05) offshore marine spread duration (topsides & bridges)

1
OFFSHORE MARINE SPREAD - DECK and BRIDGE INSTALLATION Kharg Island Gas Gathering and NGL Recovery Project C-1285 Name Duration From To Idle For Name Duration Idle for Name Duration From To Idle For 1 Barge Modifications Sascha 17 Preparation @ GPC 2 Mobilization Sascha TB1 m TB2 + TB3 m Sub-con GPC 3 Loadout & Seafastening Sascha 5 At GPC Yard TB1 5 4 Transport Sascha 5 GPC AB Site TB1 5 TB2 + TB3 5 GPC AB Site 5 Floatover Sascha 2 At AB Site TB1 2 TB2 + TB3 2 At AB Site 6 Transport Sascha 5 AB Site GPC TB1 5 TB2 + TB3 5 AB Site GPC 7 Demobilization Sascha 8 Subtotal Sascha 34 days TB1 17 days TB2 + TB3 12 days +m 9 Loadout & Seafastening Sascha 5 At GPC Yard TB1 5 TB2 + TB3 5 At B Site 10 Transport Sascha 5 GPC B Site TB1 5 TB2 + TB3 5 At B Site 11 Floatover Sascha 2 At B Site TB1 2 TB2 + TB3 2 At B Site 12 Transport Sascha 5 B Site GPC TB1 5 TB2 + TB3 5 B Site GPC 13 Demobilization Sascha d GPC Other Jobs TB1 d TB2 + TB3 d GPC Sub-con 14 Subtotal Sascha 17 days +d TB1 17 days TB2 + TB3 17 days +d Name Duration From To Idle For Name Duration From To Idle For 15 Mobilization Crane Barge m Sub-con GPC CB1 + TB5 m Sub-con GPC 16 Loadout & Seafastening of AB & B Bridges CB1 + TB5 5 At GPC Yard 17 Transport to AB Field Crane Barge 5 GPC AB Site CB1 + TB5 5 GPC AB Site 18 AB Bridge Installation Crane Barge 2 At AB Site CB1 + TB5 2 At AB Site 19 Misc. Installation Works Crane Barge 10 At AB Site CB1 + TB5 10 At AB Site 20 Demobilization from AB Field Crane Barge 1 AB Site B Site CB1 + TB5 1 AB Site B Site 21 Subtotal Crane Barge + TB4 18 days CB1 + TB5 23 days +m 22 Transport to B Field Crane Barge 1 AB Site B Site CB1 + TB5 1 AB Site B Site 23 B Bridge Installation Crane Barge 2 At B Site CB1 + TB5 2 At B Site 24 Misc. Installation Works Crane Barge 5 At AB Site CB1 + TB5 7 At AB Site 25 Transport Crane Barge 7 B Site GPC CB1 + TB5 5 B Site GPC 26 Demobilization Crane Barge d GPC Other Jobs CB1 + TB5 d GPC Sub-con 27 Subtotal Crane Barge + TB4 15 days +d CB1 + TB5 15 days +d Conclusion: Summary of Durations Sascha 51 days +m+d TB1 34 days TB2 + TB3 29 days +m+d Crane Barge + TB4 33 days +m+d +m+d CB1 + TB5 38 days +m+d Sascha - Float over Vessel Floatover of Topsides TB - Supporting Boat Tugboats - for Float over Assistance AB-GCP Deck B-GCP Deck Operation Lifting of Bridge & Other Misc. Installation Works Activity (in days) CRANE / Accomodation Barge + TB4 CB1 (Cargo Barge) + TB5 B-GCP Bridge (73 meters long) Sr. No. Operation AB-GCP Bridge (28 meters long) Structure Structure Sr. No. Activity (in days) Filename: Offshore Marine Spread Duration - Contract Scope Date: 27 Nov. 2008 Page 1 of 1

Upload: yusuf

Post on 18-Nov-2015

14 views

Category:

Documents


1 download

DESCRIPTION

Offshore Marine Spread Duration

TRANSCRIPT

  • OFFSHORE MARINE SPREAD - DECK and BRIDGE INSTALLATIONKharg Island Gas Gathering and NGL Recovery Project C-1285

    Name Duration From To Idle For Name Duration Idle for Name Duration From To Idle For1 Barge Modifications Sascha 17 Preparation @ GPC2 Mobilization Sascha TB1 m TB2 + TB3 m Sub-con GPC3 Loadout & Seafastening Sascha 5 At GPC Yard TB1 54 Transport Sascha 5 GPC AB Site TB1 5 TB2 + TB3 5 GPC AB Site5 Floatover Sascha 2 At AB Site TB1 2 TB2 + TB3 2 At AB Site6 Transport Sascha 5 AB Site GPC TB1 5 TB2 + TB3 5 AB Site GPC7 Demobilization Sascha8 Subtotal Sascha 34 days TB1 17 days TB2 + TB3 12 days +m9 Loadout & Seafastening Sascha 5 At GPC Yard TB1 5 TB2 + TB3 5 At B Site

    10 Transport Sascha 5 GPC B Site TB1 5 TB2 + TB3 5 At B Site11 Floatover Sascha 2 At B Site TB1 2 TB2 + TB3 2 At B Site12 Transport Sascha 5 B Site GPC TB1 5 TB2 + TB3 5 B Site GPC13 Demobilization Sascha d GPC Other Jobs TB1 d TB2 + TB3 d GPC Sub-con14 Subtotal Sascha 17 days +d TB1 17 days TB2 + TB3 17 days +d

    Name Duration From To Idle For Name Duration From To Idle For15 Mobilization Crane Barge m Sub-con GPC CB1 + TB5 m Sub-con GPC

    16 Loadout & Seafastening of AB & B Bridges CB1 + TB5 5 At GPC Yard

    17 Transport to AB Field Crane Barge 5 GPC AB Site CB1 + TB5 5 GPC AB Site18 AB Bridge Installation Crane Barge 2 At AB Site CB1 + TB5 2 At AB Site19 Misc. Installation Works Crane Barge 10 At AB Site CB1 + TB5 10 At AB Site20 Demobilization from AB Field Crane Barge 1 AB Site B Site CB1 + TB5 1 AB Site B Site

    21 Subtotal Crane Barge + TB4 18 days CB1 + TB5 23 days +m

    22 Transport to B Field Crane Barge 1 AB Site B Site CB1 + TB5 1 AB Site B Site23 B Bridge Installation Crane Barge 2 At B Site CB1 + TB5 2 At B Site24 Misc. Installation Works Crane Barge 5 At AB Site CB1 + TB5 7 At AB Site25 Transport Crane Barge 7 B Site GPC CB1 + TB5 5 B Site GPC26 Demobilization Crane Barge d GPC Other Jobs CB1 + TB5 d GPC Sub-con

    27 Subtotal Crane Barge + TB4 15 days +d CB1 + TB5 15 days +d

    Conclusion: Summary of Durations Sascha 51 days +m+d TB1 34 days TB2 + TB3 29 days +m+dCrane Barge

    + TB4 33 days +m+d +m+d CB1 + TB5 38 days +m+d

    Sascha - Float over VesselFloatover of Topsides

    TB - Supporting Boat Tugboats - for Float over Assistance

    AB-GCP Deck

    B-GCP Deck

    Operation Lifting of Bridge & Other Misc. Installation WorksActivity

    (in days)CRANE / Accomodation Barge + TB4 CB1 (Cargo Barge) + TB5

    B-GCP Bridge (73 meters long)

    Sr. No.

    Operation

    AB-GCP Bridge (28 meters long)

    Structure

    Structure Sr. No.Activity

    (in days)

    Filename: Offshore Marine Spread Duration - Contract ScopeDate: 27 Nov. 2008 Page 1 of 1