BASIC CONCRETE PRINCIPLES

ESTIMATING THE MATERIALS NEEDED FOR CONCRETE

#8604A

Page 2: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

2

FOUR RULES FOR A QUALITY PRODUCT

• Use proper ingredients

• Correctly proportion & measure ingredients

• Thoroughly mix the ingredients

• Properly finish and cure the poured concrete

Page 3: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

3

ADVANTAGES OF USING CONCRETE

• Fire proof• Durable and permanent• Watertight• Economical• Sanitary• Low maintenance• Attractive• Termite & rodent proof• Storm resistant• Can be “homemade”

Page 4: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

4

AGRICULTURAL USES

• Fence posts• Driveways• Walls & foundations• Septic tanks• Walks• Water troughs• Feeding floors• Steps• Cattle guards• etc

Page 5: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

5

COMPOSITION OF CONCRETE

• Portland cement• Water• Aggregates (sand and

gravel)

Page 6: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

6

WHAT IS PORTLAND CEMENT

• Manufactured from lime, iron oxide, silica, and alumna.

• It is mixed in proper proportion and heated in a kiln to approximately 3000 degrees F.

• Resulting material is called clinker• Clinker is than pulverized and mixed with

gypsum into a fine powder.

Page 7: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

7

ORIGIN OF PORTLAND CEMENT

• Joseph Aspdin, in the early 19th century and the founder of the process that is still used today used the term because the cement he produced was the color of stone taken from the quarries on the island of Portland off the coast of England.

• Portland cement is packaged in sacks containing 1 cubic foot which weighs 94 lbs.

Page 8: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

8

AGGREGATES

• Basic filler of sand, crushed stone, & gravel

• Sand is a fine aggregate less than ¼ inch.• Gravel is a coarse aggregate more than ¼

inch.• Coarse aggregate add strength.• Aggregates are cheaper than cement and

considered a cost reducing material.

Page 9: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

9

WATER

• Should be clean and free from impurities.

• Impurities affects strength, coloration, corrosion of reinforcement steel and wire.

• It also affect setting time

• When all ingredients are properly mixed, the combined weight of a one cubic foot of concrete is 150-160 lbs.

Page 10: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

10

QUALITY OF CONCRETE

• Consistency or slump refers to the “wetness” or “dryness of the mix.

• Excessive slump can be corrected by the addition of aggregate.

• Plastic consistency is the best.

• Never exceed 6 inches of slump

Page 11: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

11

CONCRETE SLUMP RANGES

• Reinforced foundation walls –Min 2” Max 4”• Reinforced slabs, beams -Min 5” Max 2”• Building columns -Min 5” Max 3”• Pavements -Min 2” Max 1”• Sidewalks, driveways -Min 4” Max 2”

Page 12: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

12

UNIFORMITY & WORKABILITY

• Uniformity refers to the thorough mixing of all ingredients

• Workability refers to the ease which concrete can be placed and shaped.

Page 13: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

13

QUALITIES OF HARDENED CONCRETE

• Durability refers to resistance to chemical actions, freezing, and thawing. Good workmanship and proper mixing improves durability.

• Strength is measured as compressive and tensile. Compressive strength is usually 10 times the tensile strength of unreinforced concrete. Additional reinforcement will equalize the strength.

Page 14: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

14

Other Conditions

• Water-cement ratio, curing time, & curing methods are just as important as reinforcement.

• Rule of thumb: Use a 5-7 gallons of water per sack of cement. Exceeding this will weaken the mix.

• Concrete cured for 7 days is only 2/3 as strong as concrete cured for 28 days.

• Damp curing can increase as much as 50% for the first 7 days.

Page 15: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

15

WATERTIGHTNESS

• The ability to prevent water passage through the mass. The water-cement ratio and curing time affect watertightness.

• Less water in the mix increases watertightness.

Page 16: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

16

WEAR RESISTANCE

• The ability to resist abrasive action of vehicles, feet, flowing water, etc.

• Aggregates should be hard and tough to resist wear.

Page 17: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

17

READY MIXED CONCRETE

• Sold by cubic yard

• Two methods of mixing—transit mixer & shrink-mixed

• Transit mixer is when mixing is done on the truck

• Shrink-mixed begins in a stationary mixer and ends up in a truck mixer.

Page 18: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

18

ADVANTAGES OF READY-MIX

• Thoroughly mixed

• Ingredients are not handled on the job site.

• Less labor is required.

• Exact quantity needed can be ordered.

• Actual price can be calculated easily.

Page 19: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

19

ADMIXTURES

• Air-entraining –hundreds of microscopic air cell are dispersed in the mix to protect during freezing and thawing actions.

• Water-reducing –increases strength.• Retarding –slows down the setting time during

high temperature.• Accelerating –calcium chloride is added to mix to

shortened the set up time.• Pozzolans –controls expansion during heat.

Page 20: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

20

ESTIMATING READY-MIX CONCRETE

• Allows a 10% waste.

• When ordering mixtures by numbers: a 6-6-6 stands for 6 sacks of cement per cubic yard, 6 gallons of water per sack of cement, and 6 % entrained air.

• To determine surface area (length x width)

Page 21: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

21

CALCULATING READY-MIX CONRETE

• Determine surface area.• Determine the concrete thickness• Refer to chart to determine the number of cubic yards

of concrete needed.• Concrete thickness Divide Area by:

1 inch 3003 inches 1004 inches 756 inches 50

12 inches 25

Page 22: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

22

RECOMMENDED MIXES

• 5-Gallon mix –for acid or alkaline resistant walks, fence posts, flower boxes, & etc.

• 6-Gallon mix –for watertight floors, tanks, walls and all reinforced concrete.

• 7-Gallon mix –for foundation walls, retaining walls, underground concrete and concrete not under water pressure.

Page 23: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

23

MOISTURE IN SAND

• Damp sand – ¼ gal/cu.ft (falls apart when hand is opened.)

• Wet sand – ½ gal/cu.ft (ball of sand holds shape when hand is opened.)

• Very wet sand – (3/4 gal/cu.ft (ball is formed and leaves hand wet when opened.

Page 24: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

24

“FULLER’S” RULE

• Rule states – mixing of a total of 42 volumes of cement, sand, and gravel will produce 27 volumes of concrete.

Page 25: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

25

FULLER’S RULE

• Use a 1 – 2-1/4 – 3 mix to build 4”thick, 6’ wide, and 100’ long sidewalk.

– Determine the amount of concrete required.

6’ x 100’ x 4” or 6’ x 100’ x 1/3’ 12 1 =200 cubic feet of concrete

Page 26: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

26

FULLER’S RULE

• Determine the amount of raw materials needed.

200 X 42 =

27

311 cu ft of raw materials

Page 27: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

27

FULLER’S RULE

• Determine the volume of mix needed.

1 + 2-1/4 + 3 = 6-1/4 (6.25) volumes of mix

Page 28: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

28

FULLER’S RULE

• Determine the sacks of cement needed.

311 cuft. raw materials = 49.76 sacks

6.25 volume of mix

Page 29: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

29

FULLER’S RULE

• Determine the cu. yds. of sand needed.

50 sacks x 2.25 = 4.17 cu yds of sand

27 cu.ft/yd

Page 30: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

30

FULLER’S RULE

• Determine the cu yds. Of gravel needed.

50 sacks x 3 = 5.55 cu yds of gravel

27 cu ft/yd

Page 31: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

31

FULLER’S RULE SUMMARY

• 1. 200 cu feet of concrete required

• 2. 311 cu ft of raw materials

• 3. 6-1/4 or 6.25 volumes of mix

• 4. 49.76 or 50 sacks of cement

• 5. 4.17 cu yds of sand

• 6. 5.55 cu yds of gravel

Page 32: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

32

MIXING CONCRETE

• Two common methods of mixing – machine and hand mixing.

• Steps in machine mixing

-add 10% water before adding in solids.

-add portion of gravel.

-add measured amount of cement

-add sand and remaining amts of gravel

-mix from 1 – 3 minutes

Page 33: 1 BASIC CONCRETE PRINCIPLES ESTIMATING THE MATERIALS NEEDED FOR CONCRETE #8604A

33

MIXING CONCRETE

• Steps in hand mixing

-place sand in mixing container

-then add cement and mix thoroughly

-add gravel and continue to mix

-add measured amounts of water

-mix thoroughly