MATERIAL MANAGEMENT1. A key factor adversely affecting project
performance is the improper handling and management of materials for that project.
2. Materials management is more important on fast-track projects.
3. Design and procurement decisions are made concurrently with construction activities.
![Page 3: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/3.jpg)
MATERIAL MANAGEMENT
![Page 4: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/4.jpg)
MATERIAL MANAGEMENT
![Page 5: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/5.jpg)
MATERIAL MANAGEMENT
![Page 6: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/6.jpg)
MATERIALS MANAGEMENT
![Page 7: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/7.jpg)
MATERIAL MANAGEMENT
![Page 8: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/8.jpg)
MATERIAL MANAGEMENT
![Page 9: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/9.jpg)
MATERIAL MANAGEMENT
![Page 10: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/10.jpg)
MATERIAL MANAGEMENT
![Page 11: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/11.jpg)
MATERIAL MANAGEMENT
![Page 12: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/12.jpg)
MATERIAL MANAGEMENT
![Page 13: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/13.jpg)
MATERIAL MANAGEMENT
![Page 14: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/14.jpg)
MATERIAL MANAGEMENT
![Page 15: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/15.jpg)
MATERIAL MANAGEMENT
![Page 16: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/16.jpg)
MATERIAL MANAGEMENT
![Page 17: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/17.jpg)
Material management route
Fig. 2.11 Typical adverse material management (Thomas et al, 1989)
Poor organisation of storage area on site
Extensive multiple handling of materials
Material badly stored or marked
Poor House Keeping
Wastage on Site
Access to storage area obscured by debris
Lack of planning of material deliveries
Lack of co-ordination between the time of deliveries and erection
Remobilization and re-familiarisation after a lengthy delay
Running out of materials
Lack of anticipation about material shortage
Material management
![Page 18: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/18.jpg)
Sequentialmanner storing
Materialstorage &
coding
Sustainabledevelopment
Improveproductivity
MaterialManagement
Reducewaste
Quantitysurveyors
(theestimator)
ArchitectsDesign
complexity
DeliveryJIT
If left over
Contractormaterialhandling
Useelsewhere
Or recyclingWork hour losses resulting from
poor material management causedcost overrun of 18%.
Reduce > Reuse > Recycle
Architects-Use standard sizesand quantities of materials,
and plan ahead toreduce off cuts.
Avoidover-ordering
CULTUREOF
WASTEREDUCTION
Material management
![Page 19: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/19.jpg)
Site materialsstrategy and
wastemanagement
policy
MonitoringStorageDeliveriesQuantitiesOrdering
Wastecontrol Plant
choice
Material management
![Page 20: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/20.jpg)
PLANNING
![Page 21: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/21.jpg)
PLANNING
![Page 22: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/22.jpg)
PLANNING
![Page 23: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/23.jpg)
PROCUREMENT
![Page 24: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/24.jpg)
PROCUREMENT
![Page 25: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/25.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 26: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/26.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 27: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/27.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 28: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/28.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 29: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/29.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 30: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/30.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 31: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/31.jpg)
EFFECTIVE MATERIAL HANDLING
![Page 32: 027 Fast-Tracked Projects-Materials](https://reader035.vdocuments.us/reader035/viewer/2022062503/58a66c831a28abb47e8b561f/html5/thumbnails/32.jpg)
EFFECTIVE MATERIAL HANDLING
• Delivery of bulk materials in large: transportation for large quantities by rail (e.g. reinforcement/steelwork) or barge (e.g. ballast from a dredger) and for large volume by pipeline (e.g. water/gas/oil/ chalk/cement/concrete) or conveyor (e.g. excavated material/fill).