09/07/20021muon meeting status of mwpc activities at cern and pnpi outline: module 0 status and...
TRANSCRIPT
09/07/2002 1Muon Meeting
Status of MWPC activities at CERN and PNPI
Outline:• Module 0 status and plans
– M3R1 (CERN)– M3R2 (CERN)– M3R4 (PNPI)
• Tooling status and plans– Wiring machine– Glueing station– Wire pitch measurement– Wire tension measurement– Soldering station
• Production areas at CERN and PNPI are in a well advanced state
09/07/2002 2Muon Meeting
M3R1 chamberStatus:• Design finished (Thomas Schneider)• Material preparation (PCBs) ongoing• Construction planned for August• Testing begin September (?) or October
->Unfortunately chamber is not really a module 0 due to pending problems, in particular on chamber closing.
->As we want to be able to reopen, there is no simple alternative to the O-ring, due to many connectors and the small gaps (otherwise we might have switched already to an alterntive solution. . . )
-> Chamber will be still made with honeycomb panels (of 10mm total thickness), due to alignment issues to be sorted out, a tight schedule and difficulties to get foam panels done in Italy in August.
->We are considering to put the loading resistors into the gas gap (suggestion of Seva).
09/07/2002 3Muon Meeting
M3R1 chamber
09/07/2002 4Muon Meeting
M3R1 chamber
09/07/2002 5Muon Meeting
M3 R2 and R4 chambersStatus M3 R2:• Design of M3R2 chamber planned for August• Material preparation and construction in September• Test in October
Status M3 R4 (tbc by Alexei): • Design done by A.Saputi / B.Botchine• Material preparation done by LNF group• Construction planned at CERN in September (Tooling for PNPI -in
preparation at CERN- should be used)• Test in October
->Schedule for both chambers is tough, we have to push
09/07/2002 6Muon Meeting
Status of Tooling Preparation
Wiring machine:• Wiring machine for PNPI under construction at CERN
(Raphael+PNPI technicians), following closely the design of the CERN wiring machine.
09/07/2002 7Muon Meeting
Wiring Machine (ctd)
Modifications:• Have both belts on the same side
(simpler transmission)• Introduce electromagnetic clutch to
facilitate start of the wiring process• To be decided still:
Implement tension measurement? Torque motor has still to be ordered
-> Be ready end of August
09/07/2002 8Muon Meeting
Glueing Tables
Status: • First glueing table has been finalized• Need to decide on exact positions of spacers for
glueing frames of Module 0
09/07/2002 9Muon Meeting
09/07/2002 10Muon Meeting
Wire pitch measurement
Status:• Hardware for first station ready (Michał, Raphael)• Software (LabView)
well advanced, should be ready this week
(Rebeca (SS)).
09/07/2002 11Muon Meeting
Wire tension measurementAcknowledgement:• Visit of A. Nedosekin in May was very useful to understand hardware and software of
the KLOE/ATLAS WTM-system !
Status:• 16-channel system could be purchased via LNF, but contains obsolete components (long
delivery time) and it is rather expensive (~10kCHF).• We investigated about adaptation of the system to up-to-date hardware (NI-DAQ 6602). ->First tests show that it is feasible (Michał and Anatoli)
DAQ-cardTTL-disc.LC-generatorHV-modulator
HV-PS Wire Chamber
09/07/2002 12Muon Meeting
Wire tension measurementPlan: • Use 2 NI-DAQ 6602 cards (8 channels each).
– 1 channel will be pulse generator (to scan frequencies around resonance) – 1 channel will be used for gate generation (to define measurement cycle)
-> 14 channels left for measurement• Each DAQ-card will have adapter card with TTL discriminators and
switch• A mother board with HV-modulator and LC-Generators (from LNF)
will be prepared->Prototypes and schematics done by Anatoli, layout will be done this
week by Giacomo Chiodi• Use external HV power supply (400 V)-> Software adaptation done by Michał and Rebeca
->6 (14) channel system is hopefully functional by mid August
09/07/2002 13Muon Meeting
Soldering Station
Plan: • Follow as closely as possible LNF station, and adapt it
to the multipurpose scanning table• 2 heads are planned for PNPI table, 1 for CERN table
(small chambers)-> Setting up planned for September/October