04 wd ff sf plans - ceredigion-online.tascomi.com
TRANSCRIPT
LLAWR CYNTAF
first floor 1.50
AIL LAWR
second floor 1.50
CAWOD
shower
YSTAFELL GYSGU 2
bedroom 2
YSTAFELL GYSGU 1
bedroom 1
GEGIN/BYW
kitchen/living
YSTAFELL GYSGU 1
bedroom 1
CAWOD
shower
BYW/BWYTA
living/dining
GEGIN
kitchen
YSTAFELL GYSGU 1
bedroom 1
YSTAFELL GYSGU 2
bedroom 2
FLAT 3
FLAT 4
up
up
up
FLAT 3
access
FLAT 4
access
up
0M 1M 2M 3M 4M 5M 6M
PARTITIONS
All internal partitions indicated thus to be formed of
15mm plasterboard to both sides of a mass per unit
area of 10kg/sqm, 89mm thick studs with a 30mm
Rockwool RWA45 semi rigid slabs laid between the
studs.
COMPARTMENT FLOOR UPGRADING
Carefully remove the existing skirtings and store on
site for re-use.
FLOOR
Carefully remove the existing floor boards and store on
site for re-use. Onto the existing joists lay Gyproc
Gypframe SIF2 channels complete with a resilient
strip. Do not mechanically fix channels to joists.
Lay 19mm Gyproc plank laid between existing floor
joists supported on Gypframe channels.
Onto Gyproc plank lay one layer of Tecsound 50
sound insulating layer in strict accordance with
manufacturers recommendations. Tuck Tecsound 50
insulating layer up behind the skirting by 150mm.
Between the existing joists lay one layer of 100mm
mineral wool insulation of 60/kg per m3 density.
FIREPROOFING
Compartment floors to have a 60 minute fire
resistance using the following method.
All products are from the Envirograf product range.
Clean off any existing ceiling paper and scrape off any
loose paint. If gloss paint rub down and coat with
Product 93 ES/Stabond. Ensure that all distemper is
removed from the ceilings.
Seal off all cleaned ceilings with Product
93ES/Stabond to aid adhesive not to dry out due to
ceiling absorbing moisture.
Cut the Product 84 Envirograf S/Ceiling intumescent
cloth to size and apply to ceiling, applying the
adhesive using a comb float.
Apply a coat of CA/N adhesive to the ceiling using a
serrated edged application. Use a clean scraper and
roll with a paper type roller the S/Ceiling paper onto
the ceiling.
Emulsion paint the ceiling after 2-3 hours. Note the
white side of the S/Ceiling product to be fixed to the
adhesive.
Fix in strict accordance with manufacturers
instructions. If in doubt call 01304 842555
CORNICE FIRE PROTECTION
All cornices to the ground floor to be protected by
infilling all cracks with Envirograph Intumescent
cement Product 63 or mastic Product 58.
Apply 2 coats of EP/CP intumecent coatings to the
cornice. If it will not adhere apply a PVA adhesive
coating at
50
50
ratio adhesive to water. Apply at a rate of
8m sq per litre.
HOT WATER SYSTEMS
Should an unvented hot water system be used then
the installer must be registered with a competent
person scheme, a copy of the Building Regulations
certificate of compliance will be necessary.
PART M
All entrance lobbies to comply with the
requirements set out in paragraph 2.29,
Approved Document M
All internal doors noted with VP , vision
panels to have glass that are within the
zone of 500mm and 1500mm above the
floor, if necessary interrupted between
800mm and 1150mm above the floor.
KITCHEN AND FOOD PREPARATION AREAS
As indicated on drawing and where applicable,
contractor to ensure that suitable sink is provided to all
kitchen and food preparation areas. Refer to notes
elsewhere for details on water supply, wastes and
ventilation to such rooms.
FAN DUCT
Ensure that duct length does not exceed
manufacturers recommendations. Supply and fix
condensation traps to suit.
SOIL STACK
To positions shown on floor plans allow for installing
110mm dia soil / stub stacks for connection of internal
drainage. All stacks to connect to 100mm dia drains at
base. Soil stacks required for ventilating to be taken up
to roof level and terminate via Glidevale Premier slate
ventilator fitted to manufacturers recommendations.
Stub stacks to be approx 1100mm high and
terminated wth Air Admitance Valve. All stubs and
stacks to be fitted with rodding access points at base.
WHITE GOODS
Exact choice of sanitary ware and associated taps,
traps and brassware to be confirmed by client.
Contractor to allow for extending hot and cold services
to appliances as required and install upvc wastes as
detailed elsewhere on drawing.
BACKGROUND VENTILATION
Background ventilation to be provided to the building
at the following rates:
Habitable rooms- min 5000mm2
Wet Rooms - min 2500mm2
[kitchen, bath, w.c]
Background ventilation to be provided in the form of
trickle ventilatiors fitted to windows. Where extract
fans and trickle ventilators are provided in the same
room, they should be a minimum of 500mm apart.
To aid air movements through the building an undercut
of minimum 7600mm2 area is to be provided to the
underside of all internal doors, i.e. typically 10mm for a
760mm door width.
SOIL STACK SURROUND
Stacks to be surrounded with quilt insulation and
13mm plasterboard and skim finish on 25 x 50mm
softwood treated framing.
HEATING
Heating throughout property to be of electric boiler and wet
radiator system, sized by the installer or electric panel
radiators. Installation to comply with following the guidance
in the 'Domestic Building Services compliance Guide and
Non-Domestic Building Services Compliance Guide.
Forward details of the system to the BCO.
HEATING
The system installed must be commissioned so that on
completion the system and its controls are left in
working order.
TIMING CONTROLS
Timing devices should be provided to control the
periods when the heating system is in operation
GLAZING
All glazing in critical areas to comply with BS 6206 and
be clearly marked. Critical areas refer to.
1. Between finished floor levels and a height of
800mm.
2. Between finished floor level and 1500mm in a door
or a side panel or close to the edge of a door.
WINDOWS
Ensure that all upper floor windows are suitable for
use as an emergency escape window. I.e.
unobstructed openable area of 0.33 sq. m and at least
450mm high x 450mm wide.
FIRE LOCKS
All principal doors to the bedrooms and any escape
doors must be fitted with suitable fire locks/latches that
do not need the use of a key to operate. Such a device
is a thumb turn mechanism.
EMERGENCY LIGHTING
Electrical contractor to install emergency lighting
system in accordance with BS5266, Part 1, 1988
capable of maintaining illumination for at least 3 hours.
ELECTRICAL
All work to be carried out by an approved contractor
registered with the NICEIC and a completion certificate
to be supplied once work is finished.
Any new socket outlets and switches to be located in a
zone between 450mm and 1200mm from finished floor
level.
FIRE DETECTION SYSTEM
Allow for installing fire detection system consisting of
smoke/heat detectors. All detectors to be wired back to
a zone panel and to be combined alarm sounder type.
Installer must provide system designed and approved
by manufacturer in accordance with BS 5839-6:2004 to
at least grade D, category LD3 system.
System indicated on the drawings is diagrammatic only
and should not be assumed that it complies with
current NICEIC regulations.
PLASTERBOARDS
All plasterboards to all bathrooms, shower rooms etc to
be of moisture resistant with the identification marks
facing upwards to show compliance.
CHIPBOARD
All chipboard used in bathrooms and shower rooms
must be moisture resistant with the identification marks
facing upwards to show compliance.
ELECTRICAL SWITCHES.
All light switches and socket outlets must be located in
a zone 450mm to 1200mm from floor finish.
LIGHTING.(luminous efficiency to be greater than 40).
Supply and fix energy efficient light fittings throughout
the property, non ballasted fittings, with an energy
efficient bulb. All external fittings to be energy efficient
type.
INTERNAL PIPEWORK
Contractor to allow for all required plumbing work to
extend hot and cold water services to all new sanitary
furniture etc. Works to include for all valves, controls
and pipe lagging etc.
KITCHEN UNITS
Kitchen installation to be of clients choice. Contractor to
allow for all plumbing and wastes to sink locations as
shown, and as described elsewhere on drawing.
LIGHT FITTINGS
Electrical contractor to ensure that ALL light fittings are
energy efficient items, such as fluorescent lamps
having a luminous efficiency greater than 40 lumens
per circuit-Watt.
External lighting to also be of similar efficiency items.
CONDENSATION IN ROOFS
Where services e.g. 100 soil and vent pass through the
roof void the junction at the ceiling should be
adequately sealed
FALSE ALARMS
Fire detection installer to provide details on what
arrangements are within the system to deal with false
alarms thus to avoid disturbances to others.
WASTE PIPES
Max length of all waste branches and minimum falls in
mm per m to be as follows.
WC, 100mm dia, max length 6m, fall 18mm per m,
WHB, 32mm dia, max length 1.7m fall between 20mm
per m.
SINK, 40mm dia, max length 3m, fall between
18/90mm per m.
BATH, 40mm dia, max 3m length, fall between
18/90mm per m
For full guidance refer to Approved Document H1,
diagram 3
BATHROOMS
As indicated on drawing, each flat must contain at least
one bathroom/ shower room, fitted with a wash basin
and either a fixed bath or shower. Refer elsewhere on
drawing for details on water supply, wastes and
ventilation to such rooms.
EXISTING FITTINGS
Carefully remove all the existing sanitary fittings,
plumbing, wastes and kitchen units and cart off site.
Make good and cap off all services as necessary.
O8. WASTES
WHB - 75mm deep UPVC trap, into 32mm dia waste
into stack via "Marley" collar boss.
W.C - 100mm pan connector into 110mm UPVC
branch into stack via "Marley" collar boss.
Bath - Combined overflow and waste into 36mm dia
waste, onto stack via "Marley" collar boss.
Sink - 75mm deep UPVC trap, into 38mm dia waste
into rodable back inlet trapped hopper or connected
into stack via boss connection.
HEATING
Heating to all flats to be from a new electricity boiler
located in each flat. Exact location to be discussed on
site with the client. Boiler to power a wet radiator
system. Agree locations of radiators with client.
fan
WALLS
Carefully remove the existing partition walls
shown in a broken red line and cart away from
site. Make good to all areas disturbed.
LATH AND PLASTER WALLS
All walls shown thus
are original lath and plaster walls that
are being retained.
ROOFLIGHT
Denotes new velux emergency
smoke release rooflight code GGU
MK08, 780 x 1398mm fitted in strict
accordance with manufacturers
recommendations. Allow for all
work in connecting into the fire
detection system. Due to restricted
space the opening area of the
rooflight is 0.72 sqm
GENERAL NOTES
DO NOT SCALE THESE DRAWINGS
It is the Contractors
responsibility to verify all
dimensions on site prior to
proceeding with the works
DIMENSIONS
The figured metric dimensions
to be worked, to, wherever given
\All dimensions unless expressly
noted otherwise are structural and
due allowance should be made
for finishes, plaster etc. Any
discrepancies between the drawing
and the works to be verified with
Architect before proceeding
PLANNING / BUILDING REGS
All work to be carried out in strict
accordance with the Planning
Permission and the current Building
Regulations, relating to materials
specifications and site practice and
performance, whether implied or
not on this drawing
MATERIALS & WORKMANSHIP
Unless otherwise stated, all materials
used in the carrying out of the works
must be materials which have been
tested or approved by an
independent third party. BSI British
Agreement Cert
TOOLS & HAZARDOUS MATERIALS
All tools, hazardous materials, toxic
substances or solvents must be used,
stored, in accordance with current
COSHH regulations
CDM REGULATIONS
Comply with all Health and Safety
Legislation. Whether implied or not on
this drawing or, generally throughout
the project, consideration must be
given to the use of the "safest"
materials and processes during the
construction of this building
s & vp
vertical
extract
fan duct
fan
s & vp
s & vp
fan
fanfan
EXTRACT FAN
To bathroom allow for connecting the fan into
a combined duct run vertically up through the
dwelling to terminate with a slate vent at roof
level. Supply and fix all bafflers as necessary.
Where the duct passes through the
compartment floors supply and fix a Quelfire
intumescent fire stop around the pipe, fitted in
strict accordance with the manufacturers
recommendations.
DRAIN
Allow for installing a new 100mm vertical soil stack as
indicated to run from the ground floor and terminated with
a soil stack slate at roof level. Allow for all work in
installing the stack. Where it abuts the existing cornice
DO NOT damage the cornice. At all compartment floor
junctions install a quelfire intumescent collar in strict
accordance with manufacturers recommendations.
On completion surround the stack in 50 X 50mm framing
finished with 12.5mm plasterboard and skim. At ceiling
level form new cornice to match the existing around the
entire duct casing.
EXTRACT FAN
To kitchen allow for connecting the fan into a
combined duct run vertically up through the
dwelling to terminate with a slate vent at roof
level. Supply and fix all bafflers as necessary.
Where the duct passes through the
compartment floors supply and fix a Quelfire
intumescent fire stop around the pipe, fitted in
strict accordance with the manufacturers
recommendations. Vertical extract duct to be
laid in same timber and plasterboard duct as
described below.
DRAIN
Allow for installing a new 100mm vertical soil stack as
indicated to run from the ground floor and terminated with
a soil stack slate at roof level. Allow for all work in
installing the stack. Where it abuts the existing cornice
DO NOT damage the cornice. At all compartment floor
junctions install a quelfire intumescent collar in strict
accordance with manufacturers recommendations.
On completion surround the stack in 50 X 50mm framing
finished with 12.5mm plasterboard and skim. At ceiling
level form new cornice to match the existing around the
entire duct casing.
WASTE
Waste from the kitchen sink to be taken along the
wall or between the floor joist if direction of span
allows and into the vertical stack.
EXTRACT FAN
To kitchen allow for connecting the fan into a
condensation trap and then into a flexible
ducting connected into a slate terminal.
STACK
Extend stack horizontally within roof void as shown
and then take vertically to terminate at a soil slate
vent at roof level. Connect all fittings to the branch
stack using correct bosses.
EXTRACT FAN
To shower room allow for connecting the fan
into a condensation trap and then into a
flexible ducting connected into a slate terminal.
VERTICAL STACKS
Allow for small radius bends to vertical stacks
as indicated at this floor level.
DWARF WALL
Existing dwarf wall structure and lath and plaster finish
to remain.
To areas shown thus:
Infill between the existing studs with 60mm Celotex
GA4060 high performance insulation board if access is
available from roof space side without removing the
existing lathing. Line internal face with Celotex PL4000
12.5mm plasterboard with 50mm insulation backing.
DWARF WALLS
Denotes existing lath and plaster dwarf walls to
remain as existing.
EXISTING WALLS
Walls shown thus
are existing plasterboard walls to be retained.
DWARF WALL
To be formed of 89 x 44 mm studs at 400mm
centres. Infill between the studs with 60mm
Celotex GA4060 high performance insulation
board. Line internal face with Celotex PL4000
12.5mm plasterboard with 50mm insulation
backing. Above to give a wall U value of 0./19.
STEPS
Carefully remove the existing small section of
steps shown in a broken red line and cart away
from site. Make good to all areas disturbed.
read this drawing in conjunction with
drawing 460/03
FD
20
S
up
gra
de
FD20S
upgrade
FD20S
upgrade
FD20S
upgrade
FD
20
S
up
gra
de
F
D
3
0
S
S
C
FD20SSCFD20SSC
FD
20
S
FD20S
upgrade
FD
20
S
up
gra
de
FD20S
upgrade
FD20S
upgrade
FD
30
SS
C
FIREPROOFING
During the works in the attic check the
fireproofing on the existing party wall between
the two properties. Infill any gaps with stone or
mineral wool fire stopping.
ROOFLIGHT
Allow for all work in preparing an
opening for the new smoke
rooflight.
s & vp
extract
fan duct
CYNLLUN MANWL
working drawing
460/04
1.50 @ A1
Ionawr 2020
byron
CYNLLUNIAU
plans and elevations
second and first floors
7 Laura Place,
Aberystwyth,
Ceredigion,
SY23 2AU
BYRON JENKINS MCIAT
YMGYNGHORI PENSAERNIOL A RHEOLAETH PROSIECTAU,
ARCHITECTURAL CONSULTANCY AND PROJECT MANAGEMENT
CAPEL AFAN, LLANAFAN, ABERYSTWYTH,
CEREDIGION SY23 4AY
01974 261145
07974 099884