Updated: Sept, 09 CONTENTS Agency /Company-Wise NORTHERN REGION NEW DELHI Delhi Transco 2 PUNJAB Kalpana Hydro 2 RAJASTHAN Astonfield Renewable Resources 2 Indo Zinc 2 UTTAR PRADESH Uttar Pradesh Power Corporation Limited 3 WEST REGION CHHATTISGARH Adhunik Power & Natural Resources 3 Spectrum Coal & Power 3 GUJARAT Astonfield Renewable Resources 3 Essar Power 3 Sanghi Cement 4 JHARKHAND Power Grid Corporation of India 4 MADHYA PRADESH Essar Power 4 Revati Cements 4 MAHARASHTRA Adani Power Maharashtra (APML) 5 Ideal Energy Projects 5 Kisan Veer Satara SSK 5 Maharashtra State Electricity Transmission Co 6 Maharashtra Power Generation Corporation 6 Maharashtra State Electricity Distribution 6 Company (MSEDCL) 6 Maharashtra State Electricity Transmission Company (MAHATRANSCO) 6 Maharashtra State Electricity Transmission Company Limited 7 Shankar Maharshi Shankarrao Mohite Patel 7 SOUTHERN REGION ANDHRA PRADESH Hinduja Group 8 Keerthi Industries 8 Meenakshi Energy 8 Singaraya Hills 8 KARNATAKA Astonfield Renewable Resources 9 Hare Krishna Metallics 9 Ind-Barath Power (Karwar) 9 Maharashtra Seamless 9 PGM Ferro Steels 9 Siruguppa Sugars & Chemicals 10 KERALA Kerala Sponge Iron 10 Kerala State Electricity Board 10 TAMIL NADU Dharani Sugars & Chemicals 11 EASTERN REGION BIHAR Astonfield Renewable Resources 12 Bihar State Electricity Board 12 JHARKHAND Adhunik Power & Natural Resources 12 Bokaro Power Supply 12 Power Generation Projects Page 1

Upload: info4085

Post on 12-Nov-2014

427 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 03 Hard Copy Format for Sep

Updated: Sept, 09

CONTENTSAgency /Company-Wise

 

NORTHERN REGIONNEW DELHI Delhi Transco 2

PUNJAB Kalpana Hydro 2

RAJASTHAN Astonfield Renewable Resources 2 Indo Zinc 2

UTTAR PRADESH Uttar Pradesh Power Corporation Limited 3

WEST REGIONCHHATTISGARH Adhunik Power & Natural Resources 3 Spectrum Coal & Power 3

GUJARAT Astonfield Renewable Resources 3 Essar Power 3 Sanghi Cement 4

JHARKHAND Power Grid Corporation of India 4

MADHYA PRADESH Essar Power 4 Revati Cements 4

MAHARASHTRA Adani Power Maharashtra (APML) 5 Ideal Energy Projects 5 Kisan Veer Satara SSK 5 Maharashtra State Electricity Transmission Co 6 Maharashtra Power Generation Corporation 6 Maharashtra State Electricity Distribution 6

Company (MSEDCL) 6 Maharashtra State Electricity Transmission

Company (MAHATRANSCO) 6 Maharashtra State Electricity Transmission

Company Limited 7 Shankar Maharshi Shankarrao Mohite Patel 7

SOUTHERN REGIONANDHRA PRADESH Hinduja Group 8 Keerthi Industries 8 Meenakshi Energy 8 Singaraya Hills 8

KARNATAKA Astonfield Renewable Resources 9 Hare Krishna Metallics 9 Ind-Barath Power (Karwar) 9 Maharashtra Seamless 9 PGM Ferro Steels 9 Siruguppa Sugars & Chemicals 10

KERALA Kerala Sponge Iron 10 Kerala State Electricity Board 10

TAMIL NADU Dharani Sugars & Chemicals 11

EASTERN REGIONBIHAR Astonfield Renewable Resources 12 Bihar State Electricity Board 12

JHARKHAND Adhunik Power & Natural Resources 12 Bokaro Power Supply 12

ORISSA Jindal Steel & Power 13

SIKKIM Lanco Infratech 13

TRIPURA North East Transmission Company 13

WEST BENGAL Astonfield Renewable Resources 14 West Bengal State Electricity Transmission

Company 14

Power Generation Projects Page 1

Page 2: 03 Hard Copy Format for Sep

Updated: Sept, 09

NEW DELHI

STATUS: PLANNING

Promoter: Promoter: Delhi Transco Delhi Transco Proj: Proj: TransmissionTransmission Cost: Cost: Rs. 576.4 millionRs. 576.4 million Loc: Loc: WazirpurWazirpur

Delhi Transco is to set up a Gas-insulate Substation (GIS)

at Wazirpur in New Delhi. The scope of works includes

complete project management, design, engineering,

type testing, manufacture, transportation to site,

insurance, storage, erection, testing and commissioning

of 220 kV GIS having 220 kV and 33 KV outdoor

equipment, 100 MVA power transformers and other

substation equipment. The cost of the project is Rs.

576.4 million. Implementation Schedule: As of August

2009, bids are invited for the project on turnkey basis.

The last date of submission being 25-08-2009. The

project has a completion period of 12-15 months from

the effective date of contract.

Delhi Transco Limited, Office of the DGM (OS),

Room No. 51, 1st Floor, Shakti Deep Building,

Jhandewalan Extension, New Delhi 110055, Delhi.

Website: www.delhitransco.gov.in

PUNJAB 

STATUS: PLANNING

Promoter: Promoter: Kalpana Hydro ProjKalpana Hydro Proj: : Gill Aqua Hydro Gill Aqua Hydro Electric PowerElectric Power Cap: Cap: 15 MW15 MW Loc: Loc: PathankotPathankot Dist: Dist: GurdaspurGurdaspur

Kalpana Hydro plans to set up 15 MW Gill Aqua Hydro

Electric Power at Pathankot in Gurdaspur district of

Punjab. Implementation Schedule: As of July 2009, the

preparation of DPR has been completed and project

consultant has been appointed. The project is in its

preliminary stage.

Kalpan Hydro Company India Private Limited,

1st Floor, NCPL Web Tower, A – 4, Sector 9, Noida

Gautam Buddha Nagar 201301, Uttar Pradesh.

India. Tel: +91 120- 4661511. Fax: + 91 120- 421206.

Email [email protected]. Website:

www.kalpanhydro.com

RAJASTHAN 

STATUS: PLANNING

Promoter: Astonfield Renewable Resources Proj: Promoter: Astonfield Renewable Resources Proj: Non Conventional Cap: 5 MWNon Conventional Cap: 5 MW

Astonfield Renewable Resources is planning to set up a 5

MW Solar power project in Rajasthan. Implementation

Schedule: As of July 2009, the Government allotment

has been received by the company. The project is in a

nascent stage.

Astonfield Renewable Resource Private

Limited, Room No. 112 & 107, DBS House, 10/ 2,

Hungerford Street. Kolkata 700017, West Bengal,

India. Tel: +91 33-32443981. Fax: + 91 33 -

40509300. Email: [email protected]

Website: www.astonfield.com

STATUS: PLANNING

Promoter: Indo Zinc Proj: Captive Power Plant Cap:Promoter: Indo Zinc Proj: Captive Power Plant Cap: 20 MW Dist: Banswara EDC: Mid-quarter of 201020 MW Dist: Banswara EDC: Mid-quarter of 2010

Indo Zinc plans to set up 20 MW captive power plant in

the premises of its cement unit in Banswara district of

Rajasthan. Implementation Schedule: As of July 2209,

DPR is under progress and clearance is awaited. The

project is scheduled to be completed by mid-quarter of

2010.

Indo Zinc Limited, 405 Apollo Tower M G Road,

Indore 452001, Madhya Pradesh. Tel: +91 731-

4289000 / 2518341. Fax : + 91 731 4058080. Email :

[email protected]

Plt: Mahi Cement, No. 40, Sharada Nagar, Link

Road, Banswara 327001, Rajasthan, India. Tel: +91

2962-250630 / 250551. Fax: 91 2962-250629.

Power Generation Projects Page 2

Page 3: 03 Hard Copy Format for Sep

Updated: Sept, 09

UTTAR PRADESH 

STATUS: PLANNING

Promoter: Promoter: Uttar Pradesh Power Corporation Uttar Pradesh Power Corporation Limited (UPPCL) Limited (UPPCL) Proj: Proj: ThermalThermal Cap: Cap: 2x660 MW2x660 MW Loc: Loc: Jawaharpur Jawaharpur Dist: Dist: EtahEtah

UPPCL plans set up Thermal Power Project in Etah

district of UP. Uttar Pradesh Power Corporation Limited

(UPPCL) plans to set up 2x660 MW thermal power

project at Jawaharpur in Etah district of UP.

Implementation Schedule: As of July 2009, bids for

appointment of technical consultants are under

evaluation.

Uttar Pradesh Power Corporation Limited, 3rd

Floor, Shakti Bhawan Extension 14, Ashok Marg,

Lucknow 226001, Uttar Pradesh, India. Tel: +91-

522-2287867 / 2287343. Fax : + 91 522 -2288484/

2287343. Website: www.uppcl.org

CHHATTISGARH

STATUS: PLANNING

Promoter: Promoter: Adhunik Power & Natural Resources Adhunik Power & Natural Resources Proj: Proj: Thermal Thermal Cap: Cap: 2 x 660 MW 2 x 660 MW Dist: Dist: BilaspurBilaspur

Adhunik Power & Natural Resources plans to set up 2 x

660 MW Coal based Super Critical thermal power plant

in Bilaspur district of Chhattisgarh. The company has

signed an MoU with the State Government.

Implementation Schedule: As of July 2009, land

acquisition is under progress and clearances awaited.

Adhunik Power & Natural Resources Limited,

C/o. Adhunik Group Of Industries, Lansdowne

Towers, 2/ 1A, Sarat Bose Road, Kolkata 700020,

West Bengal, India. Tel: +91 33- 30517100. Fax: 91

33- 22890285. Email: [email protected].

Website: www.adhunikgroup.com 

STATUS: IMPLEMENTATION

Promoter: Promoter: Spectrum Coal & PowerSpectrum Coal & Power Proj: Proj: ThermalThermal Cap: Cap: 250 MW 250 MW Dist:Dist: Korba Korba EDC:EDC: End of 2011. End of 2011.

Spectrum Coal & Power, a subsidiary of Aryan Coal

Benefication is setting up 250 MW of Coal based power

plant in Korba district of Chhattisgarh. Implementation

Schedule: As of July 2009, civil work is under progress.

The project is scheduled for completion by the end of

2011.

Spectrum Coal & Power Limited, No. 202,

Cyber Heights, Road No. 2, Banjara Hills, Hyderabad

500033, Andhra Pradesh, India. Tel: +91 40-

23545287 / 66625287. Fax: + 91 40- 23544137.

Email: [email protected]. Website:

www.spectrumcoal.com

GUJARAT

STATUS: PLANNING

Promoter: Promoter: Astonfield Renewable Resources Astonfield Renewable Resources Proj: Proj: Non Conventional Non Conventional Cap: Cap: 200 MW200 MW

Astonfield Renewable Resources plans to set up a 200

MW Solar power project in Gujarat. Implementation

Schedule: As of July 2009, the company has signed an

MoU with the State Government. Land acquisition for

the project is under progress.

Astonfield Renewable Resource PVt Ltd, Room

No. 112 & 107, DBS House, 10/ 2, Hungerford

Street , Kolkata700017, West Bengal. Tel: 91 33

32443981. Fax: 40509300. Email:

[email protected]. Website:

www.astonfield.com

STATUS: IMPLEMENTATION

Promoter: Promoter: Essar Power Essar Power Proj: Proj: ThermalThermal Cap: Cap: 2x600 2x600 MW MW Loc:Loc: Salaya Salaya Dist: Dist: Jamnagar Jamnagar EDC:EDC: 2012 2012

Essar Power is setting up a 2x600 MW Coal based

thermal power project at Salaya in Jamnagar district of

Gujarat. Harbin, China has been appointed as the

Power Generation Projects Page 3

Page 4: 03 Hard Copy Format for Sep

Updated: Sept, 09

equipment supplier. Implementation Schedule: As of

July 2009, civil works are under progress. The project is

scheduled for completion by 2012.

Essar Power Limited, Essar House, 11

Keshavrao Khadye Marg, Mahalaxmi, Mumbai City -

400034, Maharashtra, India. Tel: +91-22-66601100.

Fax:+91 22-24954787. Email:

[email protected]. Website: http:

ww.essar.com

Harbin , 170 Guixin St., Harbin-150006, Tel: 86-

451-6231639 China. 

STATUS: IMPLEMENTATION

Promoter: Promoter: Sanghi CementSanghi Cement Proj: Proj: Captive Power Captive Power PlantPlant Cap: Cap: 2 X 60 MW Loc: Sanghipuram 2 X 60 MW Loc: Sanghipuram Dist: Dist: Kutch Kutch EDC:EDC: November 2009 (Phase I) November 2009 (Phase I)

Sanghi Cement is setting up 2 X 60 MW captive thermal

power plant in two phases at the existing Sanghipuram

unit in Kutch district of Gujarat. Implementation

Schedule: As of July 2009, Ph I is under implementation

and is scheduled for completion by November 2009.

Sanghi Cement Limited, President House,

Ambawadi Circle, Ahmedabad 380006, Gujarat.

Tel:91-79-26564535/26569939. Fax: 26560408.

Email: [email protected]. Website:

www.sanghicement.com

Plt: P.O. Sanghipuram, Abadasa, Kutch 370511,

Gujarat India. Tel: 02831-274131 / 274132 /

274133/274138/274139. Fax: 274115/

2831274123. Email: [email protected].

Web:www.sanghicement.com

JHARKHAND 

STATUS: IMPLEMENTATION

Promoter: Promoter: Power Grid Corporation of India Power Grid Corporation of India Proj: Proj: TransmissionTransmission Cost: Cost: Rs.1,090 millionRs.1,090 million

Power Grid Corporation of India is to construct and

upgrade their 400 KV Bachau and 400 KV Maithon

substations. Siemens has been awarded the turnkey

contract at a cost of Rs.1,090 million. Implementation

Schedule: The projects are scheduled to be

commissioned in the next 12 to 24 months. Siemens

energy sector will construct a new 400/ 220 KV

substation at Bachau and upgrade another two existing

substations of GETCO at Limbdi and Ranchodpura in

Gujarat. This project is a part of the Associated

Transmission System for Ultra Mega Power Project

(UMPP) to transmit the bulk power generated by

Mundra UMPP to the western region. The other contract

received by Siemens is for extension of 400 KV

substations at Maithon in Jharkhand. The scope of work

in both the projects includes designing, engineering,

manufacture, supply, installation, civil works, testing and

commissioning of the complete substations. Siemens

will supply the hi-end technology products such as

circuit breakers, dis-connectors, instrument

Transformers and control & protection equipment

manufactured at its State-of-the-Art factories in

Aurangabad, Kalwa and Hyderabad.

Power Grid Corporation of India Limited,

Saudamini, Plot No. 2, Sector-29, Near IFFCO

Chowk, Gurgaon 122001, Haryana. India. Tel: +91

124-2571700 / 2571719. Fax: 91-124-2571760/

2571761. Website: www.powergridindia.com

Siemens Limited, 130, Pandurang Budhkar

Marg, Worli, Mumbai 400018, Maharashtra India.

Tel: +91 22-24987000. Fax: + 91 22-24987500.

Website: www.siemens.co.in

MADHYA PRADESH 

STATUS: IMPLEMENTATION

Promoter: Promoter: Essar Power Essar Power Proj: Proj: ThermalThermal Cap: Cap: 2x600 2x600 MW MW Loc:Loc: Mahan Mahan Dist: Dist: Singrauli Singrauli EDC:EDC: 2012 2012

Essar Power is setting up a 2x600 MW Coal based

Thermal power project at Mahan in Singrauli district of

MP. Harbin, China has been appointed as the equipment

supplier. Implementation Schedule: As of July 2009, civil

works are under progress. The project is scheduled for

completion by 2012.

Essar Power Ltd: Essar House, 11 Keshavrao

Khadye Marg, Mahalaxmi, Mumbai 400034,

Maharashtra. Tel: 91-22-66601100. Fax: 24954787.

Email: [email protected] Website:

www.essar.com

Power Generation Projects Page 4

Page 5: 03 Hard Copy Format for Sep

Updated: Sept, 09

Harbin , 170 Guixin St., Harbin-150006, Tel: 86-

451-6231639 China. 

STATUS: PLANNING

Promoter: Promoter: Revati Cements Revati Cements Proj: Proj: Captive Power Captive Power PlantPlant Cap: Cap: 35 MW35 MW Dist: Dist: SatnaSatna

Revati Cements, a group company of Indian Steel

Corporation jointly promoted by Ruchi Group of

Industries and Mitsui & Co, Japan plans to set up a 35

MW coal based captive power plant at its Satna cement

facility in MP. Implementation Schedule: As of June

2009, work on the power plant is to commence after the

completion of the cement unit in the Satna facility.

Revati Cements Pvt Ltd, No. 503, Mahakosh

House, 7/ 5, South Tukoganj, Nath Mandir Road

Indore 452001, Madhya Pradesh. Tel: +91 731

4017509 / 2518124. Fax: +91-731-2518127. Email:

[email protected] Web: www.indiansteels.com

MAHARASHTRA 

STATUS: PLANNING

Promoter: Promoter: Adani Power Maharashtra (APML) Adani Power Maharashtra (APML) Proj: Proj: Transmission Loc: Tiroda Dist: GondiaTransmission Loc: Tiroda Dist: Gondia

APML is to implement a Power Transmission Project at

Tiroda in Gondia district of Maharashtra. The project is

for evacuation of Power from the Tiroda Thermal Power

Project. The scope of works includes design, supply,

erection, testing & commissioning of 400 KV Double

circuit Tiroda-Koradi Transmission Line Package.

Implementation Schedule: As of August 2009, tenders

are invited for the project on EPC basis with the last date

of submission being 31-08-2009. The project has a

completion period of 18 months from the date of award

of contract.

Adani Power Maharashtra Private Ltd, 7th

Floor, Sambhav Building, Judges Bungalow Road,

Bokakdev Ahmedabad 380015, Gujarat India. Tel:

+91 79 25556946. Email: [email protected]

Website: www.adanipower.com 

STATUS: IMPLEMENTATION

Promoter: Promoter: Ideal Energy ProjectsIdeal Energy Projects Proj: Proj: ThermalThermal Cap: Cap: 1x270 MW 1x270 MW Cost:Cost: Rs. 4,140 million Rs. 4,140 million Loc: Loc: Bela Bela Dist:Dist: NagpurNagpur

Ideal Energy Projects to implement a Coal Based Power

Project in Maharashtra. Ideal Energy Projects

implementing 1x270 MW coal based power project at

Bela in Nagpur district of Maharashtra. The scope of

works includes design, engineering, manufacturing,

supply, erection, testing and commissioning including

civil works. McNally Bharat Engineering Company has

been awarded on EPC basis for balance of plant at a cost

of Rs. 4,140 million. Implementation Schedule: As of

July 2009, the project has been awarded.

Ideal Energy Projects Limited, No. 122,

Telecom Nagar, Pratap Nagar Nagpur 440022

Maharashtra. Tel: +91 712-2295988 / 2295989. Fax:

+91 712-

2295987.

Mc Nally Bharat Engineering Co Ltd, No. 4

Mangoe Lane, 7th Floor, Kolkata 700001, West

Bengal. Tel: +91 33-65500726 / 65500727 /

65500728 / 65500729 / 65500730 / 65500731 /

Fax: 91-33-22480340/ 22485016. Email:

[email protected]. Website:

www.mcnallybharat.com 

STATUS: IMPLEMENTATION

Promoter: Promoter: Kisan Veer Satara SSK Kisan Veer Satara SSK Proj: Proj: Thermal Thermal Cap: Cap: 22 MW22 MW Dist: Dist: Satara Satara EDC:EDC: October 2010. October 2010.

Kisan Veer Satara SSK is setting up a 22 MW Bagasse

based co-gen power plant at Satara district in

Maharashtra. Mitcon Consulting Services, Pune has

been appointed as the project consultant. Thyssen

Krupp and Siemens are the major equipment suppliers.

Implementation Schedule: As of July 2009, civil works

are yet to commence. The project is scheduled for

completion by October 2010.

Kisan Veer Satara S S K Limited, Bhuinj, A/p.

Kisanveer Nagar, Taluk Wai, Satara 415515,

Maharashtra, India. Tel: +91 2167 285240. Fax: + 91

2167 285147.

Mitcon Consultancy Services Ltd, MITCON

Kubera Chambers, Shivajinagar Pune 411005,

Maharashtra India. Tel: +91 20 25534322 /

25533309. Fax: +91 20 25533206. Website:

www.mitconindia.com

Thyssen Krupp Industries India Limited, P. O.

Bag No. 22, Pimpri, Pune 411018, Maharashtra. Tel:

Power Generation Projects Page 5

Page 6: 03 Hard Copy Format for Sep

Updated: Sept, 09

+91 2027425461 / 27425462 / 27425463 /

27425464. Fax: 91 20- 27425821/ 27425350. Email:

[email protected]. Website:

www.thyssenkruppindia.com

Siemens Limited: 130, Pandurang Budhkar

Marg, Opposite Doordarshan, Worli, Mumbai

400018, Maharashtra India. Tel: +91 22 24987000 /

24987547. Fax:24987500. Website:

www.siemens.co.in 

STATUS: IMPLEMENTATION

Promoter: Promoter: Maharashtra State Electricity Maharashtra State Electricity Transmission Company Transmission Company Proj: Proj: Transmission Transmission Cost: Cost: Rs.1,410 million Rs.1,410 million Loc:Loc: See Below See Below EDC: EDC: 20102010

Maharashtra State Electricity Transmission Company is

implementing 3 Substation projects in the State. The 220

KV and 132 KV subtations are located in Nashik,

Amravati & Nagpur. ABB has been awarded the turnkey

contract at a cost of Rs.1,410 million. The scope of works

includes system design, engineering, civil works, supply,

installation, commissioning and overall project

management. Implementation Schedule: The project is

scheduled for completion by 2010.

Maharashtra State Electricity Transmission

Company Limited, 5th Floor, Plot No. C-19, Bandra-

Kurla Complex, Bandra (E) Mumbai 400051,

Maharashtra. Tel: +91 222 6595130 / 26595164 /

Fax: 26598587. Website: www.mahatransco.in

A B B Limited, 2nd Floor, Khanija Bhavan, East

Wing, 49, Race Course Road, Bangalore 560001,

Karnataka India. Tel: +91 80 22949150 / 22949151 /

22949152 / 22949153 / 22949154. Fax : + 91 80-

22949148. 

STATUS: IMPLEMENTATION

Promoter: Promoter: Maharashtra Power Generation Maharashtra Power Generation Corporation (MAHAGENCO)Corporation (MAHAGENCO) Proj: Proj: Thermal Thermal Cap: Cap: 2x500 MW 2x500 MW Cost:Cost: Rs.16,320 million Rs.16,320 million Dist:Dist: Chandrapur.Chandrapur.

Maharashtra Power Generation Corporation

(MAHAGENCO) is implementing 2x500 MW Chandrapur

Super Thermal Power Station in Chandrapur district.

BGR Energy Systems has been awarded the turnkey

contract for balance of plant at a cost of Rs.16,320

million. The scope of work includes design, supply,

engineering, erection, testing and commissioning of all

balance work of the Plant including mechanical,

electrical, civil and structural works. Implementation

Schedule: The project is scheduled for completion in 33

months.

Maharashtra State Power Generation

Corporation Limited, Prakashgad, 3rd Floor, Plot No.

G-9, A. K. Marg, Bandra (E) Mumbai 400051,

Maharashtra India. Tel: +91 22-26474211 /

26475759. Fax: 26475329. Website:

www.mahagenco.in

B G R Energy Systems Limited, A-5,

Pannamgadu Industrial Estate, Ramapuram Post,

Sullurpet Village, Nellore 524401, Andhra Pradesh

India. Tel: +91 44-27900181. Fax: +91 44 27948249.

Website : www.bgrcorp.com 

STATUS: IMPLEMENTATION

Promoter: Promoter: Maharashtra State Electricity Maharashtra State Electricity Distribution Company (MSEDCL)Distribution Company (MSEDCL) Proj: Proj: TransmissionTransmission Cost:Cost: Rs. 10188.4 million Rs. 10188.4 million Loc: Loc: See Below See Below

Maharashtra State Electricity Distribution Company

(MSEDCL) is upgrading its distribution networks in

Nashik and Aurangabad divisions of Maharashtra. The

company has awarded an order to Ashoka Buildcon Ltd,

Nashik as part of the power transmission project. The

scope of work includes construction of 72 new

sub-stations, augmentations/enhancement of existing

128 substations, construction of 33 kV overhead lines

(973 Kms), construction of 11 kV overhead lines (5,600

Kms) & construction of 7,200 new distribution

transformers. The order is valued at Rs. 10188.4 million.

Implementation Schedule: As of July 2009, works are

under progress. The order is scheduled for completion in

two years.

Maharashtra State Electricity Distribution

Company Limited, Office Of The Chief Engineer,

Aurangabad Zone, Vidyut Bhavan, Dr. Babasaheb

Ambedkar Road, Aurangabad 431001, Maharashtra.

Tel: +91 240-2331347. Fax: +91 240-2331056.

Website: www.mahadiscom.in

Maharashtra State Electricity Distribution

Company Limited, Office Of The Chief Engineer,

Nasik Zone, Vidyut Bhavan, Nasik Road, Nashik

42210, Maharashtra. Tel: +91 253-2462491 /

2462492 / 2462493. Fax: +91 253 2461581. Web:

www.mahadiscom.in

Ashoka Buildcon Ltd, Registered office 'Ashoka

House', Ashoka Marg, Nashik 422011, Maharashtra.

Tel: +91 253-3011705. Fax: 91-253-2422704. Email:

[email protected]. Web:

www.ashokabuildcon.com 

STATUS: PLANNING

Power Generation Projects Page 6

Page 7: 03 Hard Copy Format for Sep

Updated: Sept, 09

Promoter: Promoter: Maharashtra State Electricity Maharashtra State Electricity Transmission Company (MAHATRANSCO) Transmission Company (MAHATRANSCO) Proj: Proj: TTransmissionransmission Loc: Loc: Taharabad Taharabad Dist:Dist: Nashik Nashik

Maharashtra State Electricity Transmission Company

(MAHATRANSCO) is to implement a substation project at

Taharabad in Nashik district of Maharashtra. Package B

(132/33 kV substation) includes • Establishment of 2x25

MVA, 132/33 kV transformers with bays • 132 kV line

bays (2 nos. each at Satana and Taharabad) - 4 Nos. • 33

kV outlets – 8 Nos. The scope of works includes

establishment of the substation with design,

engineering, supply of material, civil works, erection,

testing and commissioning. Implementation Schedule:

As of July 2009, bids are invited for establishment of the

substations on turnkey basis with the last date of

submission being 10-08-2009. The project is scheduled

for completion in 12 months from the date of LOA.

Maharashtra State Electricity Transmission

Company Limited, Office of the Executive Engineer

5th Floor, Plot No. C-19, ‘E’-Block, Bandra Kurla

Complex, Bandra (East), Mumbai 400051

Maharashtra, India Tel: +91 22- 26595173. Fax: + 91

22-26598587. Website: www.mahatransco.in 

STATUS: PLANNING

Promoter: Promoter: MSETCL MSETCL Proj: Proj: Transmission Transmission Cost: Cost: Rs. Rs. 100 million 100 million Loc: Loc: See BelowSee Below

MSETCL is to undertake installation of 22 kV GIS

switchgear units at Bhiwandi I and Bhiwandi II (Kamba)

substations in Maharashtra on turnkey basis. The scope

of works includes installation of 22 kV GIS switchgear

units with associated equipment / arrangements at 100

KV Bhiwandi I, 220 KV Kamba II substations with design,

engineering, manufacturing, supply, installation with

civil works, testing and commissioning. The estimated

cost of the project is Rs. 100 million. Implementation

Schedule: As of August 2009, bids have been invited for

installation of GIS switchgear units with associated

works. The last date of submission being 10-08-2009.

The project has a completion schedule of 6 months

(including monsoon period) from the date of letter from

MSETCL for taking over the site for execution.

Maharashtra State Electricity Transmission

Company Limited, Office of the Executive Engineer ,

5th Floor, Plot No. C-19, ‘E’-Block, Bandra Kurla

Complex, Bandra (East), Mumbai 400051

Maharashtra. Tel:+91(22)26595173. Fax: 91-22-

26598587. Website: www.mahatransco.in 

STATUS: PLANNING

Promoter: Promoter: MAHATRANSCO MAHATRANSCO Proj: Proj: Transmission Transmission Cost: Cost: Rs. 138.8 million Rs. 138.8 million Loc: Loc: Mahakala Mahakala Dist: Dist: JalnaJalna

MAHATRANSCO is to implement a Substation Project at

Mahakala in Jalna district of Maharashtra. Package C

(132/33 kV substation) includes • Establishment of 2x25

MVA, 132/33 kV transformers with bays. • 132 kV line

bays - 4 Nos. (2 Nos. at Mahakal and one each at Georai

and Ambad) • 33 kV outlets - 8 Nos. The scope of works

includes establishment of the substation with design,

engineering, supply of material, civil works, erection,

testing and commissioning. The cost of the project is Rs.

138.8 million. Implementation Schedule: As of July

2009, bids are invited for establishment of the

substations on turnkey basis with the last date of

submission being 10-08-2009. The project is scheduled

for completion in 12 months from the date of LOA.

Maharashtra State Electricity Transmission

Company Limited, Office of the Executive Engineer,

5th Floor, Plot No. C-19, ‘E’-Block, Bandra Kurla

Complex, Bandra (East), Mumbai 400051,

Maharashtra. Tel: +91-22-26595173. Fax:+91 22-

26598587. Website: www.mahatransco.in 

STATUS: PLANNING

Promoter: Promoter: MAHATRANSCO MAHATRANSCO Proj: Proj: TTransmission ransmission Loc:Loc: Kadegaon Kadegaon Dist:Dist: Sangli Sangli

MAHATRANSCO is to implement a Substation Project at

Kadegaon in Sangli district of Maharashtra. Package A

(220/ 132/33 kV substation) includes :

• Establishment of 2x100 MVA, 220/132-110 kV ICT with

bays.• Establishment of 2x50 MVA, 220/33 kV

transformers with bays • 220 kV line bays - 2 Nos. • 132

kV line bays - 4 Nos. • 33 kV outlets - 12 Nos. The scope

of works includes establishment of the substation with

design, engineering, supply of material, civil works,

erection, testing and commissioning. Implementation

Schedule: As of July 2009, bids are invited for

establishment of the substations on turnkey basis with

the last date of submission being 10-08-2009. The

project is scheduled for completion in 18 months from

the date of LOA.

Maharashtra State Electricity Transmission

Company Limited, Office of the Executive Engineer,

5th Floor, Plot No. C-19, ‘E’-Block, Bandra Kurla

Complex, Bandra (East), Mumbai 400051,

Maharashtra. Tel: +91 22 26595173. Fax:+91 22-

26598587. Website: www.mahatransco.in 

STATUS: IMPLEMENTATION

Power Generation Projects Page 7

Page 8: 03 Hard Copy Format for Sep

Updated: Sept, 09

Promoter: Promoter: Shankar Maharshi Shankarrao Mohite Shankar Maharshi Shankarrao Mohite Patel S S K Patel S S K Proj: Proj: Thermal Thermal Cap: Cap: 33 MW 33 MW Loc: Loc: Malshiras Malshiras Dist: Dist: Solapur Solapur EDC: EDC: 2010.2010.

Shankar Maharshi Shankarrao Mohite Patel S S K is

setting up 33 MW Bagasse based co gen at Malshiras in

Solapur district of Maharashtra. Avant Garade is the

Technical Consultant. Implementation Schedule: As of

July 2009, civil work is under progress. The project is

scheduled for completion by January 2010.

Maharshi Shankarrao Mohite Patel S S K Ltd,

Corporate Office: Shankar Nagar, Akluj, Malshiras

Taluk Solapur 413118, Maharashtra. Tel: +91 -2185-

222048. Fax: 91-2185-222249.

Avant Garde Engineers & Consultants Private

Limited, No. 68 A, Porur Kundrathur High Road,

Porur, Chennai 600116, Tamil Nadu. Tel: +91 44

24827843 / 24828717 / 24828718 / 24828719 /

24828720. Fax: 91-44-24828531. Email:

[email protected]. Website: www.avantgarde-

india.com

TAMIL NADU 

STATUS: PLANNING

Promoter: Promoter: Hinduja Group Hinduja Group Proj: Proj: Thermal Thermal Cap: Cap: 2x520 MW 2x520 MW Loc:Loc: Visakhapatnam Visakhapatnam EDC:EDC: First quarter First quarter of 2013.of 2013.

Hinduja Group plans to set up 2x520 MW Coal based

thermal power plant at Visakhapatnam in AP. Mott Mac

Donald is the technical consultant. Implementation

Schedule: As of July 2009, bids are being received from

EPC contractors and financial closure is awaited. The

project is scheduled for completion by the first quarter

of 2013.

Hinduja Group India Limited, Hinduja House,

171 Dr. Annie Besant Road, Worli 400018, Mumbai

Maharashtra. Tel: 91 22- 24960707. Website:

http://hindujagroup.com.

Mott Mac Donald, 44 Dr R G Thadani Marg,

Worli, 400018 Mumbai, Maharashtra. Tel:

39810100. Fax: +91 22 24950539. Email:

[email protected]. Web:

www.mottmac.in 

STATUS: PLANNING

Promoter: Promoter: Keerthi Industries Keerthi Industries Proj: Proj: Thermal Thermal Cap: Cap: 2020 MWMW Cost: Cost: Rs.400 million Rs.400 million Loc: Loc: Balanagar Balanagar Dist:Dist: Ranga Reddy Ranga Reddy EDC:EDC: Last Quarter of 2011. Last Quarter of 2011.

Keerthi Industries plans to set up a 20 MW bagasse

based co-gen power plant at Balanagar in Ranga Reddy

district of AP. The project envisages an investment of

Rs.400 million. Avante Garde is the project consultant.

Implementation Schedule: As of July 2009, certain

clearances are awaited from the State Government. The

project is slated for completion by the last quarter of

2011.

Keerthi Industries Limited, No. 40 IDA,

Balanagar, Ranga Reddy 500037, Andhra Pradesh,

India.

Avant Garde Engineers & Consultants Private

Limited, No. 68 A, Porur Kundrathur High Road,

Porur, Chennai 600 116, Tamil Nadu. Tel: 91-44-

24827843 / 24828717 / 24828718 / 24828719 /

24828720. Fax: +91-44–2482853. Email:

[email protected] Website: www.avantgarde-

india.com 

STATUS: IMPLEMENTATION

Promoter: Promoter: Meenakshi EnergyMeenakshi Energy Proj: Proj: Thermal Thermal Cap: Cap: 900 MW900 MW (Phase I & II)(Phase I & II) Loc: Loc: Thammenapatnam Thammenapatnam Dist:Dist: Nellore Nellore

Meenakshi Energy is setting up 900 MW thermal power

plant at Thammenapatnam in Nellore District of AP in a

phased manner. Phase I will comprises of 2x135 MW

power plants and the balance to come up in Phase II.

Implementation Schedule: As of July 2009, EPC

contractors have been appointed and civil works are

under progress.

Meenakshi Energy Private Limited, Meenakshi

House, 8-2-418, Road # 7 Banjara Hills, Hyderabad

500034, Andhra Pradesh. Tel: +91 40- 23358111 /

23358222 / 23358333. Fax: 23351133 / 23351530.

Email: [email protected] Website:

www.meenakshienergy.com 

STATUS: PLANNING

Promoter: Promoter: Singaraya Hills Singaraya Hills Proj: Proj: Non Conventional Non Conventional Cap: Cap: 6 MW to6 MW to 8 MW8 MW Loc: Loc: Hasnapur Hasnapur Dist: Dist: PrakasamPrakasam

Singaraya Hills plans to expand its wood chips

based power plant capacity from 6 MW to 8 MW at

Hasnapur power plant in Prakasam district of AP.

Power Generation Projects Page 8

Page 9: 03 Hard Copy Format for Sep

Updated: Sept, 09

Implementation Schedule: As of July 2009, PPA has

been signed with Tata Power and clearances have been

obtained. An agreement is likely to be signed with

NEDCAP & TATA Power. The project will be completed in

24 months from the date of signing the agreement.

Singaraya Hills Green Power Genco Private

Limited, No. 40-1-21/ 21, Catholic Complex, MG

Road, Vijayawada Krishna 520010, Andhra Pradesh

India. Tel: +91 40 23202391.

KARNATAKA 

STATUS: PLANNING

Promoter: Promoter: Astonfield Renewable Resources Astonfield Renewable Resources Proj: Proj: Non ConventionalNon Conventional Cap: Cap: 10 MW10 MW

Astonfield Renewable Resources plans to set up 10

MW Solar Power project in Karnataka. Implementation

Schedule: As of July 2009, the Government allocation

has been received by the company. The project is in a

nascent stage.

Astonfield Renewable Resource Private

Limited, Room No. 112 & 107, DBS House, 10/ 2,

Hungerford Street Kolkata 700017, West Bengal,

India. Tel: +91 33- 32443981. Fax: + 91 33 -

40509300. Email: [email protected].

Website: www.astonfield.com 

STATUS: COMMISSIONED

Promoter: Promoter: Hare Krishna Metallics Hare Krishna Metallics Proj: Proj: Non Non ConventionalConventional Cap: Cap: 12 MW 12 MW LocLoc: Hirebagnal : Hirebagnal DistDist: : KoppalKoppal

Hare Krishna Metallics has set up 12 MW coal & waste

heat recovery based power plant at Hirebagnal in Koppal

district of Karnataka. The first unit comprises of coal

based 8 MW, the second unit of 2 MW waste heat

recovery based while the third unit of 2 MW waste heat

recovery based. Raghu Engineers, Raipur is the project

consultant and Thermax, Pune is the EPC contractor.

Implementation Schedule: As of July 2009, the first unit

was commissioned in first week of July. The second unit

is under final stages of completion and will be

commissioned in the third week of July. The third unit

will be commissioned in a week thereafter.

Hare Krishna Metallics Private Limited, Survey

No. 20, Kasan Road, Village & Post Hirebangal,

Koppal 583228, Karnataka India. Tel: +91 8539-

264123 / 264124 / 264125 / 264126. Fax: + 91

8539-264122. Email: [email protected]

Website: www.harekrishnametallics.com.

Thermax Limited, Thermax House, 4, Mumbai-

Pune Road, Shivajinagar, Pune 411005,

Maharashtra, India. Tel: +91 20-25542122. Fax: 91-

20-25542122. Email: [email protected].

Website: www.thermaxindia.com 

STATUS: PLANNING

Promoter: Promoter: Ind-Barath Power (Karwar) Ind-Barath Power (Karwar) Proj: Proj: Thermal Thermal Cap: Cap: See BelowSee Below Loc Loc: Hankon : Hankon DistDist: Uttar : Uttar KannadaKannada

Ind-Barath Power (Karwar) plans to set up a thermal

power plant in two Phases at Hankon in Uttar Kannada

district of Karnataka. Phase I will comprise of 2x150 MW

and the Phase II of 1x150 MW PPs. Aquatherm

Engineering, Chennai is the project consultant.

Implementation Schedule: As of June 2009, land

development and various clearances are under progress.

The first unit is slated for completion in 2 years.

Ind Barath Power (karwar) Limited, Plot No.

30-A, Road No. 1, Film Nagar, Jubilee Hills

Hyderabad 500033, Andhra Pradesh India. Tel: +91

40 23553459 / 23553460. Fax: + 91 40-23607522.

Email: [email protected]. Website:

www.ibpil.co.in.

Aquatherm Engineering Consultants Private

Limited, St. Thomas Building, 2nd Floor, Western

Wing, New No. 68, Old No. 150, Luz Church Road,

Mylapore, Chennai 600004, Tamil Nadu. Tel: 91-44-

24660462 / 24660464. Fax: 91-44-24996085. Email:

[email protected] 

STATUS: PLANNING

Promoter: Promoter: Maharashtra Seamless Maharashtra Seamless Proj: Proj: CCaptive aptive Power Plant Power Plant Cap: Cap: 80 MW 80 MW Loc:Loc: Koppal Koppal

Maharashtra Seamless is planning to set up 80 MW

waste heat recovery based captive power plant at its

Koppal steel unit in Karnataka. Implementation

Schedule: As of July 2009, land acquisition is under

progress and DPR is under preparation. The project

consultant is being finalized.

Power Generation Projects Page 9

Page 10: 03 Hard Copy Format for Sep

Updated: Sept, 09

Maharashtra Seamless Limited, JINDAL

CORPORATE CENTRE, Plot No 30 Sector 44 Gurgaon

122001, Haryana India. Tel: +91 124-4624000. Fax:

+ 91 124- 2574327/ 4624215. Email:

[email protected]. Website: www.jindal.com 

STATUS: PLANNING

Promoter: Promoter: PGM Ferro SteelsPGM Ferro Steels Proj: Proj: CCaptive Power aptive Power Plant Plant Cap: Cap: 2x2.5 MW2x2.5 MW Loc Loc: Hariginadoni : Hariginadoni DistDist: : BellaryBellary

PGM Ferro Steels plans to set up 2x2.5 MW WHR based

captive power plant at its Hariginadoni facility in Bellary

district of Karnataka. Implementation Schedule: As of

July 2009, DPR is yet to be prepared. Further

developments are expected in the following months.

P G M Ferro Steel Pvt Ltd, Door No. 271/ A,

Opp Spicy Venue Restaurant Road No. 10, Jubilee

Hills Hyderabad 500033, Andhra Pradesh. Tel: +91

40-23553170. Fax: 91-40-23553187 

STATUS: IMPLEMENTATION

Promoter: Promoter: Siruguppa Sugars & Chemicals Siruguppa Sugars & Chemicals Proj: Proj: ThermalThermal Cap: Cap: 28.2 MW 28.2 MW Loc:Loc: Desanur Dist: Bellary Desanur Dist: Bellary EDCEDC: Last quarter of 2010.: Last quarter of 2010.

Siruguppa Sugars & Chemicals is setting up a 28.2 MW

bagasse based power plant at Desanur in Bellary district

of Karanataka. Avant Garde has been appointed as the

project consultant, Gannon Dunkerley as the civil

contractor and BHEL as the major equipment supplier.

Implementation Schedule: As of July 2009, civil works

are under progress. The project is scheduled for

completion by the last quarter of 2010.

Siruguppa Sugars & Chemicals Limited,

Siruguppa Taluk, Desanur Bellary Karnataka 583140.

Tel: +918396-221925 / Fax : + 91 8396221924

Bharat Heavy Electricals Limited, BHEL House,

Siri Fort, New Delhi 110049, Delhi India. Tel: +91 11-

26001010 / 66337000 / Fax : + 91 11-26493021./

26492534. Website: www.bhel.com

Avant Garde Engineers & Consultants Private

Limited, No. 68 A, Porur Kundrathur High Road,

Porur, Chennai 600116, Tamil Nadu, India. Tel: +91

44-24827843 / 24828717 / 24828718 / 24828719 /

24828720. Fax: +91 44-24828531. Email:

[email protected]. Website: www.avantgarde-

india.com

Gannon Dunkerley & Company Ltd, B-228,

Okhla Industrial Area, Phase I, New Delhi 110 020,

Delhi. Tel: +91-11-42785500. Fax:91-11-42785512.

Website: www.gannondunkerley.com

KERALA 

STATUS: PLANNING

Promoter: Promoter: Kerala Sponge Iron Kerala Sponge Iron Proj: Proj: Captive Power Captive Power Plant Plant Cap: Cap: 8 MW8 MW Dist Dist: Palakkad: Palakkad

Kerala Sponge Iron is to set up an 8 MW WHR & BFC

based CPP in Palakkad district of Kerala. The project

consultant and EPC contractor have been appointed.

Implementation Schedule: As of July 2009, the financial

closure is awaited and equipment suppliers are on

the verge of being finalised. Civil works are yet to

commence. The project is likely to be completed in 14

to15 months from the commencement of work.

Promoter Company Address Kerala Sponge

Iron Limited, Door No. 29/ 538, 1st Floor, “SREYAS”,

Near Yakkara School Bus Stop, West Yakkara,

Palakkad 678001, Kerala India. Tel: +91 491-

2531698 / 2527956. Fax : + 91491-2530035.

Plt Add: XV-D No. 810, Manthuruthy, Kanjikode

West, Palakkad 678623 Kerala India. Tel: +91 491

2531698 / 2527956. Fax :+ 91-491 2530035. 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Karapuzha Dam Hydel Karapuzha Dam Hydel Cap: Cap: 5 MW 5 MW Dist: Dist: WayanadWayanad

Kerala State Electricity Board plans to set up Karapuzha

Dam based 5 MW hydro power project in Wayanad

district. The project is dam based and the main dam is

Karapuzha Irrigation Dam. Implementation Schedule: As

of July 2009, the Board has approved the project and

various clearances are awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam, Pattom, Thiruvananthapuram 695004,

Kerala India. Tel: +91 471 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Kuttiyadi Tail Race Hydel Kuttiyadi Tail Race Hydel Cap: Cap: 4 MW4 MW Dist Dist: : Kozhikode.Kozhikode.

Power Generation Projects Page 10

Page 11: 03 Hard Copy Format for Sep

Updated: Sept, 09

Kerala State Electricity Board plans to set up a Rs.240

million, (4 MW) Kuttiyadi Tail Race Hydro Power Project

in Kozhikode district. The main river is Kuttiyadi River.

Implementation Schedule: As of July 2009, the Board

has approved the project and various clearances are

awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam Pattom Thiruvananthapuram 695004,

Kerala India. Tel: 91 471 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Pambar Hydel Pambar Hydel Cap: Cap: 40 MW 40 MW Dist: Dist: IdukkiIdukki

Kerala State Electricity Board plans to set up 40 MW

Pambar Hydro Electric Power Project in Idukki district.

The main river is Pambar. Implementation Schedule: As

of June 2009, the preparation of DPR was

completed and approved by the Board and Government

approvals are awaited.

Kerala State Electricity Board ,, Vydyuthi

Bhavanam, Pattom, Thiruvananthapuram 695004,

Kerala India. Tel: +91 471- 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Peechad Hydel Peechad Hydel Cap: Cap: 3 MW3 MW Cost: Cost: Rs.170 million Rs.170 million DistDist: Idukki: Idukki

Kerala State Electricity Board plans to set up a Rs.170

million, (3 MW) Peechad Hydro Power Project in Idukki

district. The project is run-of-river based and the main

river is Western Kallar. Implementation Schedule : As of

July 2009, the Board has approved the project and

various clearances are awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam Pattom Thiruvananthapuram 695004,

Kerala India. Tel: 91 471- 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Porufalls Hydel Porufalls Hydel Cap: Cap: 16 MW16 MW Cost: Cost: Rs.1,630 million Rs.1,630 million DistDist: Ernakulam: Ernakulam

Kerala State Electricity Board plans to set up a Rs.1,630

million, (16 MW) Porufalls Hydro Power Project in

Ernakulam district. The project is run-of-river based and

the main river is Periyar. Implementation Schedule : As

of July 2009, the Board has approved the project and

various clearances are awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam Pattom Thiruvananthapuram 695004,

Kerala India. Tel: 91 471- 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Vakkallar Hydro Electric Power Project Vakkallar Hydro Electric Power Project Cap: Cap: 24 MW24 MW DistDist: Patthanamthitta: Patthanamthitta

Kerala State Electricity Board plans to set up Vakkallar

Hydro Electric Power Project (24 MW) in

Patthanamthitta district. The main river is Vakkalar.

Implementation Schedule: As of June 2009, the

preparation of DPR have been completed & approved by

the Bboard and Government approvals are awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam, Pattom, Thiruvananthapuram 695004,

Kerala India. Tel: 91 471- 2448989. Website:

www.kseboard.com 

STATUS: PLANNING

Promoter: Promoter: Kerala State Electricity Board Kerala State Electricity Board Proj: Proj: Upper Kallar Hydel Upper Kallar Hydel Cap: Cap: 2 MW2 MW Cost: Cost: Rs.123 million Rs.123 million DistDist: Idukki.: Idukki.

Kerala State Electricity Board plans to set up a Rs.123

million, (2 MW) Upper Kallar Hydro Power Project in

Idukki district. The project is run-of-river based and the

main river is Kallar. Implementation Schedule: As of July

2009, the Board has approved the project and various

clearances are awaited.

Kerala State Electricity Board, Vydyuthi

Bhavanam, Pattom, Thiruvananthapuram 695004,

Kerala. Tel: 91 471-2448989. Website:

www.kseboard.com

TAMIL NADU 

STATUS: IMPLEMENTATION

Power Generation Projects Page 11

Page 12: 03 Hard Copy Format for Sep

Updated: Sept, 09

Promoter: Promoter: Dharani Sugars & Chemicals Dharani Sugars & Chemicals Proj: Proj: Thermal Thermal Cap: Cap: 22MW 22MW Loc: Loc: Kalayanallur Kalayanallur Dist: Dist: Villupuram Villupuram EDC: EDC: End of 2009End of 2009

Dharani Sugars & Chemicals is setting up 22MW bagasse

based co-gen power plant at Kalayanallur in Villupuram

district of Tamil Nadu. Consultants and contractors have

been appointed. Implementation Schedule: As of July

2009, civil works is under progress. The project is

scheduled for completion by end of 2009.

Dharani Sugars and Chemicals Limited, PGP

House, No. 57, Sterling Road Nungambakkam

Chennai 600034 Tamil Nadu India. Tel: +91 44-

28311313 / 28254176 / 28252789. Fax: + 91 44-

28232074.

Plt: Unit II, Kalayanallur, Pallagacharry Post,

Shankarapuram Taluk, Viluppuram 606206, Tamil

Nadu, India

Power Generation Projects Page 12

Page 13: 03 Hard Copy Format for Sep

Updated: Sept, 09

BIHAR 

STATUS: PLANNING

Promoter: Promoter: Astonfield Renewable Resources Astonfield Renewable Resources Proj: Proj: Non ConventionalNon Conventional Cap: Cap: 100 MW100 MW

Astonfield Renewable Resources is planning to set up

a 100 MW Biomass based power project in Bihar. Rice

husk will be used as fuel. Implementation Schedule: As

of July 2009, the Government allotment has been

received by the company. The project is in a nascent

stage.

Astonfield Renewable Resource Private

Limited, Room No. 112 & 107, DBS House, 10/ 2,

Hungerford Street, Kolkata 700017, West Bengal,

India. Tel: +91 33- 3244398. Fax: + 91 33 –

40509300. Email: [email protected]

Website: www.astonfield.com/contactus.html 

STATUS: IMPLEMENTATION

Promoter: Promoter: Bihar State Electricity Board Bihar State Electricity Board Proj: Proj: PowerPower TransmissionTransmission Cost : Cost : Rs.1,080.2 millionRs.1,080.2 million Dist Dist: Supaul: Supaul

Bihar State Electricity Board is implementing Rural

Eelectrification in Supaul district. Subhash Projects &

Marketing has been awarded the turnkey contract at a

cost of Rs.1,080.2 million. The project details are given

below: a) Supply of materials and equipment for

creation of rural infrastructure and household

electrification in Supaul district on turnkey basis under

Rajiv Gandhi Grameen Vidyutikaran Yojana for a value of

Rs.1,032.6 million. b) Installation / Erection including

associated civil works, testing & commissioning including

performance testing of all equipment supplied under the

supply contract and all other services specified in the

tender documents for creation of rural electricity

infrastructure and household electrification in Supaul

district of Bihar on turnkey basis under Rajiv Gandhi

Grameen Vidyutikaran Yojana for a value of Rs.47.6

million. Implementation Schedule: As of July 2009, the

project is under implementation.

Bihar State Electricity Board, Department Of

Project & Design, Vidyut Bhawan, 4th Floor, J. L.

Nehru Marg, Patna 800021, Bihar, India. Tel:

+91(0612)2235046 / Fax : 91(0612)2227557

Subhash Projects & Marketing Limited, No. 22,

3rd Floor, Block-A, Camac Street, Kolkata 700016,

West Bengal, India. Tel: +91-33-40091200 /

40091201 / 40091202 / 40091203 / 40091204 /

Fax: +91-33-40091303. Website : www.spml.co.in

JHARKHAND 

STATUS: IMPLEMENTATION

Promoter: Promoter: Adhunik Power & Natural Resources Adhunik Power & Natural Resources Proj: Proj: Thermal Thermal Cap: Cap: 2 x 270 MW (Each Phase) 2 x 270 MW (Each Phase) Loc: Loc: Jamshedpur Jamshedpur EDC: EDC: See BelowSee Below

Adhunik Power & Natural Resources is setting up 4 x 270

MW Coal based thermal power plant at Jamshedpur in

Jharkhand in two phases. Phase I and II comprise power

plant of 2 x 270 MW each capacity. DCPL, Kolkata is the

project consultant and BHEL is the main equipment

supplier. Implementation Schedule : As of July 2009,

preliminary civil work is under progress. The first unit of

phase I is expected to be completed by January 2012

and the second unit by March 2012. Work on phase II

will follow 12 months thereafter.

Adhunik Power & Natural Resources Limited,

C/o. Adhunik Group Of Industries, Lansdowne

Towers, 2/ 1A, Sarat Bose Road, Kolkata 700020,

west Bengal. Tel: +91(33)30517100. Fax:

91(33)22890285. Email: [email protected]

Bharat Heavy Electricals Limited, BHEL House,

Siri Fort, New Delhi 110049 Tel:

+91(11)26001010 /66337000.

Fax:91(11)26493021/(11)26492534 Website:

www.bhel.com

Development Consultants Private Limited, 24

B, Park Street, Kolkata -700016, West Bengal, India.

Tel: +91(33)22267601 / 22497603. Fax: 91-(33)-

22492340/ 2492897. Email: [email protected]

Website: www.dcpl.net.in 

STATUS: PLANNING

Promoter: Promoter: Bokaro Power Supply Bokaro Power Supply Proj: Proj: ThermalThermal Cap: Cap: 302 MW to 500 MW302 MW to 500 MW Loc:Loc: Bokaro. Bokaro.

Bokaro Power Supply is planning to expand its Bokaro

Power Plant capacity from 302 MW to 500 MW in

Jharkhand. Mecon, Ranchi has been appointed as

technical consultant. Implementation Schedule: As of

July 2009, DPR and clearances are under progress.

Power Generation Projects Page 13

Page 14: 03 Hard Copy Format for Sep

Updated: Sept, 09

Bokaro Power Supply Company Private

Limited, Corporate Office: Hall No. M-01, Old ADM

Building Ispat Bhawan, Bokaro Steel City Bokaro

Jharkhand India -827001 Tel: +91(6542)240380 /

246101 Fax: 06542)247062. Web: www.bpscl.in

Bokaro Power Supply Company Private Limited

(Registered office) : Ispat Bhawan, Lodi Road New

Delhi 110003, Delhi. Tel: +91(11)24367461 / Fax :

91(11)24367015.

Mecon Limited , Doranda, Ranchi, Jharkhand,

India. Tel:+91(651)2483000. Fax:+91(651)2482214.

ORISSA

STATUS: IMPLEMENTATION

Promoter: Jindal Steel & Power Proj: Transmission Promoter: Jindal Steel & Power Proj: Transmission Cost: Rs. 1200 million Dist: Angul EDC: December Cost: Rs. 1200 million Dist: Angul EDC: December 20102010

Jindal Steel & Power is setting up a Greenfield integrated

steel plant in Angul district of Orissa. The company has

awarded orders for 400/220 kV substations &

transformers to Areva T&D India. The transformers

order is for design, manufacturing, supply at site,

erection, testing & commissioning of 2x315 MVA,

400/220kV interconnecting transformers and 6x120

MVA, 220/34.5kV power transformers. The substation

order includes major AREVA products like 400/220kV

circuit breakers, instrument transformers and

automation system with control and relay panels on

turnkey basis. The company will also execute design &

engineering, supply, erection & commissioning including

detail engineering for civil works related to this

substation. The orders are valued at Rs. 1200 million.

Implementation Schedule : The project is slated for

completion by December 2010.

Jindal Steel & Power Limited, Jindal Centre, 12

Bhikaiji Cama Place New Delhi 110066 , Delhi. India.

Tel: +91-11-26188340 / 26188341 / 26188342 /

26188345. Fax: +91 11 26161271. Email:

[email protected] Website:

www.jindalsteelpower.com

Areva T & D India Limited, A-7, Sector 65,

Noida Gautam Buddha Nagar201301, Uttar

Pradesh. Tel: +91(120)4790000 / Fax :

91(120)4791140. Website: www.areva-td.co.in

SIKKIM

STATUS: IMPLEMENTATION

Promoter: Promoter: Lanco InfratechLanco Infratech Proj: Proj: Hydel Power Hydel Power Cap: Cap: 500 MW 500 MW Cost:Cost: Rs.2,650 million Rs.2,650 million Loc: Loc: Sikkim Sikkim EDC:EDC: 20132013

Lanco Infratech is setting up a 500 MW hydel Power

Plant in Sikkim. The main river is Teesta river. Alstom

Projects India has been awarded the turnkey contract at

a cost of Rs.2,650 million. The scope of work includes

design, engineering, erection, testing & commissioning.

Implementation Schedule: The project is scheduled to

be completed by 2013.

Lanco Infratech Limited, Plot No. 229, Udyog

Vihar, Phase-I Gurgaon Haryana India -122016 Tel:

+91 124-4691000 / 4691001 / 4691002 / 4691003 /

4691004 / Fax : +91 124-4691112 Website:

www.lancogroup.com

Alstom Projects India Limited, IHDP Building,

Plot No. 7, Sector 127, Noida, Gautam Buddha

Nagar 201301, Uttar Pradesh. Tel: +91 120-4731100

/ Fax: + 91 120- 4731200. Website :

www.in.alstom.com

TRIPURA

Power Generation Projects Page 14

Page 15: 03 Hard Copy Format for Sep

Updated: Sept, 09

STATUS: IMPLEMENTATION

Promoter: Promoter: North East Transmission Company North East Transmission Company Proj: Proj: Transmission Transmission Cap: Cap: 726.6 MW 726.6 MW Cost: Cost: Rs. 3640 millionRs. 3640 million Loc: Loc: Pallatana Pallatana EDC:EDC: February 2012 February 2012

North East Transmission Company (a JV of ONGC, IL&FS

and Govt. of Tripura) is undertaking Power transmission

projects associated with the 726.6 MW gas based power

plant at Pallatana in Tripura. The company has awarded

two orders to KEC International for supply of towers,

hardware, line materials and construction of 1) Package

A3: 400 kV D/C Khelerihat-Byrinhat transmission line

with a route length 119 Kms in the State of Meghalaya.

2) Package A4: 400 kV D/C Byrnihat – Bongaigaon

Transmission line with a route length of 203 Kms in the

State of Assam. The orders are valued at Rs. 3640

million. Implementation Schedule: They are scheduled

for completion by February 2012.

North East Transmission Company Limited, 1st

Floor, Corporate Towers, Ambience Mall Complex,

Ambience Island, NH-8 Highway, Near Toll Plaza

Gurgaon Haryana 122001 Tel: 91(124)4716115 /

4716117 / Fax : 91(124)4716120. Website:

www.tripurapower.com

K E C International Limited (Registered office) :

1st Floor, CEAT Mahal, 463, Dr. Annie Besant Road,

Worli, Mumbai 400030 Maharashtra. Tel:

+91(22)66670200 / Fax : 91(22)66670286 Email:

[email protected]

Website :www.kecrpg.com

K E C International Limited (Branch Office) :

DLF Infinity Towers, 7th Floor, Tower-'B', DLF City,

Phase-II, Gurgaon 122002, Haryana India. Tel: +91

124- 4188777. Fax: +91 124- 4188617. Email:

[email protected]

Website :www.kecrpg.com

WEST BENGAL

STATUS: IMPLEMENTATION

Promoter: Promoter: Astonfield Renewable Resources Astonfield Renewable Resources Proj: Proj: Non Conventional Non Conventional Cap: Cap: 10 MW10 MW Dist Dist: Bankura : Bankura EDCEDC: : December 2009December 2009

Astonfield Renewable Resources is setting up a 10 MW

Solar PV power project in Bankura district of West

Bengal. Implementation Schedule : As of July 2009, civil

works are under progress. The project is slated to be

completed by December 2009.

Astonfield Renewable Resource Private

Limited, Room No. 112 & 107, DBS House, 10/ 2,

Hungerford Street, Kolkata 700017, West Bengal,

India. Tel: 91-33-3244398. Fax: 91 33–40509300.

Email: [email protected] Website:

www.astonfield.com/contactus.html 

STATUS: PLANNING

Promoter: Promoter: Astonfield Renewable Resources Astonfield Renewable Resources Proj: Proj: Non Conventional Non Conventional Cap: Cap: 10 MW 10 MW Loc:Loc: Gangarampur Gangarampur DistDist: South Dinajpur: South Dinajpur

Astonfield Renewable Resources plans to set up a 10

MW Biomass based power project at Gangarampur in

South Dinajpur district of WB. Rice husk will be used as

fuel. Implementation Schedule : As of July 2009, the

Government allotment of land has been received by the

company. The project is in its nascent stage.

Astonfield Renewable Resource Private

Limited, Room No. 112 & 107, DBS House, 10/ 2,

Hungerford Street, Kolkata -700017 , West Bengal,

India Tel: +91 33- 3244398. Fax: + 91 33 –

40509300. Email: [email protected]

Website: www.astonfield.com/contactus.html 

STATUS: IMPLEMENTATION

Promoter: Promoter: West Bengal State Electricity West Bengal State Electricity Transmission Company Transmission Company Proj: Proj: Transmission Transmission CostCost: Rs.: Rs. 1070 million.1070 million.

West Bengal State Electricity Transmission Company is

implementing two Power transmission projects. The

company has awarded two orders to KEC International

for supply of towers, line materials and construction of

1. 400 kV S/C transmission lines associated with

Kolaghat TPS having a total length of 90.5 Kms. The

duration of the turnkey project is 24 months. 2. 220 KV

DC transmission lines from Kharagpur 400 KV Substation

to Midnapore 220 /132 KV substation and 220 kV DC

transmission lines from 400 KV Subhasgram (PGCIL)

Substation to Saltala. The total route length of the lines

is 58.5 Kms. Implementation Schedule : The duration of

the turnkey project is 18 months. The orders are valued

at Rs. 1070 million.

West Bengal State Electricity Transmission

Company Limited, Vidyut Bhavan, 10th Floor, A-

Block, Salt Lake City, Sector-II, Kolkata 700091, West

Power Generation Projects Page 15

Page 16: 03 Hard Copy Format for Sep

Updated: Sept, 09

Bengal, India. Tel: 91 33-23580065.

Fax : + 91 33-23377957. Website: www.wbsetcl.in

K E C International Limited, DLF Infinity

Towers, 7th Floor, Tower-'B', DLF City, Phase-II,

Gurgaon 122002, Haryana. Tel: +91 124-4188777.

Fax: +91 124- 4188617. Email:

[email protected]. Web: www.kecrpg.com

Power Generation Projects Page 16

Page 17: 03 Hard Copy Format for Sep

Updated: Sept, 09

Brief Note onStatus of Power Projects

 We have taken utmost care to present data region-wise and state-wise in this monthly update service. Within each state, we have placed projects in an alphabetical sequence. We have also given great deal of importance to the accuracy of the information. However, dispite our best efforts it is possible that some errors might have crept in, which may kindly be brought to our notice. It may be noted that the projects are discussed under the following categories. 

CONCEPTUAL STAGE Scheme identified but yet to be taken up for execution Scheme identified and request for pre-qualification yet to be invited Scouting for technical know-how, fuel and land Expression of interest invited Pre-qualification bids invited/ received Project promoter decides to diversify/ takes investment decision MOU under negotiation/ preparation

 

PLANNING STAGE DPR under preparation Financial closure being achieved Land being acquired Steps initiated to receive statutory approvals Negotiations initiated with consultants, contractors/ suppliers Implementation schedule announced

 

UNDER IMPLEMENTATION All clearances received Contracts awarded Financial closure acheived Fuel supply firmed up Land acquired Civil works started/ under progress/ completed Pre-commissioning work started/ under progress

 

TRIAL RUNS/ COMMISSIONED All equipments installed successfully Plant inaugurated Trial runs started Plant becomes fully operational

 

UNCERTAIN STATUSProject could not proceed towards implementation due to: Non availability of escrow covers from SEB/ Govt. Paucity of funds Non availability of suitable land Impediments in fuel supply

 

Project work held up at site due to: Objections raised by local public/ action groups Political interference Natural calamities Change in management/ M&A

Power Generation Projects Page 17

Page 18: 03 Hard Copy Format for Sep

Updated: Sept, 09

ABBREVIATIONS/ ACRONYMS USEDBOOTBOOT : Build Own Operate & Transfer: Build Own Operate & Transfer

BCTBCT : Build Commission & Transfer : Build Commission & Transfer

CAPCAP : Capacity : Capacity

CEACEA : Central Electricity Authority: Central Electricity Authority

CCFICCFI : Cabinet Committee on Foreign Investment: Cabinet Committee on Foreign Investment

CCPPCCPP : Combined Cycle Power Project: Combined Cycle Power Project

CORPCORP : Corporation: Corporation

Cu.MtrsCu.Mtrs : Cubic Meters: Cubic Meters

Dist.Dist. : District : District

EDCEDC : Expected Date of Commissioning/ Completion: Expected Date of Commissioning/ Completion

DPRDPR : Detailed Project Report: Detailed Project Report

EIAEIA : Environment Impact Assessment: Environment Impact Assessment

EPCEPC : Engineering Procurement & Construction: Engineering Procurement & Construction

Eqpt.Eqpt. : Equipment: Equipment

FIPBFIPB : Foreign Investment Promotion Board: Foreign Investment Promotion Board

FSAFSA : Fuel Supply Agreement: Fuel Supply Agreement

HOHO : Head Office: Head Office

KVKV : Kilo Volts: Kilo Volts

KVAKVA : Kilo Volts Amperes: Kilo Volts Amperes

KWKW : Kilo Watts: Kilo Watts

KWHKWH : Kilo Watt Hours: Kilo Watt Hours

LocLoc : Location: Location

LOILOI : Letter of Intent: Letter of Intent

LtrsLtrs : Litres : Litres

MoEFMoEF : Ministry of Environment & Forest: Ministry of Environment & Forest

MNESMNES : Ministry of Non-Conventional Energy Sources: Ministry of Non-Conventional Energy Sources

MWMW : Mega Watts: Mega Watts

MoUMoU : Memorandum of Understanding: Memorandum of Understanding

NANA : Not Available: Not Available

Nos.Nos. : Numbers: Numbers

O&MO&M : Operation & Maintenance: Operation & Maintenance

OffOff : Office: Office

PPAPPA : Power Purchase Agreement: Power Purchase Agreement

P.O.P.O. : Post Office: Post Office

PSSPSS : Pumped Storage Scheme: Pumped Storage Scheme

Plt.Plt. : Plant: Plant

Proj.Proj. : Project: Project

RFQRFQ : Request for Qualification: Request for Qualification

RFPRFP : Request for Proposal: Request for Proposal

RORO : Registered Office: Registered Office

SEBSEB : State Electricity Board: State Electricity Board

SIASIA : Social Impact Assessment : Social Impact Assessment

STPPSTPP : Super Thermal Power Plant: Super Thermal Power Plant

Sq.Mtrs. : Square MetersSq.Mtrs. : Square Meters

TPATPA : tonnes per annum: tonnes per annum

TPDTPD : tonnes per day: tonnes per day

TPSTPS : Thermal Power Station: Thermal Power Station

YrYr : Year: Year

Note: Costs are expressed in Millions of Rupees. (One Million equals Ten Lakhs)Note: Costs are expressed in Millions of Rupees. (One Million equals Ten Lakhs)

Power Generation Projects Page 18