09 risk management plan

Upload: shannon-macdonald

Post on 08-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 09 Risk Management Plan

    1/6

    9. Risk Management Plan

    9.1 Methodology

    For the initial risk assessment, the project manager and the team havebrainstormed and collaborated in identifying all possible risks within the current

    known elements of the project. These identified risks will be reviewed in the

    presence of Dr. Lipsett and Roger Marchand as early as their schedules allow

    the review.

    To ensure that the risk environment is being assessed sufficiently, Dr. Lipsett

    will act as the risk management expert. Other risk-related inquiries will also be

    made to the laboratory equipment experts (Roger Marchand and his team).

    The following risk management process (described in Figure #) will be

    implemented throughout the duration of the project. If any changes are made to

    the project plan during the execution phase of the project, a risk assessment will

    be carried out to determine if any new risks are present.

    Figure # - The Risk Management Process

  • 8/7/2019 09 Risk Management Plan

    2/6

    Doing Planned Reviews: Risk reviews will take place during weekly meetings to

    discuss the current state of risks within the project.

    Identification of Hazards: Throughout the project lifetime, new processes and

    actions may be implemented that pose new risks which had not been identified

    in earlier planning stages. During the planned reviews, these risks will be

    identified. (See Section 9.1.1 for further details)

    Risk Assessment/Analysis: A risk assessment/analysis will be carried out for

    any new identified risks. (See Sections 9.1.2 to 9.1.4 for analyses)

    Is the Risk Acceptable?: Risks are deemed acceptable only once they have

    been rated using a risk matrix (see Sections 9.1.2.1 and 9.1.2.2). Low level

    risks are acceptable, without any further management involvement. Mediumlevel risks are acceptable with certain conditions. These risks must be closely

    monitored, and the project manager must be present to ensure the risk is kept

    under control. High level risks are unacceptable and any actions producing

    such risks will be halted immediately.

    Manage the Residual Risk: Once a risk is determined to be acceptable, it must

    be managed in the way that is most appropriate for that risk. Methods for

    managing each risk will be discussed by the project manager, the team, and the

    Dr. Lipsett. (See Section 9.1.4 for further details)

    Can the Risk be Reduced?: Further controls, management systems, protective

    features, etc. may be added to reduce risks to an acceptable level. (See Section

    9.1.4 for further details)

    Reduce the Risk: If the risk can be reduced, the necessary changes must be

    implemented to decrease it (see Section 9.1.4). It is important to note that if a

    change is made to reduce the risk present in a process or action, a full risk

    analysis must be redone on the newly implemented process or action. This will

    reveal possible new risks that may have been added to the project. (See

    Sections 9.1.1 to 9.1.4)

    Discontinue the Activity: If a risk has been identified as unacceptable, any

    processes or actions that pose that risk will be stopped. This is important to

    protect all people involved in the project, people of the community, personal and

  • 8/7/2019 09 Risk Management Plan

    3/6

    university assets, as well as the sustainability of Chrome Engineering as an

    enterprise with favourable public opinion.

    9.1.1 Risk Identification

    9.1.1.1 Documentation Review

    Risks have been identified by the project manager and the team by

    first reviewing the following project documentation:

    1) Activity cost estimates

    2) Activity duration estimates

    3) Scope baseline

    4) Stakeholder register

    5) Cost management plan6) Schedule management plan

    7) Quality management plan

    8) Project documents

    9) Enterprise environmental factors

    10) Organizational process assets

    9.1.1.2 Tools & Techniques

    Brainstorming: At weekly meetings, the team has undergone a

    brainstorming session to assess the possibility of risks that wereoverlooked earlier in the project Planning Phase. As well, origins of

    new risks have been considered as any changes to the project plan

    have been made.

    Interviewing: Aside from the project team members, Dr. Lipsett has

    been interviewed on his perception of possible risks.

    Checklist Analysis: A checklist for the duration of the Execution

    Process has been created to ensure essential safety and risk

    management processes are not overlooked. Refer to the Laboratory

    Relocation Safety Checklist in Appendix 9.8.1.

    9.1.1.3 Identified Risks

  • 8/7/2019 09 Risk Management Plan

    4/6

    All identified risks have been documented in the Risk Register. (See

    Section 10). As any further risks become apparent, a full risk

    analysis will be performed on each new risk, and the Risk Register

    will be updated accordingly.

    9.1.2 Qualitative Risk Analysis

    9.1.2.1 Risk Probability & Impact Assessment

    Each identified risk has been assessed for the potential effects on

    schedule, cost, and scope by the project manager and the project

    team. Incident probabilities have been documented through

    brainstorming between the project manager and project team, as

    well as through interviewing Dr. Lipsett (See the Risk Register in

    Section 10).

    9.1.2.2 Probability & Impact Matrix

    A probability and impact matrix has been used to identify incident

    impacts on project objectives (time, cost, and scope). The matrix

    can be found in Appendix 9.8.2.

    9.1.2.3 Risk Data Quality Assessment

    Risk data will be reviewed on a weekly basis. The data collectedfrom individuals interviewed for their opinions on risk probabilities

    have been carefully reviewed for consistency. Any variations larger

    than 0.20 have been reassessed by the project manager, project

    team and Dr. Lipsett to attain values whose variation is equal to or

    less than 0.20 for a set of ratings describing a single risk.

    9.1.2.4 Risk Categorization

    All documented risks have been categorized by the sources of risk

    and the area of the project affected. This methodology illustrates the

    areas of the project that have the greatest exposure to uncertainty.

    Related documentation can be found in Appendix 9.8.3.

    9.1.3 Quantitative Risk Analysis

  • 8/7/2019 09 Risk Management Plan

    5/6

    Sean will complete

    9.1.4 Risk Monitoring, Control and Response Planning

    With respect to the Probability and Impact Matrix shown in Appendix 9.8.2,

    and the Risk Register in Section 10, activities posing a risk rating between

    8% and 17% will be closely monitored and controlled by the risk owner

    during the activity to ensure safe completion. Emergency services offered

    by the University of Alberta will be utilized in the event of an injurious or

    facilities-related incident. There are no current activities with a risk rating of

    18% or higher. If any risks arise with this rating, they will be avoided by

    changing the method of execution.

    During the weekly risk assessments, any new risks that are identified will be

    added to the risk register.

    9.2 Roles and Responsibilities

    The Risk Owners consist of Dr. Lipsett, Roger Marchand, AICT and the

    University of Alberta facilities. Any risk-related activities or processes relevant to

    Dr. Lipsett or Roger Marchand will be supervised by them accordingly during

    the time that the risk is present. If any incidents occur, these individuals are to

    handle them according to the risk responses listed in the Risk Register. Any

    incidents relevant to AICT or the University of Alberta facilities will be

    documented and the corresponding departments will be contacted.

    9.3 Budgeting

    (Luke will supply this information)

    9.4 Reporting Format and Content

    In the event of an incident, the Accident / Incident Report Form is to be filled out

    and returned to the Risk Owner. In the event that the risk was previously

    unforeseen, and there is no Risk Owner dedicated to the incident, this

    correspondence is to be given directly to Dr. Lipsett. This form can be found in

    Appendix 9.8.4.

    9.5 Risk Ownership

  • 8/7/2019 09 Risk Management Plan

    6/6

    All risks identified in the Risk Register have been assigned a Risk Owner. Any

    actions, processes or events posing a risk to the project will be closely

    monitored and dealt with accordingly by the Risk Owners in the event where the

    risks are present. In the event that a risk was previously unforeseen, and there

    is no Risk Owner dedicated to a risk, Dr. Lipsett will act as the designated Risk

    Owner.

    9.6 Risk Auditing

    Upon the completion of the Execution Phase of the Laboratory Development

    Project, the new laboratory set-up in Mec E 1-38 will be assessed a final time

    for possible risks present within the new layout. Any new risks will be

    documented in the Risk Register found in Section 10, and a risk analysis will be

    carried out. (See Section 9.1)

    9.7 Risk Management Plan Approval

    The Risk Management Plan is to be approved by Dr. Lipsett and Roger

    Marchand. Relevant documentation can be found in Appendix 9.8.5, and is to

    be read, understood and signed by both individuals prior to the start of the

    Execution Phase.