05 project management

Upload: tanveerhussain9

Post on 05-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 05 Project Management

    1/10

    Project Management

    1

    What is a PROJECT?

    A project is a means to achieve an end in

    harmony with the development process of the

    organization.

    It is a process where the resources are invested

    with a view to developing assets, acceptable

    within quality specifications, required to be

    used later on by the organization.

  • 7/31/2019 05 Project Management

    2/10

    Project Management

    2

    What are the usual characteristics of a Project?

    A Project is characterized by a complex set of activities that

    must be performed in a particular order within the given periodand within the given expenditure.

    Each project has a definite beginning and a definite end.

    Requirement of resources for project execution is not

    uniform.

    Operations are carried out in fixedposition type of layout.

    A project involves many tasks, each having its own

    specialization to be performed by different agencies.

    Since there are a large no. of activities, involvement of

    different agencies and strict precedence requirements,

    scheduling and control assume great importance.

    Delays in execution lead to high cost overruns.

  • 7/31/2019 05 Project Management

    3/10

    Project Management

    3

    What is PROJECT MANAGEMENT?

    Project Management is a scientific way of

    planning, implementing, monitoring and

    controlling the various aspects of a project.

    The objective is to achieve the basic goals set

    forth while formulating a project.

    It involves the coordination of group activity

    where the Project Manager plays a very vital

    role.

  • 7/31/2019 05 Project Management

    4/10

    Project Management

    4

    Objectives of PROJECT MANAGEMENT

    To achieve efficiency & effectiveness.

    To attain customer satisfaction.

  • 7/31/2019 05 Project Management

    5/10

    Project Management

    5

    Techniques of Project Scheduling

    Bar Chart or Gantt Chart Method of Scheduling (developed by Henry Gantt)

    Simple Bar Chart

    Modified Bar Chart

    Network Techniques of Scheduling

    Critical Path Method (CPM)

    Project / Programme Evaluation & Review Technique (PERT)

    Critical Path Sequencing (CPS)

    Resource Allocation & Multi-Project Scheduling (RAMPS)

    Least Cost Estimating & Scheduling (LESS)

  • 7/31/2019 05 Project Management

    6/10

    Project Management

    6

    What is a NETWORK?

    A NETWORK is a diagrammatic representation of

    all the activities involved in a Project, portraying

    the mutual inter-relationship amongst the

    activities, indicating the point of start of the Projectand the various paths or chains of activities

    through which the project programme progresses,

    being finally culminating at a particular point,

    declaring the completion of a Project.

  • 7/31/2019 05 Project Management

    7/10

    Project Management

    7

    Introduction to Network Techniques

    A NETWORK is a set of nodes and arcs. When the arcs are directed, i.e.,

    when the arcs have an arrow head and a tail head, then the corresponding

    network is called a directed network (eg., water network), else it is called a

    non-directed network (eg., road network).

    We represent a Project as a directed network.

    The activity-on-node system requires that each activity is represented by a

    node.

    The activity-on-arc requires that each arrow represents something that has

    to be done the job, the operation, the activity etc.

    The tail of the arrow represents the commencement of the activity and the

    head represents its completion. Since this is a logic model, the scale is of no

    importance.

  • 7/31/2019 05 Project Management

    8/10

    Project Management

    8

    Network Elements

    An event is defined to be the junction of two or more no. of activities.

    Initial Event Intermediate Event Terminal Event

    The arrowheads connecting two events are termed as activities. The duration

    of each activity is shown over the activity arrowhead.

    Ti j

    i-j is an activity and Ti j is the time for completion of that activity.

  • 7/31/2019 05 Project Management

    9/10

    Project Management

    9

    Errors in Network Logic

    1. Looping Error

    2. Dangling Error

    3. Logical Error

    Activity 3-4 is dependent on 1-3

    and activity 3-5 is dependent on

    activities 1-3 and 2-3.

  • 7/31/2019 05 Project Management

    10/10

    Project Management

    10

    Fulkersons Rule of Numbering Network Events

    1. Start from the initial event give it the first number 1.

    2. Proceed to each event in sequence and delete the path by which

    you reach to that event.

    3. If by such process of deletion, that event turns into an initial

    event, give it the next higher number. If there is a tie, any one of

    the events can be given the next higher number and the

    remaining one the still next higher number and so on.

    4. Adopt steps 2 and 3 until all the events are numbered.