Slides related to the Draft Development Plan for Pimpri-Chinchwad in the presentation made by the Commissioner to the Chief Minister

TRANSCRIPT

Page 1: 09. Development Plan For Pcmc

Development Plan for PCMCDevelopment Plan for PCMC

Page 2: 09. Development Plan For Pcmc

D.P. Information (PCMC)

Newly Merged villages Area – 84.51 sq.km.

a. Newly Merged villages in PCMC area on 11.9.1997

b. Draft D.P. Published on – 05.10.2000

c. Draft D.P. submitted to State Govt. for approval - 14.07.2003

d. Part approval to DP on 30/5/2008 (for roads, Water supply & Drainage reservations ( except wakad area)

f. Part approval to DP of wakad area on 9/7/2008 ( for roads, Water supply & Drainage reservations (except some roads i.e. EP-1,2,3)

Page 3: 09. Development Plan For Pcmc
Page 4: 09. Development Plan For Pcmc

DP Roads Status for Extended AreaPCMC

WardSr.No.

Name of Village

Road Length in

Kms.

Survey completed

in kms

Survey Work in %

Demarcation completed

in kms

Demarcation on site in %

1 Talawade 39.86 29.10 73% 0.00

2 Chikhali 55.04 55.04 100% 16.51 30%

3 Punawale 22.81 22.81 100% 13.46 59%

4 Rawet 25.18 22.91 91% 13.29 58%

5 Kiwale 25.48 22.17 87% 0.00

6 Mamurdi 12.47 10.97 88% 0.00

7 Boradewadi 11.80 11.80 100% 0.00

8 Moshi 28.32 28.32 100% 0.00

9 Dudulgaon 18.68 18.68 100% 16.81 90%

10 Chowisawadi 15.58 15.58 100% 8.88 57%

11 Wadmukhwadi 16.11 16.11 100% 2.26 14%

12 Charoli 48.64 35.51 73% 7.10 20%

13 Dighi 15.67 15.67 100% 15.67 100%

14 Bhopkhel 6.53 6.53 100% 0.00

D 15 Wakad 25.82 23.49 91% 18.79 80%

Total 367.97 334.67 91% 112.76 34%

A

B

C

Page 5: 09. Development Plan For Pcmc

PCMC DP for Extended Area (PLU) PCMC

• Residential= 4727.52 Ha.• Commercial = 267.62 Ha.• Industrial = 251.92 Ha.• PSP = 265.79 Ha.• Pub. Utility= 96.53 Ha.• Trans. = 1094.47 Ha.• NDZ = 1288.50 Ha.• Water Bodies = 133.04 Ha.• S.T.Park = 69.71 Ha.

-------------------------------

• Total = 8451.00 Ha.

PCMC DP for Extended Area (PLU)

3%

3%

3%

13%

16%

2%

1%

1%

58%

Residential

Commercial

Industrial

PSP

Pub. Utility

Trans.

NDZ

Water Bodies

S.T.Park

Page 6: 09. Development Plan For Pcmc

Status of Draft D.P. (PCMC)

• State Govt. sanction is awaited (Partly).– Changes suggested by General Body are sent to Govt.

• IMPLEMENTATION– Survey work and demarcation of DP roads is in

progress of all newly merged villages.– Advance possession of DP roads is taken in subject to

condition of TDR– Possession of DP roads is being taken in lieu of FSI.