1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

Upload: douglas-pitts

Post on 18-Jan-2018

219 views

Category:

Documents


0 download

DESCRIPTION

3 BROOKHAVEN SCIENCE ASSOCIATES Magnet Girder Integration

TRANSCRIPT

Page 1: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

1 BROOKHAVEN SCIENCE ASSOCIATES

Accelerator Systems Installation

F. Willeke, ASD Director6th ASAC

October 22-23, 2009

Page 2: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• Magnet Girder Integration• Installation Preparation• Installation Schedule• Installation Resource Planning• Installation Overview• Availability of Buildings• Girder Installation Details• Storage Ring Installation Logistics

Page 3: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

3 BROOKHAVEN SCIENCE ASSOCIATES

Magnet Girder Integration

Page 4: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

4 BROOKHAVEN SCIENCE ASSOCIATES

Girder Integration Workflow

2 Girders /months 2 girders / week

@ 18 months (incl. learning curve effect)

Starting 04-Aug-1 Finish 13-Jan-12

High precision Alignment

Preassembly

2 days

90 MP Girders, 60 Dipole Girders

Page 5: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

5 BROOKHAVEN SCIENCE ASSOCIATES

Database Entries in Support of Installation

Quadrupole magnet

Configuration type “D”

Specification (9809)

Girder 2, Cell 1

30.25 meters from ID center

De-focussing Quad

Magnet A terminal to supply Negative terminal

Magnet B terminal to supply Positive terminal

Power supply spec type “B”, 175 Amp

252 kcmil wire required

Located in mezzanine Cell 1 rack A1

19 RU from bottom of rack

Powers magnet QL1 in cell 1

Comprehensive Information on all subsystems and their relations including connecting cables will support installation

Page 6: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

6 BROOKHAVEN SCIENCE ASSOCIATES

Storage Ring Magnet Conventions

Example: Wiring details for Quad QL1G2C01A

• Wire type : 252 kcmil, 175 amps max 138 amps nominal• Wire starts in tunnel : 30.25 meters from Long ID center Cell 1• Wire ends in mezzanine : Cell 01 Rack A1 Height from bottom 19 RU• Connected as a de-focus quad:

• A terminal to supply negative terminal• B terminal to supply positive terminal

• Wire marking: load / source• QL1G2C01A-A / SR-PS-QBL1-C01-A1 NEG for negative voltage conductor• QL1G2C01A-B / SR-PS-QBL1-C01-A1 POS for positive voltage conductor

• Testing of wiring via traveller (QA documentation requirements)• Hipot to 2Kv prior to connection to magnet• Continuity check for wire polarity• Electrical check for magnet polarity

Page 7: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

7 BROOKHAVEN SCIENCE ASSOCIATES

Storage Ring Electrical Utilities: Detailed Planning

Racks will be equipped on the Mezzanine

Page 8: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

8 BROOKHAVEN SCIENCE ASSOCIATES

Civil Construction Sequence

Page 9: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

9 BROOKHAVEN SCIENCE ASSOCIATES

Installation Overview

Building BOD Installation Activity Start DatePentant 1*) 1-Feb-11 SR Components 20-Jun-11

Pentant 1 1-Feb-11 SC RF Cavities 21-Sep-12

RF Bld 23-May-11 RF Power Systems & Cryog’s 29-Mar-12

Inj. Bld 18-May-11 Booster RF Cavity 21-Jun-11

Inj. Bld 18-May-11 LINAC 18-Oct-11

Inj. Bld 18-May-11 Booster 08-Jun-12

Pentant 2 02-May-Jun SR Components 20-Oct-11

Pentant 3 27-Sep-11 SR Components 14-Feb-12

Pentant4 28-Nov-11 SR Components 16-Apr-12

Pentant 5 09-Feb-12 SR Components 28-Jun-12

*) includes central cooling tower building and access tunnels

Page 10: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

10 BROOKHAVEN SCIENCE ASSOCIATES

Installation Overall Plan

• LINAC Installation: responsibility and work by vendor

• Booster Installation: responsibility of the vendor, but BNL will provide experienced and trained installation and rigging staff under a BNL installation supervisor

• Storage Ring Installation: Carried out by AS staff and

BNL rigging crews, 50% will be temporary labor

Page 11: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

11 BROOKHAVEN SCIENCE ASSOCIATES

Page 12: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

12 BROOKHAVEN SCIENCE ASSOCIATES

Planned Resources

50 FTE planned this needs reassessment

Page 13: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

13 BROOKHAVEN SCIENCE ASSOCIATES

Even Cell Girders

G3 G5 G6G2 G4

G1

Black border indicates an even cell

ID Section

Page 14: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

14 BROOKHAVEN SCIENCE ASSOCIATES

Odd Cell Girders

G1

G3 G5 G6G2 G4

ID Section

Water manifolds are shown schematically as

a double red line (Aluminum)

a double green line (Copper)

Red border indicates an odd cell

Page 15: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

15 BROOKHAVEN SCIENCE ASSOCIATES

Typical cell rack groups

BlueBlue border indicates a rack group 22, 33, or 44 racks wide

Cable tray is shown schematically as a double dashed line

G3 G5 G6G2 G4

Page 16: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

16 BROOKHAVEN SCIENCE ASSOCIATES

The first slice; Pentant 1 plus…

Page 17: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

17 BROOKHAVEN SCIENCE ASSOCIATES

Dolly assembly is removed from girder with air casters inflated

Blocks are positioned at sides of floor mounting plates

Note: Threaded support shafts and hardware will not be installed at this stage

Installation of Magnet Girders

Page 18: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

18 BROOKHAVEN SCIENCE ASSOCIATES

Girder Transport in the Tunnel

Used for RHIC

New models

Page 19: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

19 BROOKHAVEN SCIENCE ASSOCIATES

“Stearman” Type Dolly system components

The dolly system includes “Stearman” Dolly components rated at 9000# and 13,500#

Expected girder weight is 17,000#

MODEL ST-8MAXIMUM LOAD CAPACITY: 13,500 LBS. (SAFETY FACTOR = 1.5)

Number of Wheels Weight Height Width Depth

Swivel Pad Diameter

Distance from center of swivel pad to handle

Handle Length

Roller Dimensions

8 91 lbs. 4.25" 23.5" 19.5" 6.625" 12" 45" 3.25" x 3.25"

MODEL RT-3MAXIMUM LOAD CAPACITY: 4,500 LBS. (SAFETY FACTOR = 1.5)

Number of Wheels Total Weight Height Width Pad Diameter Roller Dimensions

3 73 lbs. 4.25" 18" 6.625" 3.25" x 3.25"

Page 20: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

20 BROOKHAVEN SCIENCE ASSOCIATES

Pentant 1 installation Zones

24 25 27 2823

Experimental floor

Tunnel

24 25 26 2722

Mezzanine

23

26

Service Building

Page 21: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

21 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

~ 1/3 of material in building

Installation starting

26

2

Activities:

•Prepare tunnel

•Stage components on floor

•Start cable tray on mezzanine

Page 22: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

22 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

Most material in building

Installation on mezzanine

Begin in tunnel

26

4

Activities:

•Stage components on floor

•Start racks on mezzanine

Page 23: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

23 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

Most material in building

Installation on mezzanine

Installation in tunnel

26

6

Activities:

•Tray and manifolds in place in tunnel

•Racks well underway

•Stage cable and start pulling

Page 24: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

24 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

Multipole girder installation

26

8

Activities:

•Begin Girder installation

•Start populating racks

•Begin Utility installation in SB

Page 25: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

25 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

Half way in schedule

26

10

Activities:

•Girder installation

•Populating racks

•Utility installation in SB

Page 26: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

26 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

Most wiring pulled

Process utilities connected

26

12

Activities:

•Girder installation

•Populating racks

•Terminating cables

Page 27: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

27 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

About ¾ through schedule

26

14

Activities:

•Girder installation

•Racks populated

•Terminating cables

Page 28: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

28 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

About ½ vacuum complete

26

16

Activities:

•Girder installation

•Cable pulls all done

•Testing underway

Page 29: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

29 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

About 2/3 vacuum complete

26

18

Activities:

•Girder installation

•Cable pulls all done

•Testing underway

Page 30: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

30 BROOKHAVEN SCIENCE ASSOCIATES

Storage ring Pentant 1 installation: Week

24 25 27 2823

Exp’l floor

Tunnel

Service Building

24 25 26 2722

Mezzanine

23

Status:

All equipment in place

System testing underway

26

20

Activities:

•final utility connections

•equipment shakeout

Page 31: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

31 BROOKHAVEN SCIENCE ASSOCIATES

Page 32: 1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009

32 BROOKHAVEN SCIENCE ASSOCIATES

Conclusion

• Magnet Girder Integration re-planned: is the backbone for the installation activity

• Installation of utilities on the mezzanine and cabling well planned making use of the equipment relational data base

• Installation schedule has recently been re-optimized and aligned with building schedule

• Resource for installation still need to be revised and optimized, concern is large number of temporary staff (~30)

• Installation logistics, intermediate storage and space management well advanced

• Conclusion: Installation Planning is very advanced