022 b construction croductivity-write system

48
[email protected] .uk htt://www.construction-productivity.co.uk ON SITE PRODUCTIVITY-WRITE SYSTEM

Upload: dr-fereidoun-dejahang

Post on 13-Apr-2017

18 views

Category:

Engineering


2 download

TRANSCRIPT

Page 1: 022 B Construction Croductivity-WRITE SYSTEM

[email protected]://www.construction-productivity.co.uk

ON SITE PRODUCTIVITY-WRITE SYSTEM

Page 2: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System

Existing construction productivity measurement techniques are not capable of providing the real-time productivity data to project managers and engineers for analyses and sharing the data among participants involved in construction operations.

Page 3: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System On-site productivity problems cannot be taken

just in time. To address these shortfalls, the Wireless Real-

time Productivity Measurement (WRITE) System was developed.

it can measure the on-site construction productivity in real time.

In addition, an on-site construction productivity improvement model using the WRITE System and the benchmark data was developed.

Page 4: 022 B Construction Croductivity-WRITE SYSTEM

WRITE SystemObjective Approach- The real-time productivity data measured by

the WRITE System was compared to the benchmark productivity data.

The results of the comparison provided the necessary information for:

project management team to determine if immediate actions should be taken

Page 5: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Secondly, it provides an advanced

technology for managers to determine on-site construction productivity in real time.

Improving on-site could be taken just in time if needed.

These advancements enhance the contractors’ capability of managing construction projects.

Page 6: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Productivity data have been widely used as

performance indicators: to evaluate construction operations throughout

the entire phase of construction. Construction companies must continuously

track productivity in order to measure their performance.

1. Maintain profitability2. Prepare future biddings

Page 7: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Measuring productivity on site has been an important task in the construction industry.

In the past many On-site productivity measurement techniques have been developed. They include:

questionnaires stopwatch studies photography time-lapse videos video-taping

Page 8: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System In recent years, real-time

monitoring systems have become key methods to reduce the gap between:

1. Actual

2. planned production rates

In an effective way.

Page 9: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System A real-time video system was

developed by Everett and Slocum.

For monitor lifting activities of crane in attempts to improve both productivity and safety of crane operations.

Page 10: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Since 2000, wireless technologies, such as: global positioning system (GPS) radio frequency identification (RFID)

system, were utilized Have been adopted in construction In

order to track the current status of the resources and activities.

Page 11: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System

A GPS technology was used to automatically measure earthmoving performance.

It is by identifying the locations of equipment at regular time intervals,

Converting the information into project productivity (Navon and Shpatnitsky 2005).

Page 12: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

A web-based camera was used to monitor interior construction operations.

This web-based network technology produced an opportunity to avoid using a wired network connection.

In a congested construction jobsite not a good idea (Kang and Choi 2005).

Page 13: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System Existing on-site construction productivity

measurement methods have some common limitations.

They are unable to provide the real-time productivity data for analyses, and sharing the data among participants.

Page 14: 022 B Construction Croductivity-WRITE SYSTEM

WRITE SystemDEVELOPMENT OF WRITE SYTEM The developed WRITE system

includes: A video camera; a digital camera; a data processor;

Page 15: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System an AC transformer; two antennas; A laptop computer as shown in Fig 1. The preliminary test results indicated that

the developed system can measure the on-site construction productivity accurately (Kim 2008)

Page 16: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Page 17: 022 B Construction Croductivity-WRITE SYSTEM

Framework of the WRITE System

Page 18: 022 B Construction Croductivity-WRITE SYSTEM

Development of the Productivity Improvement Model

After building the WRITE System; a model for the on-site construction

productivity improvement was developed. In this model: the first task is to collect pictorial data in

the construction site using the WRITE System.

Page 19: 022 B Construction Croductivity-WRITE SYSTEM

Development of the Productivity Improvement ModelThe second task is: to determine the real-time productivity data

which is the ratio of working and nonworking time.

The third task is: to compare the real-time productivity data

with the productivity benchmark data.

Page 20: 022 B Construction Croductivity-WRITE SYSTEM

WRITE SystemDuring the comparison, Management team MUST answer two

questions, and then make productivity improvement decisions accordingly.

The first question whether the real-time productivity data is

higher than the benchmark data at which action should be taken.

Page 21: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

If the answer for this question is no, management needs to take action

immediately to improve the on-site productivity.

If it is yes, management goes to the next stage to

compare the real-time data with the acceptable benchmark data.

Page 22: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

If the real-time data is > than the acceptable benchmark data,

No action is needed. Otherwise, management needs to be aware that

action may be needed in the near future. It follows with a close monitoring at the construction

site. The developed model can be utilized for the entire

period of construction or for the segments of construction.

Page 23: 022 B Construction Croductivity-WRITE SYSTEM
Page 24: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Work Breakdown Structure (WBS) The work breakdown structure (WBS) has

been widely used to manage the project. WBS is defined as “a deliverable-oriented

grouping of project elements”. which organizes and defines the hierarchical

structure of the entire project (Jung and Woo 2004).

Page 25: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System It is often used in the complex construction

projects. To identify project information. Improve the efficiency of control

processes.

Page 26: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System A WBS shows the relationship of all

project activities. It is at important and decisive levels. WBS makes each activity more

manageable and measurable. The number of levels depends on the

size and complexity of the projects (U.S. Department of Energy 1997).

Page 27: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System The bridge reconstruction project used in

the field experiments was broken down into four levels. They are:

including Level 1 (project) Level 2 (work zone) Level 3 (activity) and Level 4 (operation) Examples of the levels of steel girder

bridge WBSs are shown in Table 1.

Page 28: 022 B Construction Croductivity-WRITE SYSTEM

Table 1. WBS for steel girder bridge reconstruction Level 1 (Project) Level 2 (Work Zone) Level 3 (Activity) Level 4 (Operation)

Steel Girder Bridge General Mobilization Set up Crane Abutment Traffic Control Moving concrete safety barrier Pier 1 Demolition Driving pile Pier 2 Excavation Forming Pier 3 Abutment 1 Structural excavation North side Abutment 2 Slope protection (filter fabric and

rock) South side Pier Drill Shafts Set bearing devices Span 1 Pier Columns Unload beams Span 2 Pier Cap Set beams Span 3 Slope protection Install diaphragms Span 4 Beam Setting Bolting and tightening splice Deck Forming Ground splice Reinforcing Deck Prepare deck material Bridge Barrier Rail Prepare deck forming Concrete Barrier Overhangs Backfill Abutments Strip Approach road Place backwall (strip drain & backfill)

Tying rebar Pouring and curing Others Strip and check elevation

Page 29: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Determining Productivity Benchmark Data Benchmarking has been used as a tool to

improve productivity since the early 1980s. The Construction Industry Institute (CII) has

established construction productivity metrics and a reporting format for construction productivity benchmarking and improvement (Han et al. 2005).

Page 30: 022 B Construction Croductivity-WRITE SYSTEM

WRITE SystemActual working time of construction

workers is at 56% in nuclear plant construction projects (Hewage and Ruwanpura 2006).

Christian and Hachey (1995) studied concrete-placement operations. Their finding showed that:

Page 31: 022 B Construction Croductivity-WRITE SYSTEM

WRITE SystemThere are 61% working time and

39% nonworking time. According to the previous

research projects, the ratio of working time and nonworking time ranges approximately from 50:50 to 60:40.

Page 32: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System There is no consensus on the

acceptance ratio of working time verse nonworking time in the construction industry.

because construction projects have different natures such as different types of projects, activities, and operations.

Page 33: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System

Productive and non-productive time for five bridge operations were identified as:

deck forming tying rebar installing finisher

Page 34: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System backfilling and placing approach road footing. A total of 66 hours of video tapes were

recorded using the WRITE System to determine the productivity rates for the five bridge operations.

Page 35: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System These videos were all taken zoomed-in to

clearly identify: the productive time; nonworking; time for each operation. The ratio of productive and non-productive

time was: 86% and 14% on average as shown in Table 2.

Page 36: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 2. Ratio of working and nonworking time determined by

the WRITE System Operation Time (Second) Percentage (%) Time Nonworking(nonproductive) Time Working Time Nonworking Time Deck forming 24,720 2,160 92 8 Tying rebar 40,320 5,880 87 13 Installing finisher 71,230 21,100 77 23 Placing backwall, strip drain, and backfill44,850 1,950 96 4

Grade and tie approach road footing 21,275 2,725 89 11

Total 202,395 33,815 86 14

Page 37: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System The benchmark data were based on

professional intuitions about rates of working time and nonworking time for each of the five bridge construction operations.

Page 38: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 3. List of survey construction

professionals Name Company Construction Specialty

Position Ken Johnson BRB contractors, Inc. Bridge

Project Manager Mike Laird BRB contractors, Inc. Bridge and

Plant Project Manager Ray Rinne A.M. Cohron & Son, Inc. Bridge Superintendent Christopher J. Rech A.M. Cohron & Son, Inc.

Bridge Project Manager

Page 39: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 4 shows acceptable ratios provided

by four survey participants. The overall average ratio for working time

(WT) was 81% and overall average ratio for nonworking

time (NWT) was 19%. Tying rebar had the highest nonworking

ratio of 21%, while deck forming had the lowest rate of

16%. T

Page 40: 022 B Construction Croductivity-WRITE SYSTEM

On-Site Construction Productivity Using the WRITE System

According to the survey participants, they can accept the working time ratio of at least 79% for these bridge operations.

Table 5 presents ratios at which action should be taken by project managers to improve on-site construction productivity.

Page 41: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System The overall average ratio for WT was

75% and overall average for NWT was

25%. Tying rebar had the highest

nonworking time rate of 28%, while deck forming had the least

nonworking time rate of 23%.

Page 42: 022 B Construction Croductivity-WRITE SYSTEM

Table 4. Acceptable ratio Operation BRB 1 BRB 2 A.M. Cohron 1 A.M. Cohron 2 Average WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) Deck forming 85 15 80 20 85 15 85 15

84 16 Tying rebar 80 20 75 25 80 20 80 20

79 21 Installing finisher 85 15 75 25 85 15 85 15

82 18 Placing backwall, strip drain, and backfill 70 30 80 20 85 15

85 15 80 20 Grade and tie approach road footing 80 20 80 20 85 15

85 15 82 18 Average 80 20 78 22 84 16 84 16 81

19

Note: WT–Working Time; NWT–Nonworking Time

Page 43: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 5. Ratio at which action should be taken Operation BRB 1 BRB 2 A.M. Cohron 1 A.M. Cohron 2 Average WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) WT (%) NWT (%) Deck Forming 75 25 75 25 80 20 80

20 77 23 Tying rebar 70 30 70 30 75 25 75 25

72 28 Installing finisher 75 25 70 30 80 20 80

20 76 24 Placing backwall, strip drain, and backfill 60 40 75 25 80

20 80 20 74 26 Grade and tie approach road footing 70 30 75 25 80 20

80 20 76 24 Average 70 30 73 27 79 21 79 21

75 25

Note: WT–Working Time; NWT–Nonworking Time

Page 44: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 6 presents the results of the comparison

between the benchmarking data from the survey and the real-time productivity data determined by the WRITE System.

For the operation of installing finisher, the nonworking ratio of 24% was equal to the

ratio at which action should be initiated by the construction manager.

The rest of operations had larger working time ratios than the minimum required working ratios.

Page 45: 022 B Construction Croductivity-WRITE SYSTEM

Table 6. Data comparison between the WRITE System and the benchmarks Operation Acceptable Ratio Ratio at which action should be taken WRITE System WT (%) NWT (%) WT (%) NWT (%) WT

(%) NWT (%) Deck Forming 84 16 77 23 92 8 Tying rebar 79 21 72 28 87 13 Installing finisher 82 18 76 24 76 24 Placing backwall, strip drain, and backfill 80 20 74 26

96 4 Grade and tie approach road footing 82 18 76 24

89 11 Average 81 19 75 25 88 12

Note: WT – Working Time; NWT – Nonworking Time

Page 46: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System By comparing the rates from the WRITE System

to the benchmark data, project managers can take actions for improving on-site construction productivity in real time.

As shown in Table 7, there are three cases that project managers can make decision using the developed model.

First, if the productivity ratio measured by the WRITE System is higher than the acceptable ratio,

then, no action is required.

Page 47: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Second, if the ratio is between acceptable

ratios and ratios, at which action should be initiated, then, management needs to be aware that

an action may be needed in the near future.

Finally, if the ratios are lower than the minimum required rate,

then, the project manager needs to take actions immediately.

Page 48: 022 B Construction Croductivity-WRITE SYSTEM

WRITE System Table 7. Making management decisions using

the WRITE System No. Ratios from the WRITE System Action

1 Higher than acceptable ratios No action needed

2 Between acceptable ratios and ratios at which action should be taken Aware that action may be needed

3 Lower than ratios at which action should be taken Action is required