1-1
1
Chapter 3
Project Management
![Page 2: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/2.jpg)
1-2
2
A Project is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform
Project Management is the management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project
Project Management Defined
![Page 3: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/3.jpg)
1-3
3
Gantt Chart
Activity 1Activity 2Activity 3Activity 4Activity 5Activity 6
Time
Vertical Axis: Always Activities or Jobs
Vertical Axis: Always Activities or Jobs
Horizontal Axis: Always TimeHorizontal Axis: Always Time
Horizontal bars used to denote length of time for each activity or job.
Horizontal bars used to denote length of time for each activity or job.
![Page 4: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/4.jpg)
1-4
4
Structuring Projects Pure Project: Advantages
Pure Project
A pure project is where a self-contained team works full-time on the project
• The project manager has full authority over the project
• Team members report to one boss• Shortened communication lines• Team pride, motivation, and commitment
are high
![Page 5: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/5.jpg)
1-5
5
Structuring Projects Pure Project: Disadvantages
• Duplication of resources• Organizational goals and policies
are ignored• Lack of technology transfer• Team members have no functional
area "home"
![Page 6: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/6.jpg)
1-6
6
Functional Project
President
Research andDevelopment
Engineering Manufacturing
ProjectA
ProjectB
ProjectC
ProjectD
ProjectE
ProjectF
ProjectG
ProjectH
ProjectI
A functional project is housed within a functional division
Example, Project “B” is in the functional area of Research and Development.
Example, Project “B” is in the functional area of Research and Development.
![Page 7: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/7.jpg)
1-7
7
Structuring Projects Functional Project: Advantages
• A team member can work on several projects
• Technical expertise is maintained within the functional area
• The functional area is a “home” after the project is completed
• Critical mass of specialized knowledge
![Page 8: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/8.jpg)
1-8
8
Structuring Projects Functional Project: Disadvantages
• Aspects of the project that are not directly related to the functional area get short-changed
• Motivation of team members is often weak
• Needs of the client are secondary and are responded to slowly
![Page 9: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/9.jpg)
1-9
9
Matrix Project Organization Structure
President
Research andDevelopment
Engineering Manufacturing Marketing
ManagerProject A
ManagerProject B
ManagerProject C
![Page 10: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/10.jpg)
1-10
10
Structuring Projects Matrix: Advantages
• Enhanced communications between functional areas
• Pinpointed responsibility
• Duplication of resources is minimized
• Functional “home” for team members
• Policies of the parent organization are followed
![Page 11: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/11.jpg)
1-11
11
Structuring Projects Matrix: Disadvantages
• Too many bosses
• Depends on project manager’s negotiating skills
• Potential for sub-optimization
![Page 12: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/12.jpg)
1-12
12
Work Breakdown Structure
Program
Project 1 Project 2
Task 1.1
Subtask 1.1.1
Work Package 1.1.1.1
Level
1
2
3
4
Task 1.2
Subtask 1.1.2
Work Package 1.1.1.2
A work breakdown structure defines the hierarchy of project tasks, subtasks, and work packages
![Page 13: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/13.jpg)
1-13
13
Network-Planning Models
• A project is made up of a sequence of activities that form a network representing a project
• The path taking longest time through this network of activities is called the “critical path”
• The critical path provides a wide range of scheduling information useful in managing a project
• Critical Path Method (CPM) helps to identify the critical path(s) in the project networks
![Page 14: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/14.jpg)
1-14
14
Prerequisites for Critical Path Methodology
A project must have:
well-defined jobs or tasks whose completion marks the end of the project;
independent jobs or tasks;
and tasks that follow a given sequence.
![Page 15: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/15.jpg)
1-15
15
Steps in the CPM with Single Time Estimate
• 1. Activity Identification
• 2. Activity Sequencing and Network Construction
• 3. Determine the critical path– From the critical path all of the
project and activity timing information can be obtained
![Page 16: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/16.jpg)
1-16
16
CPM with Single Time Estimate
Consider the following consulting project:
Activity Designation Immed. Pred. Time (Weeks)Assess customer's needs A None 2Write and submit proposal B A 1Obtain approval C B 1Develop service vision and goals D C 2Train employees E C 5Quality improvement pilot groups F D, E 5Write assessment report G F 1
Develop a critical path diagram and determine the duration of the critical path and slack times for all activities.
![Page 17: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/17.jpg)
1-17
17
First draw the network
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
Act. Imed. Pred. Time
![Page 18: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/18.jpg)
1-18
18
Sensitivity Analysis
• What if something goes wrong?
• Can you still be able to finish the project as planned?
![Page 19: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/19.jpg)
1-19
19
Example 2. CPM with Three Activity Time Estimates
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
![Page 20: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/20.jpg)
1-20
20
Example 2. Expected Time Calculations
ET(A)= 3+4(6)+15
6
ET(A)= 3+4(6)+15
6
ET(A)=42/6=7ET(A)=42/6=7Task
Immediate Predecesors
Expected Time
A None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
Expected Time = Opt. Time + 4(Most Likely Time) + Pess. Time
6Expected Time =
Opt. Time + 4(Most Likely Time) + Pess. Time
6
![Page 21: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/21.jpg)
1-21
21
Example 2. Network
A(7)
B(5.333)
C(14)
D(5)
E(11)
F(7)
H(4)
G(11)
I(18)
Duration = 54 Days
![Page 22: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/22.jpg)
1-22
22
Activity variance, = (Pessim. - Optim.
6)2 2Activity variance, = (
Pessim. - Optim.
6)2 2
Task Optimistic Most Likely Pessimistic VarianceA 3 6 15 4B 2 4 14C 6 12 30 16D 2 5 8E 5 11 17 4F 3 6 15G 3 9 27H 1 4 7 1I 4 19 28 16
(Sum the variance along the critical path.)
2 = 41 2 = 41
![Page 23: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/23.jpg)
1-23
23
Example 2. Probability Exercise
What is the probability of finishing this project in less than 53 days?
What is the probability of finishing this project in less than 53 days?
p(t < D)
TE = 54
Z = D - TE
cp2
Z = D - TE
cp2
tD=53
![Page 24: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/24.jpg)
1-24
24
Example 2. Additional Exercise Solution
tTE = 54
p(t < D)
D=56
![Page 25: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/25.jpg)
1-25
25
Time-Cost Trade-offs
-Activity crashing: reduce activity
times to complete a project earlier (at
a cost, of course)
-To reduce project completion time:
• Focus on the critical activities!!
• Be careful!! When you reduce the critical
path, it may no longer be the critical path
anymore. Check it again!!
![Page 26: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/26.jpg)
1-26
26
Crashing Example
A7
B6
C4
D8
E10
![Page 27: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/27.jpg)
1-27
27
Crashing example
• Q: By how many days can I expedite this project if I had a budget of $24?
Activity Avg. Time
Crash time
Normal cost
Crash cost
Cost per day to expedite
# of days an
activity may be
shortened
A 7 5 $70 100 (100-70)/2=15 2
B 6 3 60 80 (80-60)/3=6.67 3
C 4 2 40 60 (60-40)/2=10 2
D 8 6 80 120 (120-80)/2=20 2
E 10 7 10 40 (40-19)/3=10 3
![Page 28: 1-1 1 Chapter 3 Project Management. 1-2 2 A Project is a series of related jobs usually directed toward some major output and requiring a significant](https://reader030.vdocuments.us/reader030/viewer/2022032803/56649e2f5503460f94b201b9/html5/thumbnails/28.jpg)
1-28McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved
28
Project completion
time
Critical path
Cost of expediting
Least expensive
activity
Cost of LEA