with full scope digital I&C and Adv. MCR

Page 7: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

7

Activities ongoing

Activities ongoing in China NPP I&C industry

Engineering• CNPE

• CNPDC

• INET

System integrator• CNCS

• China Techenergy Co.

• SNPAS

Utilities• Nuclear power plants

Page 8: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

8

Activities ongoing-Engineering

China Nuclear Power Engineering Co. Ltd. (CNPE)

QS-II Extention, 2x650MW PWR

FCD: Mar. 28, 2006

Construction: 60 months

I/A for non-1E control system

Soft control for Conventional Island

Analogue technology for others

Page 9: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

9

Activities ongoing-Engineering

General engineering contractor for LA-II 2x1080MW PWR

FCD: Feb., 2005, in operation Oct., 2010.

Full scope digital I&C, T-XP, T-XS, OM690

Advanced MCR, Optimized alarm system,

China Nuclear Power Engineering Co. Ltd. (CNPE)

Page 10: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

10

Activities ongoing-Engineering

EPC contractor for Fuqing NPP, 2x1000MW PWR

FCD: Nov. 21, 2008, in operation Nov. 2013. (first unit)

Full scope digital I&C, TRICONEX + I/A, Advanced MCR, Diversified RPS

China Nuclear Power Engineering Co. Ltd. (CNPE)

Page 11: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

11

Activities ongoing-Engineering

EPC contractor for Fangjiashan NPP, 2x1000MW PWR

FCD: Dec. 26, 2008, in operation Dec. 2013. (first unit)

Full scope digital I&C, TRICONEX + I/A, Advanced MCR, Diversified RPS

China Nuclear Power Engineering Co. Ltd. (CNPE)

Page 12: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

12

Activities ongoing-Engineering

EPC contractor in Coming NPP project:

Hunan, Taohuajiang 4xAP1000

Hainan, Changjiang 2x600MW, PWR

Tianwan 5-6, 2x1000MW, PWR

Fuqing 3-4, 2x1000MW, PWR,

Fuqing 5-6, 2x1000MW, CNP1000, PWR

Full scope DCS for all projects above.

China Nuclear Power Engineering Co. Ltd. (CNPE)

Page 13: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

13

Activities ongoing-Engineering

China Nuclear Power Design Co. (CNPDC)

LA-II 2x1000MW, CPR1000, HMI detail design incl. displays,

alarm optimization, comupterized procedures.

Engineering design for Full scope DCS system of Hongyanhe ,

Yangjiang, Ningde . CPR1000.

• I&C general design

• DCS system general design

• Advanced MCR design

R&D on HFE, Stds, 1E platform (HW&SW), Software V&V etc.

Page 14: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

14

Activities ongoing-Engineering

Institute of Nuclear Energy Technology(INET), Tsinghua University

I&C engineering design for the high-temperature gas-cooled reactor demonstration project (HTR-PM) in shidaowan in Shandong Province, ATP in 2009, expected operation in 2013. Preliminary design and PSAR completed Detail design and key technologies verification testing ongoing. Emphases addressed on the integrated control mode, I&C system structure, layout and control rooms for multi NSSS system of modular reactors.

Page 15: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

15

Activities ongoing-Sys. integrator

Introduction on China local DCS System integrator

Background:

As Chinese government established the policy to actively develop the nuclear power industry, efforts on Self-reliance of DCS system integration, localization of the equipment manufacturing and making the technical service and spare parts supply for operating plants locally available, have been one of the major factors to assure the state nuclear power program to be realized and sustainable.

To meet the demands of government policy, three major players in china nuclear power industry, CNNC(China National Nuclear Corporation), CGNPC(China Guangdong Nuclear Power Corporation) and SNPTC(State Nuclear Power Technology Corporation Ltd) have established the companies respectively in the past few years, relying on the ongoing projects, to accept Tech. transfer and progressively to become a qualified DCS system engineering and integrating supplier.

Page 16: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

16

Activities ongoing-Sys. integrator

Introduction on China local DCS System integrator

Three key companies:

1) China Nuclear Control System Engineering Co., Ltd. (CNCS)

Founded in Beijing in August, 2008, jointly invested by CNPE , BNIF and Shanghai Puyuan, 3 subsidiaries of CNNC.

2) China Techenergy Co. Ltd.

Founded in Beijing in October, 2005, jointly invested by CGNPC and Beijing Hollysys Automation Company.

3) State Nuclear Power Automation System Engineering Corp. (SNPAS)

Founded in Shanghai in March, 2008, jointly invested by SNPTC and Shanghai Automation Instrumentation Corporation Ltd (SAIC).

Page 17: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

17

Activities ongoing-Sys. integrator

Activities ongoing in NPP I&C area – Sys. Integrator

1) CNCS Participated or undertake design, V&V, procurement, system integration, FAT, commisioning and SAT of digital I&C system in Fuqing and Fangjiashan NPP projects. R&D planning on 1E HW&SW platform.

2) China Techenergy Co. Ltd. Participated or undertake design, V&V, procurement, system integration, FAT, commisioning and SAT of digital I&C system in Yangjiang and Ningde NPP projects. R&D activities on 1E HW&SW platform.

3)SNPAS Participated or undertake design, V&V, procurement, system integration, FAT, commisioning and SAT of digital I&C system in Sanmen and Haiyang AP1000 projects.

Page 18: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

18

Activities ongoing-Utilities

Activities ongoing in NPP I&C area – Utilities

Keep on management of NPP I&C obsolete, aging and upgrading, improving reliability, accuracy and life time of NPP I&C system and equipment.

Continually improve equipment management system for various I&C equipment and devices, to enhance the performance monitoring and status data collection, paying much attention on reliability issues.

Obsolete and shortage of spare parts for outdated component have been critical long term issues which operating plants have to work on and put much effort to improve the situation. Most plants have launched aging management project and start to collect aging data of I&C. Together with these activities, the effort also are put on establishing the upgrading plans for NPP life cycle.

Page 19: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

19

Activities ongoing-Utilities

Activities ongoing in NPP I&C area – Utilities (Cont.)

Optimizing preventive maintenance program of NPP I&C, and

establishing maintenance plans for NPP life cycle.

Preventive maintenance system is more and more important along with the increasing of plant operating time. Plants have developed the preventive maintenance program and carried out the maintenance and repairing work based on this program, and will keep on optimizing the program with collected performance status data and defects statistics.

Integrating the activities of the equipment management and the preventive maintenance program, to make maintenance work more pertinent, efficient and actually effective, which is expected to result in a prolonged reliable operating time of I&C system.

Page 20: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

20

Issues and Topics

Issues and Topics Collected from China NPP I&C industry

Engineering

System integrator

Utilities

May or may not covered by current IAEA activities, but reflecting current needs in China NPP I&C industry.

IAEA Tech. support can be:

• Tecdoc

• Training

• Workshop

• Small group of expert consulting on specific topics

Page 21: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

21

Issues and Topics - Engineering

Issues and Topics from Engineering:•Case study and Implementing process for design and V&V of

Computerized MCR

•Qualification requirement and engineering requirement with regard to

independence and diversity on fiber optical cables used in Safety

system

•R&D and qualification of 1E digital control platform (HW&SW)

•Qualification requirement and practice on 1E instruments and

pneumatic or motor drives.

•Field Bus application in safety system

•I&C aging management and its measures to be considered in system

and plant engineering design.

•Standards application comparison between IEEE and IEC.

Page 22: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

22

Issues and Topics from Engineering: (cont.)•Application and qualification of measuring instrumentations for severe

accident conditions.

•Differences of I&C engineering design requirements among PWR,

AP1000, EPR, Fast Breeder reactor and HTGR.

•Experiences & best practices on modernization in operating plant

•I&C knowledge preservation and training for new recruits.

•Specific consulting and safety review in Hongyanhe NPP project.

• DAC solution ( diverse actuator control, without BUP

installed ) with regard D-in-D&D

• Manual checking as part of V&V on Meltec platform

•Comuperized Procedure

•Licensing Method and Stds on 1E Digital I&C application and

Supplier

Issues and Topics - Engineering

Page 23: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

23

Issues & Topics – Sys integrator

Issues and Topics by system integrator:•Consulting on comparison and application between EU and USA

standards regarding to the safety classification and respective practical

qualification requirement and methods on 1E digital platform and

IEC61513 class 2 and 3 equipment.

•Guides on period testing method, configuration and system

parameters to be examined in 1E digital system.

•In-depth technical discussion on feasibility of implementing

bidirectional communication between Safety and non-safety digital

systems through network.

•Practice and method for V&V of 1E digital system development

platform and tools.

•Practice on reliability analysis and V&V of 1E SW platform.

Page 24: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

24

Issues and Topics by utilities:•Site elements seals maintenance

After analysis on Equipment defects statistics, seals of site sensor

element and driving component are major weakness causing leakage.

Sharing of method and requirement on its repairing or maintenance

practice of other NPP is needed.

•Spare parts rules for new I&C

Due to the very fast upgrade or replacement of obsolete I&C

equipment, and failure modes of new one are hardly obtained in time, it

is difficult for maintenance department to define the rules and scope of

spare parts.

Issues & Topics – Utilities

Page 25: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

25

Issues and Topics by utilities : (Cont.)•Preventive maintenance for DCS HW&SW

Preventive maintenance activities for digital control system seem

only limited to general periodic functional testing and cleaning. What

should be done with this respect for in-depth preventive maintenance

on hardware and software?.

•Analogue I&C Performance monitoring

A workshop needs to be held to share the best practices on

performance monitoring, and Surveillance, diagnostics, and prognostic

methods of NPP analogue I&C systems.

Issues & Topics – Utilities

Page 26: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

26

Issues and Topics by utilities : (Cont.)•Study or practices sharing on engineering of DCS online

maintenance

Technologies of computer network, server, workstation, power

supply, and redundancy engineering of critical component and power

module of digital control system have made it possible to perform

maintenance work on line for DCS. A platform supported by IAEA to do

the in-depth engineering analysis on the feasibility and technical

constrains is appreciated, in order to establish the specification to the

engineering of signal distribution and power supply, and the

requirement to the manufacturing on modules, wirings, switches, heat

dispersion component.

Issues & Topics – Utilities

Page 27: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

27

Issues and Topics by utilities : (Cont.)•Practices on DCS FAT, installation, commissiong and SAT

All the new built NPPs in China will be installed with digital control

system, for which DCS system FAT, site installation, commissioning

and SAT will take place in 2011 to 2014. Workshop in 2010 sponsored

by IAEA on best practices in those areas would be appreciated.

•I&C aging management

IAEA to provide technical support and guidance on I&C aging

management in the operating plant, with respect to techniques and

methods of mechanism analysis, monitoring, screening out and

counter measures.

Issues & Topics – Utilities

Page 28: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

28

Issues and Topics by utilities : (Cont.)•NPP suppliers list and Technicians & experts list

The facts that the original I&C were supplied by foreign

manufactures who may be no longer maintaining the production of the

outdated component, or may have been bankrupted and no longer

exist, have caused difficulties for operating plant to have long term,

stable and in time spare parts supply.

IAEA is recommended to generate an updated manufactures list

by product or system, which shares the information of companies who

have ever been or are being NPP suppliers, and to collect and

establish a global I&C technicians and experts contact list together with

the brief introduction of their organization and products or systems

being used for communication and information exchange.

Issues & Topics – Utilities

Page 29: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

29

Experts & Contributors

Special Thanks to the Experts & Contributors:China Nuclear Power Engineering Co. Ltd.

• Mr. Lv Dongbao, Deputy Chief Engineer, [email protected]

• Ms. Zhang Li, General Design Division, [email protected] Nuclear Power Design Co. Ltd.

• Mr. Sun Yongbin, Director I&C Dept., [email protected] Nuclear Power Co. Ltd.

• Mr. Fang Jintu, Equipment Management Dept., [email protected]

• Mr. Tian Lu, Engineering Design Management Dept., [email protected]

• Mr. Pu Xiaobin, Planning Dept., [email protected] Power Qinshan Joint Venture Co. Ltd.

• Mr. Dong Juncheng, Maintenance Dept, [email protected] Qinshan Nuclear Power Co. Ltd.

• Mr. Hong Tan, Maintenance Dept., [email protected]

Page 30: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

30

Experts & Contributors

Special Thanks to the Experts & Contributors: (Cont.)China Nuclear Control System Engineering Co., Ltd.

• Mr. Tang Yi, President, [email protected] Techenergy Co. Ltd.

• Mr. Hao Zhijian, President, [email protected]

• Mr. Zhu Yiming, [email protected] Nuclear Power Automation System Engineering Corp.

• Mr. Qiu Shaoyang, President, [email protected]

• Mr. Zenghai, Chief Engineer, [email protected] of Nuclear Energy Technology(INET), Tsinghua University

• Mr. Zhang Liangju, I&C division, [email protected]

Page 31: 1 China country report on I&C status and recommendations to IAEA Jiang Hong The 22nd Meeting of the IAEA TWG – NPPIC on May 20-22, 2009, Austria Center

31

Thank you

for your attention