04-n.j. gimsing

Upload: lamkinpark3373

Post on 10-Feb-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/22/2019 04-N.J. Gimsing

    1/14

    From Bridges across Great Belt and resund towards a Femern Belt Bridge

    Niels J GIMSINGProfesor Emeritus

    Techn. Univ. of DenmarkDK-2800 Lyngby, [email protected]

    Professor Emeritus at the

    Department of Civil Engineering.

    Participated in the design of theGreat Belt Bridge and the resundBridge, and acted as specialistdesign adviser on numerous bridgesaround the World . Co-owner ofGimsing & Madsen, ConsultingEngineers, Denmark.

    Summary

    In Denmark the construction of three major bridges was initiated in the 1990.s: Storeblt Bridge(Great Belt Bridge), resund Bridge and Femern Belt Bridge. The first two were completed in 1998

    and 2000, respectively, and the third is expected to be constructed during the second decade of the

    21st century. In both design and construction procedures a number of innovative features have been

    introduced.

    Keywords: Box girder bridge, suspension bridge, cable-stayed bridge, wind tunnel test, compositeaction.

    1. Introduction

    Denmark consists of the peninsula Jutland and

    406 islands, out of which 79 are inhabited. The

    second largest island, Funen, is separated from

    Jutland by the strait Little Belt and from the

    largest island, Zealand, by the strait Great Belt.

    In round figures 45% of the population lives in

    Jutland 10% on Funen and 45% on Zealand

    were the capital Copenhagen is situated.

    The substitution of ferry services by bridges

    across the straits separating the different parts ofDenmark began in 1935 with the opening of the

    bridge across the Little Belt and in 1937 with the

    opening of the Storstrm Bridge between

    Zealand and Falster. At the opening the 3.2 km

    long Storstrm Bridge was the longest in Europe.

    After the completion during the 1930.s of more

    than ten bridges across a number of the smaller

    straits in Denmark the country was virtually

    joined in two infrastructure units separated by

    the 18 km wide Great Belt.Fig. 1: Map of Denmark

  • 7/22/2019 04-N.J. Gimsing

    2/14

    Plans to build the final link - across the Great Belt - were worked out already in the late 1930.s but

    the outbreak of World War II and the subsequent post war period with lack of resources made it

    impossible to consider construction of a Great Belt Bridge for a period of more than twenty years.

    In 1978 the Great Belt Bridge was close to

    reach the construction stage based on adesign with either a 780 m cable stayed-

    bridge main span or a design with a 1416 m

    suspension bridge main span across the

    international navigation route between the

    Baltic Sea and the North Sea.

    The 1978 design never reached the

    construction stage as the government

    decided to give priority to a natural gas

    distribution net throughout the country.

    Finally in 1987 the Danish Parliament approved the construction of a fixed traffic link across the

    Great Belt but now in a different configuration from that of 1978. In stead of carrying both the road

    and the railway across the East Channel on a bridge it was decided to let the railway cross in a

    bored tunnel and only carry the motorway across on a bridge. Across the West Channel both road

    and railway should be on a bridge (as assumed in 1978) but in a different alignment.

    2. Great Belt Bridge

    The two bridges forming a part of the Great Belt crossing is the 6.6 km long West Bridge between

    Funen and Sprog and the 6.8 km long East Bridge between Sprog and Zealand.

    2.1 West BridgeThe West Bridge crosses domestic Danish waters without international restrictions regarding

    navigational requirements. The West Bridge could therefore be constructed as a low level bridge

    with a maximum vertical clearance of 18 m just to allow passage of coasters, fishing boats and

    leisure vessels [1].

    The most unique feature of the West Bridge is the

    extensive use of precast elements for both thesubstructure and the superstructure. The elements

    were cast on a work site area close to the bridge

    abutment on Funen. Five production lines were

    used to cast the caissons and the pier shafts as well

    as the box girders for the road and the rail

    superstructures.

    The huge precast elements with a weight of up to

    6000 tonnes (and slightly more) were moved onto a

    load-out pier where they could be picked up by the

    purpose built floating crane Svanen with a lifting

    Fig. 2: Design from 1978 for a suspension bridgewith a 1416 m main span for both road and railway

    Fig. 3: Casting yard on Funen

  • 7/22/2019 04-N.J. Gimsing

    3/14

    capacity of 6000 tonnes. As some of the largest caissons had a weight in excess of the lifting

    capacity they had to have their lower part submerged during transportation to utilize buoyancy.

    The superstructure of the West Bridge is divided

    into two parallel bridges with individual girders

    for the road and the railway, whereas the caissonsin the substructure are common for both bridges.

    The precast box girder elements have the full

    length of the span (110 m) reaching from midspsn

    to midspan. That allowed the floating crane to

    pick up the girder elements at the center as the

    post-tensioned reinforcement both in the

    construction phase and in the final stage would

    have the right position at the top of the girders

    above the supports.

    From erection of the first caisson to installatiom of

    the last box girder elements a period of only 25 months elapsed.

    2.2 East BridgeThe East Bridge crosses the international navigation route from the Baltic Seato the North Sea.Therefore, the bridge had to be designed so that the largest existing ships could pass safely through

    the large main span across the navigation channel [2].

    In 1978 it was believed that a 780 m span would be adequate to allow safe passage of the largest

    ships provided that it could be assured that the very large ships could be guided through the main

    span without encountering other ships in the immediate vicinity of the bridge. With a 1416 m span

    it was believed that ships could pass the main span without restrictions.

    Prior to tendering the East Bridge in 1990 a number of navigation studies were performed to ensure

    that the bridge would not affect the safe passage through the Great Belt of even the largest ships. In

    the meantime it also became clear that it would not be acceptable to impose one way passage of

    large ships through the main span.

    The final choice of the main span length of the East Bridge was based on manoeuvring simulations

    carried out at the Danish Maritime Institute. Here the navigational safety was studied for main spansof 900 m, 1200 m, 1400 m and 1600 m by having experienced pilots and ship captains to

    manoeuvre computer generated ships through the shipping lane under severe weather conditions.

    The result of the navigational studies was that only with a main span of 1600 m (and a vertical

    clearance of 65 m) could all the involved shipmasters agree that the bridge would have no

    decremental effect on safe passage.

    2.2.1 Approach spans

    On either side of the 2700 m long suspension bridge approach bridges with lengths of 1600 m and

    2500 m, respectively, have been constructed as continuous box girders in steel.

    Fig. 4: The floating crane Svanen with aprecast element for the roadway

    superstructure

  • 7/22/2019 04-N.J. Gimsing

    4/14

    As for the West Bridge full span prefabricated elements were erected for the approach spans of the

    East Bridge. However, due to application of steel the weight of a 193 m long girder element was

    only 2500 tonnes in stead of the 5800 tonnes weight of the 110 m long precast elements of the West

    Bridge.

    The steel girders for the East Bridgeapproach spans were fabricated in Italy

    and assembled into 193 m long erection

    units on a work site area at Aalborg in

    Denmark. From here they were

    transported on a barge to the bridge site

    and lifted onto the piers by two cranes

    positioned at either end of the erection

    unit.

    The extreme end of the erection unit was

    initially supported 4 m above the final level of the bearing and in this position the continuity at theother end was completed by site welding. Subsequently, the girder was lowered onto the final

    bearing and by this procedure it was ensured that continuity would also be achieved for the dead

    load of the steel girders.

    During the detailed design of the East Bridge it was discovered that vortex excited oscillations of

    the slender approach span girders with a depth-to-span ratio around 1/25 could be experienced even

    for cross winds with a velocity of less than 25 m/sec. These vibrations would not endanger the

    structural integrity of the bridge but could result in discomfort by the users of the bridge. It was,

    therefore, decided to install large tuned mass dampers to eliminate all oscillations for wind speeds

    below 25 m/sec. For wind speeds above 25 m/sec the bridge would in any case be closed to all

    traffic so user comfort did not have to be considered.

    Besides the tuned mass dampers a number of dehumidification plants are also installed inside the

    box girders to exclude corrosion and make interior painting superfluous. This system was for the

    fist time used in the box girder of the Little Belt suspension bridge from 1970 and has since then

    been used intensively around the world as a most efficient way to exclude corrosion inside major

    box girders.

    2.2.2 Anchor Blocks

    The anchor blocks of the East Bridge are located farfrom the coasts at open sea and they are therefore

    very visible compared to anchor blocks on land

    where they can be partly hidden behind vegetation

    and buildings.

    It was, therefore, important to arrive at a less

    massive appearance than found in many existing

    anchor blocks.

    The anchor blocks are founded at a water depth of

    approximately 10 m on 122 m long and 55 m wide precast concrete caissons. The upper visible partof the anchor blocks are cast in situ.

    Fig, 5: Erection of a 193 m long box girder element forthe East Bridge approach spans

    Fig. 6: Anchor block of the East Bridge

  • 7/22/2019 04-N.J. Gimsing

    5/14

    2.2.3 Pylons

    The two pylons reach a height of 254 m making them the

    highest concrete pylons in the world at the time of construction.

    The pylons are designed with a very simple and cleanappearance characterised by just two cross beams between the

    quasi-vertical legs. In contrast to other large suspension bridges

    there is no cross beam immediately below the deck but half way

    to the top.

    In situ casting was chosen as slipforming was abandoned by the

    client and prefabrication of segments was unattractive due to

    weight problems.

    The batching plants were located on a work site area on Zealand

    and transported to the pylons by truck mixers on ferry boats.After arrival at the pier the mixed concrete was pumped to the

    top of the pylon and cast into the jump form.

    In each pylon the total quantity of concrete amounted to nearly

    40,000 m3.

    2.2.4 Cables

    Each main cable contains 18.648 galvanised wires with a minimum tensile stress of 1570 MPa and

    a diameter of 5.38 mm.

    Both the air-spinning method and the PPWS method was allowed by the client during bidding but

    only the air-spinning method proved to be competitive [3].

    2.2.5 Deck

    The deck of the suspension bridge consists of a slender box girder in steel with a depth of 4.3 m and

    a width of 31 m. It was fabricated in Italy in 48 m long segments and transported on a barge to

    Denmark.

    With a span approximately 15% longer than that of the

    Humber Bridge there were special concerns aboutaerodynamic stability as past experience had indicated

    that the critical wind speeds for bridges with a mono-

    box deck would diminish as the span was increased.

    Initially the wind tunnel tests were performed on

    section models with different cross sectional layouts to

    determine a suitable configuration.

    The section model tests indicated that it would be

    possible to achieve the required critical flutter wind

    speed of more than 60 m/sec with the mono-box but to give a further verification of the adequacy itwas decided to test a full aeroelastic model in a scale of 1:200. As the continuous box forming the

    Fig. 7: Pylon under construction

    Fig. 8: Full bridge model in wind tunnel

  • 7/22/2019 04-N.J. Gimsing

    6/14

    deck of the suspension bridge is 2700 m long it was necessary to build a special 14 m wide wind

    tunnel at the Danish Maritime Institute.

    The result of the extensive wind tunnel tests was a critical flutter wind speed of 72 m/sec,

    comfortably higher than the limit of 60 m/sec. However, this was for a model with an open railing,

    but the client also wanted to know the influence of adding wind screens to improve the user comfort.

    Adding wind screens proved to have a decisive effect

    as it reduced the critical flutter wind speed to 62 m/sec.

    In contrast to the majority of existing suspension

    bridges the deck of the Great Belt suspension bridge is

    continuous from one anchor block to the other - and

    with only lateral support at the pylons.

    The omission of a pylon cross beam below the deck

    and the continuity of the steel box clearly exhibits thefact that the vertical load of the deck is transferred to

    the main cables through the hanger cables.

    3. resund Bridge

    The bridge constituting the eastern part of the resund Link has a total length of 7845 m and it

    consists of three main sections: the western approach bridge with a length of 3014 m; the main

    bridge (over the navigation channel) with a length of 1092 m; and the eastern approach bridge with

    a length of 3739 m.

    Fig. 10: The resund Bridge

    .Across the navigation channel the main span has a length of 490 m and a vertical clearance (air

    draught) of 56 m.

    The bridge is the longest cable-stayed bridge in the world with both road and railway traffic, and it

    is also one of the largest composite structures ever built [4].

    3.1 Approach bridges

    The two approach bridges have a combined length of 6753 m which constitutes approximately 85%

    of the total length of the bridge. It was, therefore, evident from the initial design phase that the

    emphasis should be laid on arriving at an optimum solution for these spans.

    Fig. 9: Deck at pylon

  • 7/22/2019 04-N.J. Gimsing

    7/14

    A double deck configuration offered the advantage of separating the train and automobile traffic

    and at the same time the required stiffness would be achieved through the large structural depth

    imposed by the clearance requirements above the railway tracks.

    The double deck arrangement naturally leads to a structure with steel trusses between the two decks

    which in turn can be incorporated as chords to achieve maximum structural efficiency. With thetrain load constituting the major part of the live load it was important to position the two vertical

    main trusses just outside the clearance diagram of the railway so that the heavy load on the tracks

    could be carried as directly as possible through transverse girders to the lower nodes of the main

    trusses.

    Fig. 11: Cross section and part elevation of approach spans

    With the transverse position of the trusses determined by the clearance of the railway the wider

    roadway deck had to be made with overhangs, i.e. the deck slab should be cantilevered on either

    side of the trusses. This was in fact advantageous for the upper deck as it led to a favourable

    distribution between positive and negative moments in the slab and thereby made it possible to

    design the roadway deck as a solid concrete slab supported directly on the top chords of the main

    trusses. With a span of 12 m between the top chords the concrete slab had to be designed with a

    varying depth and with transverse prestressing.

    The design of the trusses was influenced by a number of considerations. The geometrical layout

    should be clean and simple not only for the overall appearance but also to give a harmonic rhythm

    when viewed from a passing train, the truss should be maintenance friendly, and the truss should be

    so rigid that it could respect the strictrequirements regarding deflections

    under passing trains. The solution

    was to use a Warren truss composed

    of unilateral triangles with relatively

    flat diagonals inclined approximately

    45o in stead of the generally accepted

    value of 60o (a value arrived at when

    minimizing the quantity of structural

    steel and neglecting the favourable cost implications of reducing the number of nodes). All truss

    members are made as closed boxes with stiffeners and diaphragms inside so that the exterior

    surfaces are clean and easy to maintain. The interior of all boxes is protected against corrosion byinstallation of dehumidification plants.

    Fig. 12: Approach spans

  • 7/22/2019 04-N.J. Gimsing

    8/14

    The most efficient use of the different structural materials would clearly be achieved by establishing

    a composite action between the concrete slab and the top chords of the steel trusses. However, the

    composite action should not only cover longitudinal shear but also bending moments between the

    top chords and the concrete slab so that

    a rigid closed frame could beestablished by the lower cross beams,

    the diagonals of the truss and the upper

    concrete deck. This required that the

    top plate of the chords was equipped

    with studs in two different sizes,

    normal studs in the central region of the

    top plate and long studs along the edges

    (above the webs of the box shaped

    chords).

    The long studs would be efficiently anchored inside the concrete slab and thereby allow transfer ofthe moment as a couple consisting of two vertical forces of opposite sign. The short studs on the

    other hand were only to transfer shear.

    the assumption

    For the design of the studs it was important to

    investigate the interaction between the long and the

    short studs to avoid that the long studs were

    overstressed before the short studs were efficiently

    activated.

    In 1989 when a double deck truss bridge was

    considered for the West Bridge of the Great Belt

    Link a full scale test was performed at the

    Department of Structural Engineering, Technical

    University of Denmark. From this test it could be

    concluded that it would be safe to base the design on

    the assumption that total shear was equally

    distributed over the long and the short studs whereas

    the moment transfer only affected the long studs.

    A great effort was made during the conceptual design

    phase to design the main trusses in such a way thatthey were not only structurally efficient but also

    pleasing in appearance. This resulted in gently curved

    gusset plates in a configuration that was favourable in

    relation to fatigue a feature of special importance

    due to the train loading. Besides this it was also

    decided to keep the exterior surfaces plane so that

    variations in plate thickness were to be made by

    adding thickness inside the box sections. This

    implied a slight complication in the fabrication as the

    interior diaphragms were to be geometrically adjusted as the side plate thickness was varied but this

    proved to be of minor importance.

    Fig. 13. Joint between the top chord and the upperconcrete slab

    Fig. 14: Top chord with studs

    Fig. 15: Test specimen in the structurallaboratory at Techn. Univ. of Denmark

  • 7/22/2019 04-N.J. Gimsing

    9/14

    In the design of the trusses it was attempted to

    minimize the number of structural elements to

    give the structure a clear and logic layout. An

    important step was to reduce the number of nodes

    by having a diagonal inclination of approximately

    450

    . The effort resulted in a truss with only 64members within the span length of 140 m: 14 top

    chord members, 14 bottom chord members, 28

    diagonals and 8 transverse girders. In a traditional

    truss with stringers, wind bracings and verticals in

    the main trusses the number of members can

    easily amount to more than 350.

    The trusses of the approach spans are made

    mainly of high strength steels S 460 N with a yield

    stress of 460 MPa. Only the lower cross beams

    and the top chord members between the gussetplates are made of S 355 N.

    The steel structure for the approach bridges

    totalling approximately 65,000 tons were

    manufactured in Spain on a large work site area in

    Cdiz. Here the steel trusses were assembled and

    painted in elements with the full span length

    (generally 140 m). Also in Cdiz the upper roadway slab was cast, and for this purpose the

    subcontractor had built a huge covered workshop with a roof spanning 150 m so that the steel

    trusses could be moved in and out sideways. Furthermore, the workshop had large air condition

    plants installed to reduce the temperature rise during concrete hardening.

    From Cdiz the approach span girders were

    transported in pairs to the work site area in Malm

    on large barges each capable of carrying two

    prefabricated spans each weighing almost 5000

    tons,

    At the work site area in Malm the precast concrete

    trough girders were added at the lower deck before

    the full span unit was transported to its final

    location.

    Every second week two 140 m girders arrived in

    Malm and were subsequently erected by Svanen.

    Consequently, the bridge grew in average by 20 m

    per day throughout the erection period.

    3.2 Main bridge

    With the main bridge forming a relatively small part (approx. 15%) of the total bridge length it wasobvious that a structural solution should be sought where the approach spans (comprising

    Fig. 16: Node of the main truss

    Fig. 17: Truss at the storage area in Malm.

    Fig. 18: Covered workshop at the work site

    Fig. 19: Svanen with 140 m truss element

  • 7/22/2019 04-N.J. Gimsing

    10/14

    continuous trusses) could continue into the main bridge without a complete change of structural

    system and materials, and without an abrupt visual transition. Also the strict requirements regarding

    strength and stiffness imposed by the passage of both heavy freight trains and high speed passenger

    trains proved to have a strong influence on the design of the main bridge with its 490 m main span

    the longest for any cable-stayed bridge carrying both road and railway traffic.

    All these requirements clearly pointed towards a cable-stayed main span with a girder composed of

    two vertical steel trusses and an upper concrete deck - as in the approach spans of the bridge. The

    demand for a high degree of rigidity led to a harp-shaped cable system with relatively steep cables

    and intermediate support in the side spans.

    Fig. 19: Elevation of cable-stayed spans

    To facilitate the anchoring of the stay

    cables at the deck level it was decided

    to change the truss geometry in the

    cable supported regions. Thus, the

    geometry of the approach spans where

    all diagonals have the same length ismodified so that the two diagonals

    leading to each node have different

    inclinations and lengths. By this it was

    achieved that the long diagonals

    became parallel to the stay cables.

    With the vertical trusses positioned in

    the same transverse distance as in the

    approach spans special structural

    elements are required to transfer the

    load to the cable system. Furthermore,the selection of a harp shaped cable

    system and free-standing pylons above

    the bridge deck imposed a distance of

    31.5 m between the cable planes.

    With the chosen lateral position of the vertical cable planes (imposed by the demand to have

    uniform compression across the pylon cross sections from vertical load) the distance between the

    cable anchorages at the girder level became 7 m larger than the width of the roadway. The load

    transfer from the main trusses to the stay cables is, therefore, established by adding triangular

    brackets (outriggers) in the plane of the long diagonals. At the end of each outrigger two anchor

    tubes are positioned to give support to the sockets of the double stay cable.

    Fig. 20: Adjustment of truss geometry from approachspan to main span

  • 7/22/2019 04-N.J. Gimsing

    11/14

    Besides the adjusted truss geometry and

    the addition of outriggers the main span

    girder also deviates from the approach

    spans by having a lower railway deck

    made as a shallow box girder in steel.

    This was chosen to reduce the dead loadand improve the capacity to transmit the

    large positive moments at midspan.

    The triangular brackets (outriggers)

    and the adjusted truss geometry give the

    main span a quite unique appearance

    and at the same time it exhibits an

    honest structure where nothing is done

    to hide the flow of forces from the two

    decks to the stay cables and further to

    the 203.5 m high pylons.

    The steel structure of the main span

    girder was fabricated in Sweden at a

    shipyard in Karlskrona. The steel grade

    applied was generally S 420 N with a

    yield stress of 420 MPa. After

    completion of erection units with a

    length of 140 m or 120 m the steel

    structure was transported to the work

    site area in Malm where the upper

    concrete slab was cast.

    During erection the girder of the main

    span was supported on the pylon cross

    beams, on the permanent piers in the

    side span and on temporary piers in the

    main span. The temporary piers were

    allowed due to the fact that the

    navigation channel were to be relocated

    after completion of the main span

    erection, and consequently no shipping

    took place through the main span until

    after completion of the superstructure.

    After erecting the superstructure from

    the transition pier at the end of the side

    spans to midspan the cable erection was initiated and subsequently the load was transferred from

    the temporary piers to the cable system.

    With the chosen procedure comprising temporary piers the 490 m long main span could be erected

    as four girder units with the concrete slab already in place as it was cast at the work site area. Only

    Fig. 21: The main span girder with outriggers at thework site area

    Fig. 22: Deck cross section in the cable-stayed spans

    Fig. 23: Partly erected main span on temporary piers

  • 7/22/2019 04-N.J. Gimsing

    12/14

    relatively small portions of the deck slab at the joints between the erection units had to be cast on

    site.

    The stay cables of the resund Bridge

    contains approximately 70 seven-wire strands

    inside a HDPE tube with an external diameterof 250 mm. To counteract rain-wind induced

    vibrations the surface of the tubes were made

    with a double helical spiral 2 mm thick.

    However, this modest measure did not prove

    sufficient to suppress the vibrations and

    especially in case of sleet large oscillations of

    the longest stays were observed. Further

    measures in the form of dampers at the stay

    anchorages and on the free length then had to

    be taken.

    4. Femern Belt Bridge

    Only two years elapsed from the opening of the Great Belt Bridge to the opening of the resund

    Bridge but almost twenty years will pass before the third if the large bridges, Femern Belt Bridge,

    will be ready to carry the traffic from Sweden, Norway and Eastern Denmark on the most direct

    route to Central Europe. The distance from Copenhagen to Hamburg will be shortened by 150 km

    when travelling via Femern in stead of via Great Belt.

    The final treaty between Denmark and Germany to build a bridge across the Femern Belt was

    signed on 3 September 2008. It was agreed that the bridge from coast to coast should be designed,

    financed and supervised by a Danish owned bridge authority whereas the approaches on land should

    be handled by each of the two countries. The preferred solution was indicated to be a high level

    bridge with a multi-span cable-stayed bridge across the international navigation channel. However,

    it was also stated that an immersed tunnel should be further investigated for comparison.

    4.1 Feasibility study 1999A feasibility study of the Femern Link was performed at the end of the 1990.s. It comprised traffic

    forecast, environmental issues, geotechnical investigations for a number of technical solutions.

    In the technical studies both immersed and bored tunnels were investigated for rail only as well as

    for rail+road. Bridges were studied only for combined road and railway traffic with a dual-two lane

    motorway and a double track railway.

    The bridge proposals were in their main design features similar to the resund Bridge, i.e. with a

    double deck truss carrying the two railway tracks on the lower level and the motorway on the upper

    level. The depth of the truss was, however, increased to 15 m to allow the approach bridges to have

    spans of 240 m.

    Across the navigation channel two solutions were studied, a multi-span cable-stayed bridge and a

    suspension bridge.

    Fig. 24: Polyurethane tubes used as casings

    around the bundles of seven-wire strands

  • 7/22/2019 04-N.J. Gimsing

    13/14

    The cable-stayed bridge was designed with three

    724 m main spans to allow one-way ship traffic in

    two navigation channels each with a horizontal

    clearance of 700 m.

    The suspension bridge was designed with a 1752 mmain span and 588 m side spans.

    The cost estimates clearly pointed towards the

    cable-stayed option and after the conclusion of the

    Feasibility Study it was decided that the primary

    solution for the Femern Belt Link should be the

    bridge option with cable-stayed main spans and as a

    secondary solution an immersed tunnel.

    More recently it has been questioned by some navigational authorities whether the cable-stayed

    bridge will give sufficient safety as shipmasters without experience in navigating through the bridgemight be confused when approaching it and then select the central span in stead of the assumed

    outer starboard span. Also, it is realised that the nearest anchor pier in the side spans of the cable-

    stayed bridge would carry a special risk in relation to ship collision as the distance from the center

    of the navigation span to the nearest anchor pier is only 640 m .

    Fig. 26: Suspension bridge from the Femern Belt Link Feasibility Study 1999

    It is, therefore, likely that the bridge consultants will reconsider the design of the navigation spans

    in the Femern Belt, and maybe also reinvestigate a suspension bridge main span.

    4.2 Ongoing investigationsTo give the best basis for the designers of the reference design to be tendered a number of

    investigations have already been initiated.

    Extensive environmental investigations have started to form the basis for the Environmental Impact

    Assessment (Hydrography, Marine Biology, Approaches on land, etc.).

    Geotechnical investigations of soil conditions is expected to continue until the end of 2011 within a

    total budget of 40 million Euro.

    Investigations into navigational safety are about to be concluded and will form a decisive basis for

    the final choice of main span and approach span configurations.

    With the unexpected appearance of individual cable vibrations in the resund Bridge a thorough

    study of cable vibrations under wind, rain and frost conditions has been initiated at the Department

    Fig. 25: Cable-stayed bridge from theFemern Belt Link Feasibility Study 1999

  • 7/22/2019 04-N.J. Gimsing

    14/14

    of Civil Engineering, technical University of Denmark As part of this study a Climatic Wind

    Tunnel will be installed at Force Technology in Denmark.

    The specifications for the Femern Climatic Wind Tunnel:

    - 20m x 8m closed-circuit- 25 m/sec mean wind velocity (min) with turbulence grid and flaps at -5

    OC

    - 40 m/sec mean velocity (min) without cooling elements

    - Water spray capabilities (simulated rain) and water-proofing

    - 2m2m section minimum to allow for a maximum of 10% blockage on a 200 mm wide

    cable or bridge section

    - Consistency of flow characteristics for both smooth and turbulent flow

    - Full turbulence spectrum (within reason) achieved through some form of flaps

    (turbulence generators)

    - Approx. 1 MW tunnel power consumption

    The total expected cost for the Climatic Wind Tunnel is approximately 1.3 Million Euro.

    The actual construction of the Femern Belt Link is planned to start in 2012 with a completion in

    2018.

    5. References

    [1] GIMSING, NIELS J. (editor), The Great Belt Publicartions: West Bridge, A/S Great Belt,

    Copenhagen, 1998

    [2] GIMSING, NIELS J. (editor), The Great Belt Publicartions: East Bridge, A/S Great Belt,

    Copenhagen, 1998

    [3] GIMSING, NIELS J., Cable Supported Bridges Concept and Design, Wiley,

    Chichester, U.K., 1998.

    [4] GIMSING, NIELS J. (editor), The resund Technical Publications:

    THE BRIDGE, resundsbro konsortiet, Copenhagen, 2000.

    [5] Trafikministeriet, Femer Blt-Forbindelsen, Forundersgelser Resumerapport (Femern

    Belt Link. Feasibility Study Summarising Report), Trafikministeriet, Copenhagen, 1999.