Page 1 of 6 July 30, 2013 TO: All Plan Holders FROM: Luis Mendez, Deputy Director SCCRTC Bill Baker, Resident Engineer, Santa Cruz Branch Line Bridge Supports, Repairs and Member Replacements Project SUBJECT: Notice – Questions & Answers Priority One Repairs: 1. Q: Bridge 4.87: Posting all piles at Bent 1 goes against AREMA Chapter 7. Is there enough room to double cap this bent or should the contractor frame the bent? A: Replacement of abutment one with a framed bent or double capping is correct. Bidders are advised to review the inspection report and inspect the structure to determine if there is enough room for double capping. Inspection reports are available on the SCCRTC website at www.sccrtc.org/RRBridgework. 2. Q: Bridge 5.42: a) Is it the intention of the owner to replace all the ballast boards at this location? b) What is the depth of the ballast? c) Is there a track joint on the bridge? A: a) See the inspection report for details of condition of ballast guard and ballast planks. Only one span of ballast planks are to be replaced. The Appendix G scope of work calls for replacement of 30 track feet of ballast guard and replacement of 15 lineal feet of ballast planks. b) Our observation during inspections indicates approximately 14” ballast depth. Bidders are advised to inspect the structures to determine ballast depth. c) Yes. 3. Q: Bridge 11.6: Posting pile at Bent 17 shows posting piles 1, 4, 5 & 6. Posting 3 piles adjacent to each other violates AREMA Chapter 7 also, should this bent be framed instead? A: Replacement of piles with a framed bent at Bent 17 is correct.

Upload: others

Post on 12-Jun-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

 

Page 1 of 6 

 

July 30, 2013 

TO: All Plan Holders 

FROM: Luis Mendez, Deputy Director SCCRTC 

Bill Baker, Resident Engineer, Santa Cruz Branch Line Bridge Supports, Repairs and 

Member Replacements Project 

SUBJECT: Notice – Questions & Answers  

Priority One Repairs: 

1. Q: Bridge 4.87: Posting all piles at Bent 1 goes against AREMA Chapter 7. Is there enough room 

to double cap this bent or should the contractor frame the bent? 

 

A: Replacement of abutment one with a framed bent or double capping  is correct.   Bidders are 

advised to review the inspection report and inspect the structure to determine if there is enough 

room  for  double  capping.  Inspection  reports  are  available  on  the  SCCRTC  website  at 

www.sccrtc.org/RR‐Bridgework.   

 

2. Q: Bridge 5.42:  

a) Is it the intention of the owner to replace all the ballast boards at this location? 

b) What is the depth of the ballast? 

c) Is there a track joint on the bridge? 

 

A:  

a) See  the  inspection  report  for  details  of  condition  of  ballast  guard  and  ballast  planks.  

Only one span of ballast planks are to be replaced.  The Appendix G scope of work calls 

for  replacement of 30  track  feet of ballast guard and  replacement of 15  lineal  feet of 

ballast planks.  

b) Our observation during  inspections  indicates approximately 14” ballast depth.   Bidders 

are advised to inspect the structures to determine ballast depth. 

c) Yes. 

 

3. Q: Bridge 11.6: Posting pile at Bent 17 shows posting piles 1, 4, 5 & 6. Posting 3 piles adjacent to 

each other violates AREMA Chapter 7 also, should this bent be framed instead? 

 

A: Replacement of piles with a framed bent at Bent 17 is correct. 

 

Page 2: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

July 30, 2013  

Page 2 of 6 

4. Q: Bridge 15.89(d): Posting pile at Bent 2 again shows 3 adjacent piles. Should  the contractor 

frame this bent? 

 

A: Replacement of piles with a framed bent at Bent 2 is correct. 

 

5. Q: Bridge 23.54: 

a) The  bridge  appears  to  be  a  single  span  bridge  to  be  re‐built  entirely.  The  work 

description  shows  posting  all  10  pile,  again  this  goes  against  AREMA  best  practices. 

Should the contractor frame the abutments? 

b) Has the owner considered replacing this bridge with a culvert? For the amount of work 

to be done, a new RCB or large CMP culvert may be cheaper and will help by eliminating 

a bridge. 

A:  

a) Replacement of piles with a framed bent at abutments 1 and 2 is correct. 

b) Bidders are directed  to submit bids based on  the Appendix G scope of work  to replace 

the  structure  in‐kind.   Replacement with  culvert  and  other  design  alternatives will  be 

taken into consideration after the project is awarded.  See General Conditions Item 37, p. 

12, for information regarding implementation of changes in the work.   

 

6. Q: Bridge 9.09: 

a) What is the width of the Right‐of‐Way (ROW) at this bridge location? 

b) Can  the  contractor  drive  support  pile within  the  ROW without  violating  the  current 

permits?  The  current  suggested  staging  does  not work.  It  gets  a  crane  out  over  the 

work, but cannot get it back. 

c) What constitutes “heavy equipment” per the permit requirements? 

d) The pier concrete repairs require grading, wire sawing and re‐casting of concrete at the 

bottom  of  the  structure.  How  is  the  contractor  to  accomplish  this  without  having 

equipment on the bottom? 

e) The  contractor will have  to  remove  and  repair  the  girders; does  the owner have  the 

original bridge drawings? 

f) What are the weights of the steel sections that have to be removed? 

g) What is the intention of the owner for painting of the existing steel for this structure? Is 

the paint only  for  the  repaired areas or  is  it  for  the entire member? The construction 

notes  reference blasting all  seams, welds, edges,  corners, etc.  Is  it  the  intent  to  then 

coat the entire girder over the top of the existing lead paint? 

h) The  deck  removal  notes  state  that  the  contractor  is  responsible  for  all  ties,  rail  and 

hardware and has to re‐use or replace at no additional cost to the RR. The majority of 

the time, damage  is not apparent until the member/piece  is actually removed. How  is 

the  contractor  to  account  for  this  in  the bid? Potential bidder  suggests  adding  a  line 

Page 3: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

July 30, 2013  

Page 3 of 6 

item to the bid for misc. repairs and replacement with a value of $50,000 for all bidders 

to include with their bid. This allowance will help pay for the incidental unknowns.   

 

A:  

a) Bidders may  refer  to  the Right‐of‐way maps  in  the  reference documents  found on  the 

SCCRTC  website  at  www.sccrtc.org/RR‐Bridgework.  See  file:  Right‐of‐Way‐

Maps_SCCRTC.pdf.      This  location  is  on  Map  Sheet  43  where  ROW  locations  vary 

between approximately 50 and 80 feet. 

b) See General Conditions  Item 54, p. 27, regarding permits and  licenses.   See also the La 

Selva drawings, General Notes  ‐1, Drawing No. 3 of 67, PERMITS.   The Contractor shall 

procure  all  permits  and  licenses  necessary  to  conduct  the work. There  is  no  known prohibition  to  driving  support  piles  within  the  ROW  and  none  is  anticipated  to  be 

imposed by any permitting agency.     The staging is only a suggestion, the contractor is required to develop and submit their own staging plan. 

c) Heavy equipment would be  the  type and  size  to  create  significant  slope damage,  i.e., 

dozers, excavators, etc. 

d) Placing  of  small  equipment,  i.e.,  Bobcat  or  similar  sized  equipment  with  a  crane  to 

minimize slope disturbance was envisioned. The contractor is encouraged to utilize other 

means to accomplish the work while minimizing slope disturbance. 

e) Bidders  may  refer  to  the  reference  documents  found  on  the  SCCRTC  website  at 

www.sccrtc.org/RR‐Bridgework.  See the file sn0909‐1thru60.pdf. 

f) Bidders are advised to review the reference documents found on the SCCRTC website at 

www.sccrtc.org/RR‐Bridgework.   

g) See the La Selva drawing,   General Notes ‐2, Drawing No. 4 of 67, stating,   “ GENERAL:  

CLEAN AND PAINT ALL EXPOSED STRUCTURAL STEEL AND OTHER METAL  SURFACES.  “  

See  also  General  Notes  ‐3,  Drawing  no.  5  of  67  under  the  heading  PRE‐CLEANING.   

Cleaning means  removing  dirt,  grease,  loose  chalky  paint  and  other  foreign material 

from the surfaces.  Existing, in‐tact paint on surfaces after cleaning may be painted over. 

h) The General Notes‐3, Drawing No. 5 of 67,  states,    “THE COST OF DISPOSING OF UN‐

USEABLE MATERIAL AND  THE REPLACED MATERIAL  SHALL BE PAID  FOR AT  INVOICED 

COST OF THE NEW MATERIAL PLUS 50%, NO ADDITIONAL PAYMENT WILL BE MADE.”  A 

subsequent addendum will  include under Bid  Item 4a. Deck Removal, Storage and Re‐

installation a sub‐Item 4a.‐1, an allowance of $50,000 for Disposal and Replacement of 

Track Material Unsuitable for Re‐use.  

 

General Questions: 

7. Q: Pile Replacement: 

a) New  creosote  treated pile  is generally no  longer driven. Typically a new  steel bent  is 

driven with HP 14x89 pile and a HP 14x89  cap  if  the bent  is  to be  replaced.  Is  it  the 

intention  of  the  owner  to  have  the  contractor  drive wood  pile?    The  operation  and 

Page 4: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

July 30, 2013  

Page 4 of 6 

equipment  involved  for  driving  a  new  pile  is  quite  different  from what  is  needed  to 

splice a pile. Who will be making  the determination on whether  to post a new pile or 

replace? 

b) How should the contractor price this item if it is undetermined? 

 

A:  

a) Driving new pile  is not  intended. Pile  (less  than 3 piles per bent) can be posted.  If 3 or 

more piles need to be replaced, then replace the bent with a framed bent. 

b) See above response. 

 

8. Q: Ballast Contamination: 

a) The ballast removal at various bridges all have the same note that the ballast might be 

contaminated and  it  is up to the contractor to test and dispose of accordingly. Has the 

owner tested the ballast? What types of contamination are thought to be present?   

 

A: 

a) The owner has not tested the ballast. Some possible contaminates are hydrocarbons and 

latent deposits from railcar contents.   

 

All  ballast  removed  from  the  bridge  decks  as  necessary  to  perform  repairs  shall  be replaced with clean ballast and compacted per AREMA Volume 1  ‐ Track, Chapter 1 – Roadway  and  Ballast,  Section  2.0  Substructure  Introduction  through  Section  2.10 Maintenance Practices.   Existing  ballast  on  the  right‐of‐way  is  considered  re‐usable  as  backfill  or  for  roadbed shoulder widening as  long as  it remains on the right‐of‐way.   Ballast removed from the ballast deck structures to facilitate the work may be stockpiled within the SCCRTC right‐of‐way for future re‐use or placed within the right‐of‐way as backfill or roadbed shoulder widening.     Ballast used for these purposes will be placed at  locations approved by the owner’s representative.  See also Questions and Answers from the attached Notice issued May 2. 

  

9. Q:  Stringer Replacement:  Is  it  the  intention of  the owner  to  replace only  the  span described 

(nominally a 15’ span) or is the full length of the stringer to be replaced?  This item will impact 

the contractor’s means and methods, and cost. 

 

A: The intention is to replace only the span (nominally a 15’ span). 

 

10. Q: Will SCCRTC participate  in a facilitated partnering process to ensure good owner/contractor 

relationship throughout the project? 

 

Page 5: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

July 30, 2013  

Page 5 of 6 

A: Yes. 

 

11. Q:  Must  pedestrian  access  under  bridges  that  have  pedestrian  facilities  under  them  be 

maintained? 

 

A: Contractor shall employ its best efforts to maintain pedestrian access under bridges that have 

pedestrian facilities under them while maintaining safety for workers and users of the pedestrian 

facilities. 

12. Q:  With reference to the questions and answers from the RT‐14019‐01 contract that bid on May 

24, 2013: Do the answers to these questions remain accurate on the RT‐14019‐01 contract that 

is  scheduled  to  bid  on August  9,  2013?  If  any  do  not  remain  accurate  please  re‐answer  the 

questions accordingly. 

A:   The previous Questions & Answers notices are attached and edited for this bid.  The answers 

remain accurate except as noted in text that is italicized and included in square brackets.   

Priority Two Repairs: 

13. Q: Bridge 6.25: 

a) Bent 8  shows  replacing/posting piles 4, 5 & 6. This  is posting 3 adjacent piling again. 

Should this bent be framed instead?  

b) The work description shows replacing stringers in Span 8. The stringers are numbered 7, 

10,  11 &  12.  Is  the  numbering  correct? Are  there  6  stringers under  each  rail on  this 

bridge? 

 

A:  

a) Bent 8 will need to be replaced with a framed bent. 

b) Yes, the numbering  is correct.   There are 12 stringers, 6 for each rail.   The stringers are 

spaced apart for supporting the ballast deck. Stringer 1 and 12 are ballast stringers on a 

ballast deck bridge. Bidders are advised to review the  inspection report and  inspect the 

structure. 

 

14. Q: Bridge 15.89(b): 

a) The description  shows  replacing/posting pile  for  this bridge. Due  to  the height, aren’t 

the  taller portions  framed?   According  to AREMA Chapter 7, a pile  that  is over 23’  in 

height on a tangent bridge cannot be posted.   

b) If the above is true, does the owner want the girts replaced at the new framed member 

sections?    Typically  this  is  a  best  practice when  installing  new members  in  a  framed 

section. 

 

 

Page 6: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

July 30, 2013  

Page 6 of 6 

A:  

a) No, the taller portions are not framed. Splicing the pile may be the preferred option. 

b) Bids should be based on the quantities shown for the structural members provided in the 

Scope of work.  Determination of any further replacement of structural members will be 

addressed according to the contract provisions for Changes in the work.  

 

15. Q:  Bridge  19.43(a  &  b):  Replace  ties  is  listed  as  an  approximate  quantity.  Please  provide  a 

quantity for contractor to bid. 

 

A: The Bids should be based on the quantities 80 bridge ties for Bridge 19.43a and 60 bridge ties 

for Bridge 19.43b. 

 

16. Q: Bridge 26.55: Would the owner consider replacing this bridge with a culvert? 

 

A: Replacement with culvert will be taken into consideration after the project is awarded. 

 

Priority Three Repairs: 

17. Q: Bridge 23.47: Would the owner consider replacing the bridge with a culvert? 

 

A: Replacement with culvert will be taken into consideration after the project is awarded. 

 

18. Q: Bridge 26.09: Would the owner consider replacing the bridge with a culvert? 

 

A: Replacement with culvert will be taken into consideration after the project is awarded. 

 

19. Q: Retaining Wall MP 8.94  to MP 9.09: Do  you have design drawings  for  this?   Contractor  is 

unable to price this item as described. 

 

A: Design drawings are not available at  this bid  time.   Bids should be based on  the quantities 

provided in the Bid form and Scope of work.  The guiding reference document is AREMA Manual 

Chapter 8, Part 5 Retaining Walls, Abutments and Piers.  Bidders are advised to inspect the site 

of the structure.   

 

See also Questions and Answers from the attached previous Bid Q&A notices. 

 

 

Page 7: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

 

 

April 18, 2013 

TO: All Plan Holders 

FROM: Luis Mendez, Deputy Director SCCRTC 

Bill Baker, Resident Engineer, Santa Cruz Branch Line Bridge Supports, Repairs and 

Member Replacements Project 

SUBJECT: Notice – Questions & Answers  

General Notes and Inquires from April 10 Pre‐Bid Meeting  

Q: Will there be liquidated damages? 

A:   Yes,  liquidated damages are addresses on Page XIII of the bid package, which  is the fourth 

page of the Bid Form. Liquidated damages are also addressed in Section 36 (Page 11 of the bid 

package), Section 44 (Page 18 of the bid package) and Section 48 (Page 19 of the bid package). 

[These  page  numbers  are  12,  19  and  20  respectively  in  the  bid  package with  a  due  date  of 

August 9, 2013.] 

   

Q: Is pre‐bid meeting attendance mandatory for bidding? 

A: No, the pre‐bid meeting is not mandatory. It was held on 4/10/2013. If your firm would like 

to visit the site on your own, please contact the Railroad operator: Iowa Pacific Holdings/Santa 

Cruz  &  Monterey  Bay  Railway  (IPH)  representative,  Jeff  Weeks  (510)  927‐6376 

[email protected]  for permission  to be on  site. Google maps of  the  locations of  sites 

visited on 4/10 are available. 

 

Q: Are there any other special requirements for bidding? 

A:  The  requirements  for  bidding  are  covered  in  the  bid  documents.  Any  changes  will  be 

addressed in upcoming addendum. 

 

Q: Items 9 and 42 on Appendix I, the reference documents  list  in the bid package, seem to be 

the same document. 

A: Yes, they are the same document. Item 9 is the final stamped and signed version. 

 

Q: Is there an engineer’s estimate for the Santa Cruz Branch Line Bridge Supports, Repairs and 

Member Replacements? 

Page 8: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

 

A: Please see APPENDIX F: Bid  Item Cost Estimate  in  the Bid Documents. The  total estimated 

cost  for  the project  is $4,685,295.  [This has been  revised  to $4,781,190.00, due  to additional 

costs associated with fire damage to bridge at MP 23.54.] 

 

Q: Are trains currently running over the La Selva Bridge? 

A: No. They are not operating past approximately MP 4.5. However,  train equipment  for  the 

train to Christmas Town service beginning from the Santa Cruz Boardwalk will be moved over 

the  La  Selva  Bridge  between  November  1,  2013  and  January  5,  2014.  [The  requirement  to 

schedule  the work  to allow  the Train  to Christmas Town equipment  to be moved over  the La 

Selva Bridge between November 1, 2013 and January 5, 2014 has been removed.] 

 

Q: Most of  the  structures  that  require  repair are  timber. Are  they  to be  replaced with  steel 

members? 

A: No.  The  timber  structures members  are  to be  replaced  in‐kind.  [Bidders are advised  that replacement framed bents on timber bridges may be either steel or timber.   Replacement with other than in‐kind components shall be designed by a qualified railroad bridge engineer per FRA CFR 49  PART 237—BRIDGE SAFETY STANDARDS  Subpart F—Repair and Modification of Bridges   237.131 Design.]  

Q: Does the scope of work include only steel bridges? 

A: No, there are both timber and steel bridges included in the work. 

 

Q: Are there only design drawings for the steel bridges? 

A: Yes, the scope of work narratives for the timber bridges are  included  in the bid documents 

(see APPENDIX G: Project Scope of Work.) 

 

Q: Will there be a need for any additional engineering for timber bridges? 

A: No. All work will  be  to  replace  in‐kind  according  to AREMA  specifications.  [See  comment 

above.] 

 

Q: Has sequencing been determined? 

A: There is a suggested sequencing plan for the La Selva bridge and a suggested jacking plan for 

the  Capitola  bridge.  However,  it  is  the  contractor’s  responsibility  to  prepare  their  own 

sequencing and jacking plans for all locations and submit for approval.  

 

Q:  Does  the  removal  of  any  bridge members/components  compromise  the  integrity  of  the 

bridge? 

A: Yes. 

Page 9: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

 

 

Notes: 

1. Rail removal and replacement work must be done by qualified personnel. 

2. High levels of arsenic were found in the soil at some locations. 

3. Steel structures were determined to contain lead paint. 

4. For the steel structures, the intent is to do the work from the top down. 

5. It may be possible to get a crane on the ground to assist at the La Selva Bridge. 

6. Access will primarily be by SCCRTC rail line ROW. 

7. Safety protocol: contact Jeff Weeks prior to accessing the ROW. 

8. Several bridges have pedestrian access routes that lead to the beach. Coastal beach access 

via pedestrian trails, etc. must be maintained, and cannot be shut down for the duration of 

the construction activity. 

9. There are businesses and residents  leasing area under the Capitola Bridge. Notice must be 

given to move out while construction activity is underway. 

 

Antonelli Pond MP 22.29 

 

Q: Is the foundation ok? 

A: Yes, as far as we know. 

 

Q: What about damage that is not identified in the inspection report? 

A: Contractor shall work with the CM to identify any additional damage. 

 

Q: Who is responsible for inspection? 

A: The CM is responsible.  

 

Q: Is there any direction given for field welding? 

A: Yes, in the specifications. 

 

Notes: 

1. For walkway  repairs, only damaged portions  (i.e. holes, broken  ledgers, etc.) need  to be 

repaired. There  is no  total  replacement. This  is  identified as a  lineal  foot  item  in  the bid 

schedule. 

 

San Lorenzo River MP 19.43 

 

Q: Will access be available through the existing parking area near the bridge? 

Page 10: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

 

A: SCCRTC will contact the owner to inquire. [The parking lot is owned by the Seaside Company, 

who  owns  the  Santa  Cruz  Beach  Boardwalk.  According  to  a  representative  of  the  Seaside 

Company, access would be available through the parking area near the bridge but contractors 

should ensure that safe access to the Boardwalk by visitors is adequately maintained, it should 

not be during peak visitor season, adequate  insurance should be maintained by the contractor 

and any other necessary details should be worked out.] 

 

Q: Is this bridge steel or wrought iron? 

A: Steel. 

 

Q: Can it be welded to? 

A: Yes. Paint must be cleared around the area to be welded. 

 

 

Q: Are the bottom plates of the stringers to be replaced? 

A: Yes, a new plate is to be added. 

 

Q: When was the San Lorenzo bridge built? 

A: Based on available records, it is estimated to have been built in 1904. 

 

Q: Can the rail hardware (e.g. tie plates) be reused. 

A: Yes, if they are in good condition, but if not in good condition, they must be replaced. 

 

Capitola MP 15.89 

 

Q: Can you confirm that the new anchor bolts and rebar do not conflict? 

A: Cannot confirm off‐hand. See referenced as‐built documents. 

 

Hidden Beach MP 11.16  

 

Q: Is there a missing pile? 

A: Yes. 

 

Q: Does a new pile need to be driven? 

A: No. 

 

Q: What is to be done about the missing pile? 

Page 11: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

 

A: Bad section was removed but never replaced. Contractor shall supply new pile section and 

splice per SP common standards and AREMA Manual for Railway Engineering. 

 

Seascape MP 10.45 

 

Q: Is there a preference for notching the bracing timbers versus the use of spacers? 

A: Spacers are preferred (see SP common standards.) 

 

Q: Is there trackwork needed on this bridge? 

A: No, but the deck planks may need to be replaced. 

 

La Selva Beach MP 9.09 

 

Q: Do ties need to be removed and placed back exactly at the same  location from which they 

were removed and in the same order and orientation as they are currently placed? 

A: Yes, and some of the guard timbers and all hardware needs to be replaced. 

 

Q: Is access from the grade crossing back to the bridge a possibility? 

A: All access is up to the contractor to determine. 

 

Notes: 

1. The La Selva Bridge must be operational from the beginning of November to the middle of 

January. [This no longer applies.] 

2. All  ties  need  to  be marked  first  to  ensure  replacement  back  in  the  same  location  and 

orientation. 

3. The access ramp from the Manresa Beach parking lot to the beach is approximately 9 feet in 

width. 

4. Crane access may be difficult. 

5. Contractor must remain outside of the water channel below the bridge. 

6. Contractor shall build a fence to separate the bridge area from the privately owned parking 

area  at  the  base  of  the  bridge.  [And  contractor  shall  employ  its  best  efforts  to maintain 

access to the beach from the parking lot.] 

Retaining Wall MP 8.94  

Q: The existing walls are approximately 15 feet from the centerline of the track. How far away 

do the new retaining walls need to be from the centerline of the track?  

Page 12: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

 

A: The new retaining wall shall be constructed in approximately the same position with latitude 

of +/‐ 2  feet to accommodate construction, while maintaining a minimum distance of 15  feet 

from the centerline of the track. 

 

Q: Do the new retaining walls need to be engineered? 

A: No, the new retaining wall shall be constructed according to AREMA specifications. 

San Andreas Road MP 8.64  

Notes: 

1. The concrete structure is not part of the work scope.  

2. There is an existing utility line running parallel and southwest of the bridge. 

 

Page 13: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

 

 

May 2, 2013 

TO: All Plan Holders 

FROM: Luis Mendez, Deputy Director SCCRTC 

Bill Baker, Resident Engineer, Santa Cruz Branch Line Bridge Supports, Repairs and 

Member Replacements Project 

SUBJECT: Notice – Questions & Answers  

1. Q: The Bid Form doesn’t appear to have any total or subtotals. Is this the intention of the form?  

A: Understanding you are looking for the space on the Bid Form where the Bidder enters 

the Total Bid: The Bid Form has a space above the Bid Schedule for the bidder to fill out 

the sum for the Total Bid.  The intent of the form is to have the Bidder’s Total Bid 

entered here on Pg. XI, just above the Bid Schedule.  See also the last instructional line 

on Pg. XII: 

 

(Bidder shall multiply the Estimated Quantity of each bid Item, by the Bidder’s Unit Price 

for each Item, which total shall be written as the Unit Total for each Item. Bidder’s Total 

Bid shall be the sum of the Unit Total of each bid Item.) 

 

See also the Instructions to Bidders that begin on Pg. VI. 

 

2. Q: In Appendix E, the Contractor Occupancy/Access Agreement paragraph 3 states that 

the contractor agrees to reimburse the railroad for all cost and expense incurred by the 

Railroad in connection with the work. The costs listed include inspectors, is it the intent 

that the contractor will reimburse the railroad for all inspection costs? If so please 

provide a listing of work the railroad wishes to inspect and anticipated costs for these 

inspections so that this cost can be included in the pricing. 

 

A:  The Inspectors referred to in paragraph 3 of Appendix E will be part of the staff of 

the Owner’s Representative on this contract.  The Railroad does not anticipate incurring 

cost for inspectors in connection with the work on this contract that would be the 

contractor’s responsibility to reimburse.  

 

Page 14: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

May 2, 2013  

Refer also to Special Conditions and Requirements Section II.1. A under Engineering 

Services, Contractor Payment for Services Provided by Engineer, stating that SCCRTC 

shall be reimbursed by the Contractor for additional services including inspections that 

are necessary due to damages caused by the Contractor, negligence or rejected or 

nonconforming work.  

 

3. Q: The drawings do not size the welds or the bolts.  We need to supply this information 

to the fabricators for pricing information. Can you supply this information? 

 

A: All weld sizes when not specified on plans are minimum weld sizes per AWS D1.5 

which are dependent on plate thicknesses. H.S. bolts are to be 7/8 inch diameter. 

4. Q: SCCRTC received a request from a prospective bidder for a four week bid extension 

for the Santa Cruz Branch Rail Line Improvement Project.  

 

A: The bid due date of May 10, 2013 remains in place. [This no longer applies.] 

 

5. Q: In the bid Documents, on sheet XII there are three bid items that pertain to the 

bridge at milepost 19.43, item 15, 16 and 25. However there is not a description for bid 

item 25, only a description for bid items 15 and 16. Is this a mistake in the bid form?  

 

A: The bid items are corrected in Addendum No. 2. Bid Item 25 is removed from the 

package. [The Bid Item No.’s 15 and 16 have been revised to Bid Items 16 and 17 

respectively in the bid package with a due date of August 9, 2013.] 

 

6. Q: A prospective bidder observed that the bridge at milepost 23.47 has been damaged 

by a recent fire and points out that the condition it is in currently greatly deviates from 

the bid item description and the recent engineering inspection report that is in the bid 

documents. 

 

A: The bridge that was damaged by a recent fire is Bid Item No. 17, Bridge 23.54.  A 

revised scope for Bridge 23.54 is issued in Addendum No. 2.  Note that the questioner 

erroneously identified the burned bridge as Bridge at MP 23.47. 

 

The scope for Bid Item No. 27, Bridge 23.47 remains unchanged. 

 

Page 15: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

May 2, 2013  

[Bid Item No. 17 has been revised to No. 9 in the bid package with a due date of August 

9, 2013.] 

 

7. Q: a) The “Project scope of work”  sheets state that: 

 

i. “All ballast removed or disturbed during the repair process shall be replaced with clean 

ballast and compacted ….” 

ii. “The contractor shall test all soil and ballast prior to removing it from SCCRTC property 

in order to comply with all Federal, State, Local laws governing contaminated soil.” 

iii. “All ballast removed from ballast deck structures shall be properly disposed of in 

accordance with Federal, State and Local regulations.” 

b) Additionally the AMEC Phase II Investigation (December 2009) identifies the possibility of 

hydrocarbons, arsenic, chromium, lead and pesticides. However there does not appear to 

be sufficient samples to determine what if any contaminates there are at the bridge 

locations. Without this information the contractor is unable to accurately estimate the 

disposal cost. Is there testing information available specifically for the bridge locations? If 

no additional information is available payment of the disposal fees under an allowance 

item would ensure uniformity of contractors pricing or an alternative option would be to 

allow material to be left on site.  

A: a) i. All ballast removed from the bridge decks for the convenience of the Contractor to 

perform repairs or as necessary to perform repairs shall be replaced with clean ballast 

and compacted per; AREMA Volume 1 ‐ Track,   Chapter 1 – Roadway and Ballast, Section 

2.0 Substructure Introduction through Section 2.10 Maintenance Practices.  

ii. As stated, any soil or ballast designated to be removed from SCCRTC property shall be 

tested prior to removal from the right‐of‐way.   See INSTRUCTIONS TO BIDDERS Items 3 

and 5.  See also page 1 and 2 of the GENERAL CONDITIONS, items 3 and 4. Bidders must 

satisfy themselves through their own testing and investigation, as to the conditions to 

be encountered.   Bidders shall include in their bids, sums to compensate Bidder in the 

event that Bidder is awarded the Contract and encounters unexpected or other 

conditions.  This includes compensation for unsuitable materials as described in 

INSTRUCTIONS TO BIDDERS Item 3. 

iii. Any suitable ballast removed from the ballast deck structures to facilitate the work may be stockpiled within the SCCRTC right‐of‐way or re‐used as backfill or for roadbed shoulder widening on the right‐of‐way.  Ballast used for these purposes will be placed at locations approved by the owner’s representative.     Contractor’s work plan shall contain provisions for management of materials to address soil and ballast sampling, 

Page 16: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

May 2, 2013  

excavation, handling, stockpiling, and disposal procedures for any materials removed from the SCCRTC right‐of way in compliance with Federal, State and local laws.  

b) See INSTRUCTIONS TO BIDDERS Items 3 and 5. See also page 1 and 2 of the GENERAL 

CONDITIONS, items 3 and 4. The AMEC Phase II investigation is made available for 

information but does not constitute part of the contract.  Bidders must satisfy themselves 

through their own testing and investigation, as to the conditions to be encountered.   The 

bid documents do not have a separate allowance item for disposal fees as it is considered 

incidental to the work.  See above response a)iii  addressing management of soils and 

ballast.  Contractor’s materials management plan shall be in compliance with Federal, 

State and local laws.  Any unsuitable material designated for removal from the SCCRTC 

right‐of‐way shall be properly disposed of including but not limited to the material testing, 

cost to transport and disposal fees at an authorized disposal facility.   

8. Q: Is there minority outreach associated with this project? 

 

A: Please refer to the “Public Notice” section, page IV, of the bid documents. 

 

Page 17: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

 

 

May 20, 2013 

TO: All Plan Holders 

FROM: Luis Mendez, Deputy Director SCCRTC 

Bill Baker, Resident Engineer, Santa Cruz Branch Line Bridge Supports, Repairs and 

Member Replacements Project 

SUBJECT: Notice – Questions & Answers  

1. Q: Bid item number 37, Handrail Repair, does not have a bid item description. Which type of Handrail is in need of repair; cable or wood and on which bridge shall the repairs be made?  A: See inspection reports in the reference documents for details on Bid Item 30 ‐ handrail repair.  Bidder to determine type and quantity of repair based on inspection reports, site visit of April 10th and bidder’s own site investigations. 

 

2. Q: On page one of the general notes for the La Selva Bridge under General Notes it states, “All material and workmanship shall conform to the American Railway Engineering and Maintenance of Way Association’s Manual for Railway Engineering (AREMA Manual)…” In AREMA Manual Chapter 15 Section 3 Subsection A & B pertains to structural steel fabricators qualifications which states that fabricators must poses a SBR (Simple Steel Bridge Structures) or a CBR (Major Steel Bridge Structures) or another suitable program as determined by the engineer. As well as, “Structural steel fabricators of Fracture Critical Members shall be certified under the AISC Quality Certification Program, with a Fracture Critical Endorsement (F) or another suitable program as determined by the engineer.” Is it the owner’s intentions that the structural steel fabricator have either a SBR or a CBR certification and a Fracture Critical Endorsement (F) for this project? Also what constitutes a “suitable program” that will be accepted by the engineer in lieu of the aforementioned qualifications?  A: To Clarify AREMA Chapter 15, Section 3.1.1, Subpart a) AISC Quality Certification CBR shall be required for fabrication of all bridge steel.  To Clarify AREMA Chapter 15, Section 3.1.1, Subpart b) AISC Quality Certification Program with a Fracture Critical Endorsement shall be required for the fabrication of any members listed as Fracture Critical Members (FCM) within the Contract Plans.  No other qualification will be deemed suitable.  

3. Q: While reviewing the drawings for the La Selva Bridge, the Span Top Plan drawing for Span 5 seems to be missing. Was this was left out intentionally or is it located someplace else in the drawings?  

A: Rev. 1 of Drawing 54 of 67 is in the La Selva Package, Addendum No 4.  [This has been corrected and question does not apply to bid package with due date of August 9, 2013.]  

Page 18: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

May 20, 2013  

 

4. Q: It appears that the following represents the grading of the wood materials for the project:  

Specie  (Douglas Fir, Hem‐Fir, SYP) 

Grade ‐ Select Structural, #1, or #2 

Surfacing ‐ Rough (Full Sawn, or Standard Sawn), S4S, or S1S, S1E, S1S1E, Etc. 

Treatment type ‐ Creosote, 50/50 Creosote/Petroleum oil, Penta‐H, ACZA or ACQ 

Retention of Treatment ‐ 12#, 10#, 8# if Creosote or 50/50, Penta‐H .60, .50, ,40, ACZA .4#, .6#, 1.0#, 1.5#, 2.5# 

 a) What is the appropriate AWPA UC (use code) this would spell out retentions & type of 

treatment? What preservative or preservatives are to be used? (The UC's gives more than 1 option) 

b) Which Certifications are required ‐ Independent, Agency Certs (WCLIB WWPA PLIB)? c) Is there any moisture content spec? d) What is the grade and surfacing of the material? e) What certificates are needed? ‐ Mill certificates, Agency certificates, or 3rd party 

certificates. f) What are the BMP's required?  If so are treating plant certificate OK or do we need 3rd 

party?  A: a) AREMA only refers to AWPA C28 for the preservative requirements for glulam timber (Ch. 

7 Sec 1.5.1.6). Other preservatives vary by the location of the bridge element (i.e. above 

ground dry, marine use, ground contact, etc.) Those preservative designations vary greatly 

and can be found in AWPA’s Use Category System: User Specification for Treated Wood.    

 

b) The appropriate grading Agencies/Bureaus are referenced in the Tables found in AREMA 

Chapter 7, Section 2.  They are:   

NELMA – Northeastern Lumber Manufacturers Association, Inc. NLGA ‐ National Lumber Grades Authority SPIB – Southern Pine Inspection Bureau WCLIB – West Coast Lumber Inspection Bureau WWPA – Western Wood Products Association 

 

c) Moisture content is listed in AREMA Table 7‐2‐13 per specie. 

 

d) Grade is listed in AREMA Table 7‐2‐13. Grade recommendations for railway lumber can be 

found in ASTM D 2555 and ASTM D245 (AREMA Ch. 7 Sec 1.4.1b). AREMA does not specify 

rough or surfacing of lumber, except for a note for dapping ties (Ch. 7 Sec. 1.13.7). 

 

e) The above agency/bureau certification of the mills is sufficient. List of certified mills can be 

found on the agencies’ websites. AREMA has some information regarding the agency/bureau, 

but is not practical to list here. Each State has its own and lists the mills which are certified 

depending on the species of wood. 

Page 19: 07302013 Notice - Questions & Answers FINAL - SCCRTC...replaced with clean ballast and compacted per AREMA Volume 1 ‐ Track, Chapter 1 – Roadway and Ballast, Section 2.0 Substructure

Notice – Questions & Answers ‐ Santa Cruz Branch Line Bridge Supports,  Repairs and Member Replacements Project 

May 20, 2013  

 

f) The above agency/bureau certification of the treatment plants is sufficient. AREMA 

provides some guidance toward the type of treatment to be used. Depending on the location 

of the treatment facility, there will be an agency/bureau with a list of certified treatment 

facilities. 

 

5. Q: What vertical height shall we assume the new retaining wall will be; the 4 to 5 feet it is currently or greater since at some locations it is supported from below?  A: The height of the wall would be approximately 4' to 5' in height. The wall is to be approximately 15' from centerline of the existing track alignment with top of wall even with top of tie.  

6. Q: Also what will the anticipated surcharge loading be; will it be cooper E‐80 loading or less?  

A: The surcharge loading would be Copper E‐80 loading.  

7. Q: Bid Items #29, #30 and #32 don’t seem to have a description of what work is entailed in Appendix G, as the other bid items not shown in the drawings have.   

 a) Can you please provide drawings of the typical walkway to be repaired under bid item #29 

and for the typical handrail to be repaired under bid item #30? The only description we have found is a brief reference in the questions and answers, shown below:  “Notes: 1. For walkway repairs, only damaged portions (i.e. holes, broken ledgers, etc.) need to be repaired. There is no total replacement. This is identified as a lineal foot item in the bid schedule.”  

b) Can you please provide a description of what bid item #32 covers?  Is the quantity “each” the same as per day in this usage? 

 A:  a) See the inspection reports in the reference documents for details on the handrail and 

walkway repairs.  The Bidder is to determine type and quantity of repair based on inspection reports, site visit of April 10th and bidder’s own site investigations.    

 b) Refer to Item 40. DELAYS, in the General Conditions, Pgs. 15‐16 for information on Bid 

Item #32.  The quantity “each” is the same as per day in this usage. [These page numbers are 16‐17 in the bid package with a due date of August 9, 2013.]