058 lean construction (part 2) construction productivity

24
[email protected] htt://www.construction-productivity.co.uk LEAN CONSTRUCTION

Upload: dr-fereidoun-dejahang

Post on 08-Jan-2017

42 views

Category:

Engineering


2 download

TRANSCRIPT

Page 1: 058 Lean Construction  (PART 2) Construction productivity

[email protected]://www.construction-productivity.co.uk

LEAN CONSTRUCTION

Page 2: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

In the past 50 years, manufacturing industries have greatly improved their competitiveness.

This has been achieved through the use of lean methods such as:

Supply Chain Management Just-In-Time techniques. Also, for several years lean methods have

been applied to the construction industry,

Page 3: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Lean construction is a process used to maximizes value and reduces waste.

Lean construction comes from Lean production.

It captures these objectives through the use of Supply Chain Management (SCM) and Just-In-Time (JIT) techniques,

Also, by sharing information between all the parties involved in the production process.

Page 4: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

It is based on lean manufacturing, of the Toyota Production system. developed by Taichii Ohno in the

1950s. Ohno learnt from mass production at

Ford Motor manufacturing facilities in the U.S. and witnessed high level of waste during production.

Page 5: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Ohno identified several wastes in mass production systems in car industry such as:

1. overproducing2. waiting time 3. transporting

Page 6: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

also, in other areas such as:1. processing methods; 2. unnecessary stock on hand; 3. unnecessary motion;4. defective goods; 5. failure to meet customers’ needs;6. high waste through out the

process.

Page 7: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

The Toyota Production System was based on the “Just –In – Time (JIT) philosophy;

The main objectives were: minimizing waste continuous improvement from

inception to completion with highly motivated work force

Page 8: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

The outcome was:reduced inventories High productivity better equipment

utilization of machinery shorter lead times

Page 9: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Less errors Highly motivated workforce with higher morale JIT is a pull system that responds to

actual customer demand. products are “pulled from ” the JIT

system.

Page 10: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

JIT only considers the resources required to meet the customer’s needs.

In the mid – 1970’s Toyota reduced the time needed to produce a car from fifteen days to one day, by using JIT.

Page 11: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Applying Lean Thinking in construction Using experienced design teams The same design team working on the design

of the project from beginning to end. Speed up the design process. Use innovative approaches to speed up the

design process. Innovative ideas in design and assembly. The use of pre-fabricated building elements. Manufactured off site and pre-assembled on

site.

Page 12: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Supporting sub-contractors in developing tools for improving processes.

In order to keep up with Leanconstruction It is important to follow the work of Construction Lean Improvement Programme (CLIP).

CLIP operates across the whole construction supply chain, from raw materials processors to clients.

Page 13: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Researchers believe that project cost will increase up to ten percent because of poor supply chain design.

Supply Chain Management (SCM) analyzes the impact of design on the construction process.

Through SCM, all parties are kept aware of commitments, schedules, etc.

Page 14: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

All the parties work for high quality product with minimal lead-time, including:

minimizing wastage; eliminating delays and disruptions.Ballard and Howell designed the

Last Planner System as one method for applying lean techniques to construction.

Page 15: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION Womack and Jones (1996) suggested

that there are five key principles that need to be monitored when lean construction systems are applied in construction. Those are:

Value-clarifying the customer’s needs; the supply chain involvement in all

stages, from inception to completion; By clarifying activities or products that signify value.

Page 16: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Value stream: By mapping thewhole value stream establishing cooperation between

all parties involved; identifying and eliminating waste; From taking such steps the

construction process can be improved.

Page 17: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Flow: Business flow includes project

information such as:1. specifications 2. contracts 3. plans, etc. Job site flow involves the activities and

the way they have to be carried out. Supply flow refers to the materials

used in a project.

Page 18: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Pull: The efforts of all participants

provides smooth pulls during the construction process.

Perfection: Use of best methods of work

instructions and best procedures. Introduction of best quality control

methods.

Page 19: 058 Lean Construction  (PART 2) Construction productivity

Current practice V lean construction CURRENT LEAN

Construction management is either activity or contract centred

Coordination between organizations or crews is primarily controlled from a central plan

that central plan establishes sequence and determines when an activity starts/finish

in lean production, the production is managed in a manor that the main objective is best product at lowest cost for customer

Project duration and cost are considered in “project-as-production system” terms

project total cost and duration are more important than the cost or duration of an activity

Page 20: 058 Lean Construction  (PART 2) Construction productivity

Current practice V lean construction CURRENT LEAN

costs, errors, and learning occur while work in progress

cost savings results from productivity improving

Often not achievable resulting in cost, time overrun

project duration is cut short by increasing manpower, machinery,

by adding additional activities to reduce time

Coordination is accomplished in

general by the central schedule

the details of work flow are managed throughout the organization by people who are project goals orientated

Time, cost, quality,..

Page 21: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION CURRENT LEAN

Additional cost due to waste

which could have been avoided within the activities,

Delays and disruption which could have been avoided within activities,

customers are valued highly,

primary objectives is the

work flow, Movement of

information, good

communication amongst all,

Movement of materials,

Page 22: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION CURRENT LEAN

rework which could have been avoided,

all add to total time of the project,

disrupt in critical path

Increases time and cost,

Waste control, Highly

motivated work force,

Removal of hygiene factors (de-motivating factors),

Page 23: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Lean thinking forces attention on how value is generated rather than how any one activity is managed.

An overall success.

Page 24: 058 Lean Construction  (PART 2) Construction productivity

LEAN CONSTRUCTION

Just-In-Time(JIT)

Supply ChainManagement

(SCM)

Business FlowPull

Perfection

LeanConstruction

maximizes valuereduceswaste

Based on LeanManufacturing, of the Toyota

Production system

JIT onlyconsiders the

Resourcesrequired

Construction LeanImprovement Programme

(CLIP),(Supply chain)

High quality product with minimallead-time

Eliminating delays and disruptions