09/07/2002 1 Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans M3R1 (CERN) M3R2 (CERN) M3R4 (PNPI) Tooling status and plans Wiring machine Glueing station Wire pitch measurement Wire tension measurement Soldering station Production areas at CERN and PNPI are in a well advanced state

Upload: christina-bates

Post on 17-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 1Muon Meeting

Status of MWPC activities at CERN and PNPI

Outline:• Module 0 status and plans

– M3R1 (CERN)– M3R2 (CERN)– M3R4 (PNPI)

• Tooling status and plans– Wiring machine– Glueing station– Wire pitch measurement– Wire tension measurement– Soldering station

• Production areas at CERN and PNPI are in a well advanced state

Page 2: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 2Muon Meeting

M3R1 chamberStatus:• Design finished (Thomas Schneider)• Material preparation (PCBs) ongoing• Construction planned for August• Testing begin September (?) or October

->Unfortunately chamber is not really a module 0 due to pending problems, in particular on chamber closing.

->As we want to be able to reopen, there is no simple alternative to the O-ring, due to many connectors and the small gaps (otherwise we might have switched already to an alterntive solution. . . )

-> Chamber will be still made with honeycomb panels (of 10mm total thickness), due to alignment issues to be sorted out, a tight schedule and difficulties to get foam panels done in Italy in August.

->We are considering to put the loading resistors into the gas gap (suggestion of Seva).

Page 3: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 3Muon Meeting

M3R1 chamber

Page 4: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 4Muon Meeting

M3R1 chamber

Page 5: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 5Muon Meeting

M3 R2 and R4 chambersStatus M3 R2:• Design of M3R2 chamber planned for August• Material preparation and construction in September• Test in October

Status M3 R4 (tbc by Alexei): • Design done by A.Saputi / B.Botchine• Material preparation done by LNF group• Construction planned at CERN in September (Tooling for PNPI -in

preparation at CERN- should be used)• Test in October

->Schedule for both chambers is tough, we have to push

Page 6: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 6Muon Meeting

Status of Tooling Preparation

Wiring machine:• Wiring machine for PNPI under construction at CERN

(Raphael+PNPI technicians), following closely the design of the CERN wiring machine.

Page 7: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 7Muon Meeting

Wiring Machine (ctd)

Modifications:• Have both belts on the same side

(simpler transmission)• Introduce electromagnetic clutch to

facilitate start of the wiring process• To be decided still:

Implement tension measurement? Torque motor has still to be ordered

-> Be ready end of August

Page 8: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 8Muon Meeting

Glueing Tables

Status: • First glueing table has been finalized• Need to decide on exact positions of spacers for

glueing frames of Module 0

Page 9: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 9Muon Meeting

Page 10: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 10Muon Meeting

Wire pitch measurement

Status:• Hardware for first station ready (Michał, Raphael)• Software (LabView)

well advanced, should be ready this week

(Rebeca (SS)).

Page 11: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 11Muon Meeting

Wire tension measurementAcknowledgement:• Visit of A. Nedosekin in May was very useful to understand hardware and software of

the KLOE/ATLAS WTM-system !

Status:• 16-channel system could be purchased via LNF, but contains obsolete components (long

delivery time) and it is rather expensive (~10kCHF).• We investigated about adaptation of the system to up-to-date hardware (NI-DAQ 6602). ->First tests show that it is feasible (Michał and Anatoli)

DAQ-cardTTL-disc.LC-generatorHV-modulator

HV-PS Wire Chamber

Page 12: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 12Muon Meeting

Wire tension measurementPlan: • Use 2 NI-DAQ 6602 cards (8 channels each).

– 1 channel will be pulse generator (to scan frequencies around resonance) – 1 channel will be used for gate generation (to define measurement cycle)

-> 14 channels left for measurement• Each DAQ-card will have adapter card with TTL discriminators and

switch• A mother board with HV-modulator and LC-Generators (from LNF)

will be prepared->Prototypes and schematics done by Anatoli, layout will be done this

week by Giacomo Chiodi• Use external HV power supply (400 V)-> Software adaptation done by Michał and Rebeca

->6 (14) channel system is hopefully functional by mid August

Page 13: 09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status

09/07/2002 13Muon Meeting

Soldering Station

Plan: • Follow as closely as possible LNF station, and adapt it

to the multipurpose scanning table• 2 heads are planned for PNPI table, 1 for CERN table

(small chambers)-> Setting up planned for September/October