05 project management
TRANSCRIPT
-
7/31/2019 05 Project Management
1/10
Project Management
1
What is a PROJECT?
A project is a means to achieve an end in
harmony with the development process of the
organization.
It is a process where the resources are invested
with a view to developing assets, acceptable
within quality specifications, required to be
used later on by the organization.
-
7/31/2019 05 Project Management
2/10
Project Management
2
What are the usual characteristics of a Project?
A Project is characterized by a complex set of activities that
must be performed in a particular order within the given periodand within the given expenditure.
Each project has a definite beginning and a definite end.
Requirement of resources for project execution is not
uniform.
Operations are carried out in fixedposition type of layout.
A project involves many tasks, each having its own
specialization to be performed by different agencies.
Since there are a large no. of activities, involvement of
different agencies and strict precedence requirements,
scheduling and control assume great importance.
Delays in execution lead to high cost overruns.
-
7/31/2019 05 Project Management
3/10
Project Management
3
What is PROJECT MANAGEMENT?
Project Management is a scientific way of
planning, implementing, monitoring and
controlling the various aspects of a project.
The objective is to achieve the basic goals set
forth while formulating a project.
It involves the coordination of group activity
where the Project Manager plays a very vital
role.
-
7/31/2019 05 Project Management
4/10
Project Management
4
Objectives of PROJECT MANAGEMENT
To achieve efficiency & effectiveness.
To attain customer satisfaction.
-
7/31/2019 05 Project Management
5/10
Project Management
5
Techniques of Project Scheduling
Bar Chart or Gantt Chart Method of Scheduling (developed by Henry Gantt)
Simple Bar Chart
Modified Bar Chart
Network Techniques of Scheduling
Critical Path Method (CPM)
Project / Programme Evaluation & Review Technique (PERT)
Critical Path Sequencing (CPS)
Resource Allocation & Multi-Project Scheduling (RAMPS)
Least Cost Estimating & Scheduling (LESS)
-
7/31/2019 05 Project Management
6/10
Project Management
6
What is a NETWORK?
A NETWORK is a diagrammatic representation of
all the activities involved in a Project, portraying
the mutual inter-relationship amongst the
activities, indicating the point of start of the Projectand the various paths or chains of activities
through which the project programme progresses,
being finally culminating at a particular point,
declaring the completion of a Project.
-
7/31/2019 05 Project Management
7/10
Project Management
7
Introduction to Network Techniques
A NETWORK is a set of nodes and arcs. When the arcs are directed, i.e.,
when the arcs have an arrow head and a tail head, then the corresponding
network is called a directed network (eg., water network), else it is called a
non-directed network (eg., road network).
We represent a Project as a directed network.
The activity-on-node system requires that each activity is represented by a
node.
The activity-on-arc requires that each arrow represents something that has
to be done the job, the operation, the activity etc.
The tail of the arrow represents the commencement of the activity and the
head represents its completion. Since this is a logic model, the scale is of no
importance.
-
7/31/2019 05 Project Management
8/10
Project Management
8
Network Elements
An event is defined to be the junction of two or more no. of activities.
Initial Event Intermediate Event Terminal Event
The arrowheads connecting two events are termed as activities. The duration
of each activity is shown over the activity arrowhead.
Ti j
i-j is an activity and Ti j is the time for completion of that activity.
-
7/31/2019 05 Project Management
9/10
Project Management
9
Errors in Network Logic
1. Looping Error
2. Dangling Error
3. Logical Error
Activity 3-4 is dependent on 1-3
and activity 3-5 is dependent on
activities 1-3 and 2-3.
-
7/31/2019 05 Project Management
10/10
Project Management
10
Fulkersons Rule of Numbering Network Events
1. Start from the initial event give it the first number 1.
2. Proceed to each event in sequence and delete the path by which
you reach to that event.
3. If by such process of deletion, that event turns into an initial
event, give it the next higher number. If there is a tie, any one of
the events can be given the next higher number and the
remaining one the still next higher number and so on.
4. Adopt steps 2 and 3 until all the events are numbered.