02 project charter (annotated)
TRANSCRIPT
-
8/7/2019 02 Project Charter (Annotated)
1/4
Group 1
Project Management Tools and Techniques
Project Charter
Project Name Laboratory development project
Develop a Project Charter for your chosen project. Use the table below
# Area Description
1 Problem/
Challenge/
Opportunity
Dr. Michael Lipsett intends to reorganize and consolidate some of his lab
space / researchers / facilities from 2 labs into a single new lab.
2 Project
Goal
Use the
SMART
formula
Did you use the
SMART
formula?
Planning the setting up of a new laboratory in Room number MEC E 1-
38 in Mechanical Engineering building by migrating the equipments and
infrastructure from room numbers MEC E 2-22 and MEC E 2-14. Theplanning should facilitate coordinated and optimized movement of labresources in the most efficient way possible such that the disturbance to
the ongoing work/studies in the building is minimized.
Laboratories affected by the migration process need to be thoroughly
inspected for available furniture and equipment, and a tentative layout of
the new lab in MEC E 1-38 needs to be prepared. Discussion withstudents, researchers, faculty members and administrative staff who are
going to be affected has to be undertaken and feedback should be
incorporated in the project plan. The migration process will be conducted
after the Wwinter term of 2011 ends.
3 Project
Deliverables
Others?
(maybe break
down the plan
into separate
deliverables)
1. F A complete plan for a fully functional and operational laboratory setup in MEC E 1-38.
2. Segregated laboratory consisting of two sections for analytical workand hands-on experimentation. (This is part of #1)
3. Infrastructure support for assistance in emergency situations (First-aid,Communication modes, Alarms etc.). (This is also part of #1)
1. Intermediate report (work in progress: outline of requirementspecification, (review templates), (ask Lipsett what he wouldlike))
2. Final Report
3. Contract
4 Imperative
One other?
1. Fully functional and operational laboratory set up in MEC E 1-38.1. Flexible layout for future changes, as well as additional open space for
future expansion
-
8/7/2019 02 Project Charter (Annotated)
2/4
# Area Description
(ex. Equipment
must be easily
moved)
2. Segregated laboratory consisting of two sections for analytical work
and hands-on experimentation.
3. Infrastructure support for assistance in emergency situations (First-aid,
Communication modes, Alarms etc.).
4. Meets AB codes/standards/regulations
5 Desirables
One other?
1. Movement of slurry pipeline in room number Mec E 2-14 to the new
laboratory.
2. Flexible configuration to facilitate easy movements and later changes
in layout.
3. Arrangement flexible for future laboratory expansion. (This is the
same as #2)
2. Balance: quiet space/working space/active lab space
3. Collapsible furniture
6 Assumptions 1. MEC E department will not propose any major configuration changes
at the later stage of project.
2. UWS internet connectivity will be available in the new location (MEC
E 1-38).
3. Power supply will not be interrupted during equipments functionalitytesting in the new lab.
7 Constraints 1. Slurry pipeline will make the new laboratory noisy and we want a
quiet environment to facilitate study and analysis. Thus? (how does
this constrain us?)
2. Project teams timing schedules do not have considerable overlap and
they have different academic commitments. (I think this section involvesproject constraints (by the client), not team constraints)
3. Completion of planning has to be finished before the end of winterterm. Scheduling the teams availability and efforts in line with the
ongoing academic activities has to be achieved. (Same comment as #2)
1. Minimum impact/disturbance to current research work
2. Budget
3. Deadline
-
8/7/2019 02 Project Charter (Annotated)
3/4
# Area Description
8 Stakeholders # Stakeholder name Needs and Expectations
1 Project Owner
(Dr. Lipsett)
Dr. Lipsett needs a smooth transition to
the new laboratory. He expects needs the
complete plan for the new laboratory tobe finished by the end of the winter term.
He expects no disruption to existingresearch projects.
2 Project Manager Project manager needs timely
achievement of project goals within the
approved budget. She expectsimprovement in his herprofessional
growth path.
3 Project Team Project team needs a good environment
where they can apply their skills to the
project in thebest manner. They expectaugmentation in their skill set and as well
as experience.
4 University of
Alberta
University needs requires a fully
functional laboratory compliant to the
relevant technological and safety
standards. It expects introduction ofa newlaboratory to provide more
experimentation options to the professors,
students and researchers.
5 Students in MEC
E department
Students who are not directly affected by
the move need the migration to causeminimum disruption to them. They expect
that the new laboratory will be useful tothem.
6 Students affected
by the move
Students need a well equipped laboratory
which allows them to experiment and
conduct analysis in an ambientatmosphere. They expect that the new
laboratory will not be unfamiliar to them.
7 Technicians Technicians need clear guidelines and
relevant timelines about the migration
process. They expect to acquire goodexposure and new skills during the
migration process. They also expect theproject to fit in their ongoing schedules
and commitments.
8 Glen Thomas Glens Dr. Thomas need is to get a clear
idea of what is required of him so that hecan check the availability and plan
accordingly. His expectations would be
are to getbe notified of any lackdiscrepancies in the facilities.
-
8/7/2019 02 Project Charter (Annotated)
4/4
# Area Description
9 Roger Marchand Rogers Mr./Dr. Marchands need is to
know well in advance specifics relating tothe logistics / scheduling of the moving of
the large mill. He expects the scheduling
will not affect his ongoing commitments
and activities.10 Professors
affected by the
move
The affected Professors need minimumdisruption to their ongoing research and
lab activities. Their expectation would be
that the project team coordinates with
them so that all lab movements are notundertaken at the same time (limited
hallway size). (Is the constraint the lab
equipment that is in use or the hallwaysize? I dont think hallway size is an
issue)
11 Visitors
9 Success
Criteria
1. Fully functional and operational laboratory in MEC E 1-38.
2. Successful commissioning of equipments and other laboratory
infrastructure.
3. Approval of the functioning of new laboratory by Dr. Lipsett.