02779-rizhao project quality plan
TRANSCRIPT
-
8/1/2019 02779-Rizhao Project Quality Plan
1/19
Bluewater Bio
105 Wigmore Street
London W1U 1QY
Tel +44 (0)207 518 1726
Fax +44 (0)207 493 0071
///March 2011/i/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
i
Tubli WPCC
Upgrading of Secondary
Treatment Using HYBACS at TubliWPCC
035-Q-7003
In the interests of conservation, this
document has been prepared for
doubled-sided printing.
-
8/1/2019 02779-Rizhao Project Quality Plan
2/19
Project Quality Plan
035-Q-7003
This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other
project or purpose without obtaining prior written approval from Bluewater Bio Ltd. Bluewater Bio Ltd accepts noresponsibility or liability for the consequences arising should this document be used for a purpose other than the purposes for
which it was commissioned and intended. Any person using or relying on the document for such other purpose agrees and willby such use or reliance be taken to confirm his agreement to indemnify Bluewater Bio Ltd. for all loss or damage resultingtherefrom. Bluewater Bio accepts no responsibility or liability for this document to any party other than the person for whom itwas commissioned or intended.
///March 2011/ii/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
ii
-
8/1/2019 02779-Rizhao Project Quality Plan
3/19
List of Contents
Sections and Appendices
1 Preface 1
1.1 Puprose of the Outline Project Quality Plan 1
1.2 Amendment Record 1
1.3 Distribution Record 1
2 Introduction 2
2.1 General 2
2.2 Reference Documentation 2
2.3 Contacts 3
2.4 Scope of Works Summary 3
3 Project Specific Requirements 4
3.1 Management Responsibility 4
3.1.1 Project Review 4
3.1.2 Design Reviews 5
3.1.3 Project Quality Plan Review 5
3.2 Contract Review 5
3.3 Design Control 5
3.4 Design Programme 6
3.5 Design Approval 6
3.6 Design Reviews 6
3.7 Design Variations 7
3.8 Document and Data Control 7
3.9 Selection & Control of Sub-Contractors 7
3.10 Product Identification and Traceability 7
3.11 Inspection and Testing 8
3.12 Inspection, Measuring and Test Equipment 8
3.13 Inspection and Test Status 8
3.14 Control of Non-conformances 8
3.15 Corrective and Preventative Action 9
3.16 Handling, Storage, Packaging, Preservation and Delivery 9
3.17 Quality Records 9
///March 2011/iii/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
iii
-
8/1/2019 02779-Rizhao Project Quality Plan
4/19
3.18 Quality Audits 10
3.19 Training 10
3.20 Statistical Techniques 10
4 Project Organisational Structure 10
5 Project Reporting 10
Appendix A Project Organisational Structure 11
Appendix B Project Status Report Form 13
Appendix C Report Data Input Table Do Not Delete from Electronic Document 14
Tables
No numbered tables
Figures
No numbered tables
///March 2011/iv/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
iv
-
8/1/2019 02779-Rizhao Project Quality Plan
5/19
Page not used
///March 2011/v/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
v
-
8/1/2019 02779-Rizhao Project Quality Plan
6/19
1 Preface
1.1 Puprose of the Outline Project Quality Plan
The purpose of this Project Quality Plan is to describe how the Bluewater Bio Quality Management
System (QMS), will be applied to Upgrading of Secondary Treatment Using HYBACS at Tubli
WPCC project. This is a key document within the QMS and identifies the particular responsibilities,
procedures, method statements, inspection and testing requirements and records required to meet the
project specification.
1.2 Amendment Record
Amendments made to this Plan are to be recorded below. Holders of controlled copies of this plan and
those who may be affected by any changes must be informed of the revision update.
Issue
No
Date Amendment
Authorised By
Pages
Amended
Description
1 31-10-2011 Matt Rolls n/a Contract Issue For Information
2
3
1.3 Distribution Record
Distribution of controlled copies of this plan is to be recorded below.
Date Distribution
Authorised By
Issue No.
Distributed
Distribution details
(who,company,client.etc)
12-05-2010 Adrian Harris A Pre-Contract Issue to MoW
For Information
31-10-2011 Matt Rolls 1 Contract Issue to MoW For
Information
Page | 1
////1/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
7/19
2 Introduction
2.1 General
This Project Quality Plan, for the Upgrading of Secondary Treatment Using HYBACS at Tubli WPCC
project has been produced in accordance with the requirements of the Bluewater Bio Quality
Management System (QMS).
2.2 Reference Documentation
The Following documentation is to be read in conjunction with this outline Project Quality Plan:
Project Execution Plan
This plan is produced by Bluewater Bio, is the lead plan, and will detail the overallmanagement of the project, interfaces with other plans, (commissioning, environmental,
health & safety & sub-contractor supplied plans, etc.), and quality issues associated with the
construction of the contract. Sections of this document are meant for Bluewater Bio internal
use only and these will be omitted from any issue to external sources.
Construction Health & Safety Plan
This plan is produced by Bluewater Bio and deals with the health and safety issues and site
management details associated with the contract. This plan is monitored and updated in
accordance with developments of the project.
Following entrance into the contract execution phase of the project, the following documentation willbe produced:
Project Environmental Plan
This plan is produced by Bluewater Bio during the detailed design phase, will be the lead
environmental plan, and deals with all significant environmental issues of the contract during
the construction phase.
Site Waste Management Plan
This plan is produced by Bluewater Bio during the detailed design stage and will be
developed as the contract progresses
Commissioning Plan
This plan is produced by Bluewater Bio and deals with the commissioning strategy for the
HYBACS plant.
Although produced as individual plans, with them all interlinked with each other, they are issued as
separate documents to concentrate on their specific subject and to ensure that all contract requirements
and key activities are covered.
All plans will include, where relevant, organisation charts, roles and responsibilities, references to
standard procedures and process, and any project specific procedures or processes. Documentation
Page | 2
////2/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
8/19
produced in accordance with these plans will not normally become part of the plans, but will be
referenced within the appropriate plan and stored separately.
2.3 Contacts
Client Details
Name Bahrain Ministry of Works
Address P.O. Box 5, Manama, Kingdom of Bahrain
Telephone
Contact Name Ayman Shawkat Ahmed Tuffaha
Position SEPPD Project Manager
Client Representative
Name P2M Berlin
Address P.O. Box 37316, Um Al Hassam, Manama, Kingdom of Bahrain
Telephone
Contact Name Kay Uwe Bohlen
Position Project Manager
Contractor
Name Bluewater Bio Zero Waste W.L.L.
Address P.O. Box 3010, Manama, Kingdom of BahrainTelephone
Contact Name Matt Rolls
Position Senior Project Manager
Site Manager Richard Jones
Lead Civil / Mechanical / Electrical Designer Details
Name Bluewater Bio
Address 105 Wigmore Street, London, W1U 1QY
Telephone
Project Manager Terence Hedley
Position Project Manager
2.4 Scope of Works Summary
The works involves of the design, construction, supply and install, testing and commissioning of the
following, including all electromechanical equipment:
New feed chamber and interception of existing flow at outlet of preliminary treatment plant
Page | 3
////3/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
9/19
New Grit Removal Plant
New SMART Feed Pump Station
New SMART Plant
Modification to existing aeration tanks 9 and 10 into HYBACS configuration
New FBDA system for aeration tanks 9 and 10
New Internal Recycle Pump Station within aeration tanks 9 and 10
New feed and distribution chamber for clarifiers 9 12
Modification to existing clarifier de-sludge pipework system
New External Recycle & Surplus Sludge Pump Station
New control panels for HYBACS plant, incl. GRP kiosk and associated services
All associated mechanical works for HYBACS plant upgrade (pipework, supports, etc.)
All associated electrical works for HYBACS plant upgrade (cabling, control system, etc.)
All associated civil works for HYBACS plant upgrade (structures, access steelwork, etc.)
1 Years Operation & Maintenance of HYBACS plant from Take-Over
3 Project Specific Requirements
3.1 Management Responsibility
Bluewater Bio will maintain an Authorised Signatory List on site. This will list the people together
with a specimen signature/set of initials that can authorise various documents throughout the duration
of the project.
3.1.1 Project Review
The project will be reviewed during two sets of regular meetings as detailed within the Project
Execution Plan and listed below:
Weekly Site Meetings: To be held on site and include the Contractors site manager, Client
Representatives Site Engineer and representatives of the Clients on-site
team. Additional attendees shall attend as required, these would include
designers, project managers and representatives of sub-contractors.
Monthly Progress Meetings: To be held at a location requested by the Client and will be attended by
the Clients project manager, Client Representative Project Manager and
Contractors Project Manager as a minimum.
Prior to the monthly Progress Meeting, the Bluewater Bios Project Manager will review the progress
of the project. This review may include, but not be limited to; programme and progress; design issues;
construction, safety, environmental and quality issues; outstanding queries; variations and their
resultant effects; sub-contractor and supplier procurement; and complaints from the public or
stakeholders.
Page | 4
////4/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
10/19
All relevant points from this review will be included within Bluewater Bios Monthly Status Report.
Where this review identifies issues of significant importance that requires action by Bluewater Bio or
another party, details of these issues will be given, together with any proposals to rectify the situation.
This will include any issue where work has been identified as being non-compliant with the
requirements of the contract. Agreement to any rectification methods or corrective action will be
recorded in the minutes of the meeting.
3.1.2 Design Reviews
Undertaken at regular intervals by Bluewater Bio, these meetings will review the design process, the
design output, design approval and co-ordination, and any other design related issues. The results of
these meetings will be recorded with agreed actions noted.
All design matters will be recorded and included on the relevant detailed design documentation and
will be submitted to the Client Representative for Client approval in accordance with the project
programme.
Where the design issues have significant effect, or require input from a wider panel of personnel, these
will be recorded in our weekly report and discussed at the Progress Meeting.
3.1.3 Project Quality Plan Review
Formal reviews are undertaken quarterly, but this document remains live throughout the project to
reflect current status at all times during the project life cycle. Where significant changes have occurred
prior to the quarterly review, the plan will be revised and re-issued. Where applicable, these changesshall be subject to the approval of the Client / Client Representative.
3.2 Contract Review
Following the receipt of first draft project specific contract documentation from the Client, the project
team will meet to review the requirements of this documentation. The review meeting will be attended
by key personnel associated with this project, and will discuss the Contract requirements, design,
safety, environmental and quality requirements, and the method and programme of construction.
Where applicable, Bluewater Bio will revert to the Client with comments, amendments andqualifications on the draft contract documentation with a view to finalising the content of the final
contract. Upon finalisation of the contract documentation, Bluewater Bio will proceed with final sub-
contractor negotiations.
3.3 Design Control
Where Bluewater Bio, or their sub-contractors, is responsible for design, the design process will be
managed as detailed below:
Page | 5
////5/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
11/19
Work Scope - check that the scope of works to be designed is fully defined and understood
and any discrepancies brought to Clients attention.
Specifications and Standards - check that the specifications and standards listed as applicable
within the contract agreement and that the works are to be designed to are fully defined,
applicable and available.
Receipt of Information - check that the receipt of information (drawings, specifications) is
complete and correct and can allow the full scope of the works to be progressed.
Design Philosophy - check for any design philosophy requirements or any specific restrictive
regulation or obligation.
Design Team Organisation - identify from the above the design activities required and assign
appropriate qualified staff.
Check all design information has been issued to sub-contractors and has been understood
Attend design meetings as required to liaise with Client / Client Representative.
Ensure design has gone through the Bluewater Bio quality management system proceduresprior to issue to Client and sub-contractors.
Ensure that all design output is checked to ensure that it has been compiled in accordance
with design input information and specified requirements.
3.4 Design Programme
A design programmes is produced and is kept as a live document throughout the project
life cycle.
The design programme is incorporated into the overall project programme and this will be
distributed to all required parties, including the Client / Client Representative with the
Monthly Status Report. Ensure that all the design programmes are co-ordinated between each party and satisfy the
Contract Programme requirements.
3.5 Design Approval
Submit For Construction design documentation to Client Representative for approval
Receive co-ordinated comments on submitted design data within 21 days
Where applicable, forward co-ordinated comments onto relevant sub-contractors
Where applicable, revise design in accordance with comments received from Client
Representative Where applicable, re-submit For Construction design to Client Representative for approval
Following approval of For Construction design, all future issues of design documentation
to be issued as For Information until As Built phase.
3.6 Design Reviews
Design Input confirm receipt of information required, including approved copies of
drawings from sub-contractors, and highlight any interface problems.
Design Programme ensure design output complies with the agreed design programme
requirements.
Page | 6
////6/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
12/19
-
8/1/2019 02779-Rizhao Project Quality Plan
13/19
3.11 Inspection and Testing
Inspection and Test Plans shall be produced that cover all relevant activities of the Works and will
identify all pre-planned inspection and tests that have to be undertaken to verify conformance to the
requirements of the specifications and contract documentation.
Inspection and Test Plans will indicate each inspection stage, the relevant specification reference, the
person responsible for the inspection or test, the frequency of the inspection or test, the verifying
document produced, and file where the document is stored.
Registers and copies of all current Inspection and Test Plans, Methods Statements and Risk
Assessments will be maintained and kept up to date by the Site Manager. These documents will not
form part of this plan, but will be stored in a designated location specified by the Site Manager.
3.12 Inspection, Measuring and Test Equipment
All equipment supplied for use by Bluewater Bio, or where applicable their nominated sub-
contractors, will be checked to ensure that it has a current calibration certificate traceable to National
Standards, is fit for its intended purpose and that it is regularly checked for accuracy. An initial check
will be made upon receipt and thereafter at the stipulated intervals detailed within standard procedures
or work instructions. Any equipment that is found not to have a valid calibration certificate, is
damaged, or outside the specified accuracy parameters, will be withdrawn from use, quarantined, and
returned to the provider for re-calibration.
All measuring, inspection and test equipment, when not is use, shall be stored in a secure manner and
in accordance with the manufacturers recommendation, ideally in the provided box.
Equipment that is provided and utilised by a sub-contractor for measuring, inspection or test purposes
shall be checked by a Bluewater Bio person prior to its use on site. This check shall ensure that
equipment has a valid calibration certificate, is fit for its proposed purpose, is undamaged and checked
for accuracy on a regular basis.
3.13 Inspection and Test Status
The inspection and test status of the Works can be ascertained from the relevant inspection records,
which will be retained and filed by the Site Manager, or his nominee. Inspection records may take theform of, but will not be limited to; Bluewater Bio Inspection Record Sheets; sub-contractors records
and documentation; signed off schedules of work; or Certificates of Conformity / Compliance.
3.14 Control of Non-conformances
Where a product or material is found to be non-compliant upon delivery, the material or product shall
not be accepted. The delivery ticket shall be marked as such and the goods returned to the Supplier.
Where a product or material is found to be non-compliant after delivery has taken place, it shall be
segregated and quarantined from conforming material to ensure that it is not incorporated into the
Page | 8
////8/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
14/19
works. Such material shall be clearly labelled. All non-conformances shall be recorded on a non-
confromance report and a non-conformance register shall be maintained.
Where a product or material is found to be non-compliant after installation and during inspection, the
Bluewater Bio inspection personnel will record the details on a Non-conformance Report, maintaining
a Non-conformance Register, and seek the necessary corrective action from the relevant Supplier or
sub-contractor. Upon rectification, the product or material will be re-inspected to close out the non-
conformance. Where a concession is required, the Employers Project Managers consent / approval
will be sought.
3.15 Corrective and Preventative Action
As noted above, non-conforming material or products will be recorded on a Non-conformance Report
with the proposed corrective and preventative actions sought from the relevant Supplier or sub-
contractor. Where a concession is required, consent/approval will be sought from the Client
Representative.
Reviews of the Project Quality Plan will take due cognisance of any Bluewater Bio Non-conformance
Reports and Corrective Action Requests that have been raised. During the weekly review, the Project
Team will consider all non-conformances raised, and where relevant, will include a section in the
weekly report noting the reasons for the defects and the proposed remedial measures being taken.
3.16 Handling, Storage, Packaging, Preservation and Delivery
All materials that Bluewater Bio and their nominated sub-contractors are directly responsible for willbe stored in accordance with the manufacturers recommendations to prevent damage, loss and
contamination. Where materials have a defined shelf life, the Site Manager will ensure that they are
stored in a way to ensure that those with the shortest remaining shelf life are used first.
All products will be handled on site in accordance with the manufacturers recommendations, and in
accordance with local Health and Safety legislation, to ensure that the product is not damaged during
handling, nor are site personnel put at risk.
Where it is considered necessary, Bluewater Bio, or the relevant sub-contractor, will produce a risk
assessment and method statement to cover the delivery, storage, handling and installation of specific
products.
Where the sub-contractor is responsible for the storage of materials, Bluewater Bio will make random
inspections to ensure that the materials are being stored in the correct manner.
3.17 Quality Records
All quality records will be filed, indexed and stored in accordance with their relevant procedure.
Page | 9
////9/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
15/19
3.18 Quality Audits
Independent Auditors appointed by the Project Manager will carry out regular internal Q&E Site
Inspections.
Should these site inspections find major deficiencies or omissions then a full audit will then be
undertaken.
All site inspection & audit reports will be maintained on site, with the originals being filed & retained
by the Project Manager.
3.19 Training
Project specific training, for example site inductions or toolbox talks, are to be identified and
addressed by the Project Team upon commencement of the site activities.
3.20 Statistical Techniques
Statistical techniques will be used to monitor, review and interpret results for the following items, but
not limited to; non conformance reports; corrective action requests; waivers, etc.
4 Project Organisational Structure
Please refer to Appendix A for a copy of the Project Organisational Structure.
5 Project Reporting
Daily Construction Logs will be completed by the Site Manager at the end of every working day and
submitted to the Project Manager. The Project Manager will review and submit to the Client on a
weekly basis.
A monthly status report will be submitted to the Client in accordance with the Clients standard
completion report system.
A template of the Monthly Status Report can be found in Appendix B.
Page | 10
////10/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
16/19
Appendix A Project Organisational Structure
////11/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
17/19
Page not used
////12/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
18/19
Appendix B Project Status Report Form
////13/var/www/apps/conversion/current/tmp/scratch20102/96406032.doc
-
8/1/2019 02779-Rizhao Project Quality Plan
19/19
Appendix C Report Data Input Table Do Not Delete from ElectronicDocument
Note:1
To change a field in any particular row in the right-hand (5th
) column, place the cursor in thesame row in the 4 th column headed X, right click and then left click on Update Field. The field
must contain at least one character which must be a space if no entry is required.
Item Location Bookmark
name
X1 Record of input
Main Title first line Pages i and ii T1 Tubli WPCC
Main Title second
line
Pages i and ii T2 HYBACS Secondary
Treatment Plant
Upgrade
Main Title third line Pages i and ii T3 Project Quality Plan
Left Hand Header
upper line
Left aligned in headers
- upper line
HL1 Tubli WPCC -
HYBACS Secondary
Treatment Plant
Upgrade
Left Head Header
lower line
Left aligned in headers
lower line
HL2 Project Quality Plan
Firms Name Right aligned in
headers first line
HR1 Bluewater Bio Zero
Waste W.L.L.
Client/Associate
(where applicable)
Right aligned in
headers second line
HR2 Bahrain Ministry of
Works
Project Number Footers PRJNR 035Report Number Footers RPTNR /Q/7003
Revision Letter Issue and Revision
Record on page ii and
footers
REV 1
Date of issue or report Page i, Issue and
Revision Record on
page ii and footers
DATE October 2011
035//Q/7003/1/October 2011/14