STATUS REPORT OF AS ON 09.02.13

“A”-BLOCK STATUS

1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-

Completed.

Page 2: 09 02-2013

STATUS REPORT OF AS ON 09.02.13

“B”-BLOCK STATUS

1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-

Completed5. Cellar Slab(-

1)Shuttering work in progress for 1 &2 flats.

Page 3: 09 02-2013

STATUS REPORT OF AS ON 09.02.13

“C”-BLOCK STATUS

1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar – for flat

No:01 completed for flat No:02 today completed.

Page 4: 09 02-2013

STATUS REPORT OF AS ON 09.02.13

“D”-BLOCK STATUS

1. PCC-Completed2. FOOTINGS-Completed3. G. Slab-Completed4. Sub Cellar-Completed5. Cellar Slab Column

work in progress for flat 1 & 2.

Page 5: 09 02-2013

STATUS REPORT OF AS ON 09.02.13

“E”-BLOCK STATUS

1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub. Cellar- 40%-

Completed

Page 6: 09 02-2013

STATUS REPORT OF AS ON 09.02.13

“TOTAL SITE” STATUS

1. All Blocks PCC-Completed

2. All Block Footings-Completed

3. All locks G. Slab-Completed

4. Total Site Sub Cellar- 88%-Completed