01720 record document
TRANSCRIPT
![Page 1: 01720 Record Document](https://reader031.vdocuments.us/reader031/viewer/2022021220/577ce1051a28ab9e78b4a251/html5/thumbnails/1.jpg)
7/29/2019 01720 Record Document
http://slidepdf.com/reader/full/01720-record-document 1/4
CERTIFIED
_ __________ DATE: ________
PROJECTENGINEER
____________ DATE
DISCIPLINEENGINEER
__ ________ _ DATE: ________
Saudi Aramco 2616-ENG (3/99)
SAUDI ARAMCO OIL COMPANY
15-Sep-07
OPERATIONS
_____________ DATE:_________
_
R E V .
N O .
D A T E J O
B / E W O
D E S C R I P T I O N
E N G ’ G
C E R T
P M T
O P E R N S .
SAUDI ARABIA
PLANT NO.CONSTRUCTION SPECIFICATIONS
CONSTRUCTIONAGENCY
______________ DATE:
__
COMMUNITY SUPPORT BUILDINGS
Section 01720
SHT. NO.
1OF4
INDEX REV. NO.DWG. TYPE DRAWING NO.
JOB/EWO#
¿
À
¾
RABIGH
KAUST TOWN CENTER RESIDENTIAL &K55 A VE-417361
BI-25-00002
00
DOC
E D S D
V E R I F I C A T I O N
C O N
T R O L N U M B E R
B y :
D a t e :
R E V I S I O N
C E R T I F I C A T I O N
T H I S I N D I C A T E S T H A T R E V . N O .________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R T I F I C A T I O N R E Q U I R E M E N T S , ,
B Y D R A W I N G C O M P L E T I O N C E R T I F I C A T E
( D C C ) N O . :__________________________
SECTION 01720
RECORD DOCUMENTS
SUBSECTION INDEX
Part 1 - General
1.01 Requirements Included1.02 Maintenance of Record Documents and Samples1.03 Identification and Recording1.04 Record Documents
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
PART 1 - GENERAL
1.01 Requirements Included
A. Maintain at the site for Saudi Aramco record copy of:
1. Record Drawings.
2. Construction Progress Schedules.
3. As-Built Drawings.
4. Record Specifications including addenda change orders and othermodifications to the Contract.
5. Record Shop Drawing Information including literature, catalog cuts andtest data.
6. Record Miscellaneous Submittals including inspection and test reports,guarantees, warranties, survey data and commissioning reports.
7. Record Samples.
B. Related Requirements:
1. Section 01340: Shop Drawings, Samples and Miscellaneous Submittals
2. Section 01700: Close-Out Requirements
1.02 Maintenance of Record Documents and Samples
![Page 2: 01720 Record Document](https://reader031.vdocuments.us/reader031/viewer/2022021220/577ce1051a28ab9e78b4a251/html5/thumbnails/2.jpg)
7/29/2019 01720 Record Document
http://slidepdf.com/reader/full/01720-record-document 2/4
CERTIFIED
_ __________ DATE: ________
PROJECTENGINEER
____________ DATE
DISCIPLINEENGINEER
__ ________ _ __ DATE: ______
Saudi Aramco 2616-ENG (3/99)
SAUDI ARAMCO OIL COMPANY
15-Sep-07
OPERATIONS
_____________ DATE:_________
_
R E V .
N O .
D A T E J O
B / E W O
D E S C R I P T I O N
E N G ’ G
C E R T
P M T
O P E R N S .
SAUDI ARABIA
PLANT NO.CONSTRUCTION SPECIFICATIONS
CONSTRUCTIONAGENCY
______________ DATE:
__
COMMUNITY SUPPORT BUILDINGS
Section 01720
SHT. NO.
2OF4
INDEX REV. NO.DWG. TYPE DRAWING NO.
JOB/EWO#
¿
À
¾
RABIGH
KAUST TOWN CENTER RESIDENTIAL &K55 A VE-417361
BI-25-00002
00
DOC
E D S D
V E R I F I C A T I O N
C O N
T R O L N U M B E R
B y :
D a t e :
R E V I S I O N
C E R T I F I C A T I O N
T H I S I N D I C A T E S T H A T R E V . N O .________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R T I F I C A T I O N R E Q U I R E M E N T S , ,
B Y D R A W I N G C O M P L E T I O N C E R T I F I C A T E
( D C C ) N O . :__________________________
A. Store documents and samples in Contractor's field office apart from documentsused for construction. Do not use record documents for construction purposes;protect from deterioration and loss in a secure fire-resistive location; provideaccess to record documents for Saudi Aramco inspection during normal workinghours.
1. Provide files and racks for storage of documents.
2. Provide locked cabinet or secure storage space for storage of samples.
B. File documents and samples in accordance with Saudi Aramco instructions.
C. Maintain documents in a clean, dry, legible condition, and in good order for turnover to Saudi Aramco in accordance with Section 01700 "Close-OutRequirement".
1.03 Identification and Recording
A. Label each document and sample "PROJECT RECORD BOOK" in neat largeprinted letters. As-built drawings shall be stamped as required in 1.4, B. below.
B. Record information concurrently with construction progress.
C. Do not conceal any work until required information is recorded.
1.04 Record Documents
A. Record Drawings: Maintain a white-print set (blue-line or black-line) of Contractdrawings and accepted shop drawings in clean, undamaged condition, with mark-up of actual installations which vary from the work as originally shown. Mark each
drawing showing the as-built condition fully and accurately according to draftingmanual. Mark-up new information which is recognized to be of importance, butas for some reason not shown on either the Contract Drawings or shop drawings.Give particular attention to concealed work which would be difficult to measureand record at a later date. Note related change order numbers where applicable.
B. Construction Progress Schedules:
1. Submit initial progress schedule in duplicate within 20 days after dateestablished in Notice to Proceed for review by Saudi AramcoRepresentative.
2. Submit a computer generated chart with separate line for each majorsection of Work or operation, identifying first work day of each week.
3. Submit computer generated network analysis diagram using the criticalpath method (CPM), generally as outlined in Associated GeneralContractors of America (AGC) publication "The Use of CPM in
![Page 3: 01720 Record Document](https://reader031.vdocuments.us/reader031/viewer/2022021220/577ce1051a28ab9e78b4a251/html5/thumbnails/3.jpg)
7/29/2019 01720 Record Document
http://slidepdf.com/reader/full/01720-record-document 3/4
CERTIFIED
_ __________ DATE: ________
PROJECTENGINEER
____________ DATE
DISCIPLINEENGINEER
__ ________ _ DATE: ________
Saudi Aramco 2616-ENG (3/99)
SAUDI ARAMCO OIL COMPANY
15-Sep-07
OPERATIONS
_____________ DATE:_________
_
R E V .
N O .
D A T E J O
B / E W O
D E S C R I P T I O N
E N G ’ G
C E R T
P M T
O P E R N S .
SAUDI ARABIA
PLANT NO.CONSTRUCTION SPECIFICATIONS
CONSTRUCTIOAGENCY
________________ DATE:
N
COMMUNITY SUPPORT BUILDINGS
Section 01720
SHT. NO.
3OF4
INDEX REV. NO.DWG. TYPE DRAWING NO.
JOB/EWO#
¿
À
¾
RABIGH
KAUST TOWN CENTER RESIDENTIAL &K55 A VE-417361
BI-25-00002
00
DOC
E D S D
V E R I F I C A T I O N
C O N
T R O L N U M B E R
B y : :
D a t e
R E V I S I O N
C E R T I F I C A T I O N
T H I S I N D I C A T E S T H A T R E V . N O .________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R T I F I C A T I O N R E Q U I R E M E N T S , ,
B Y D R A W I N G C O M P L E T I O N C E R T I F I C A T E
( D C C ) N O . :__________________________
Construction - A Manual for General Contractors and the ConstructionIndustry".
The Contractor shall submit the CPM and the computer generated chart14 days counted from day of site handing over.
4. Show complete sequence of construction by activity, identifying Work ofseparate stages and other logically grouped activities. Indicate the earlyand late start, early and late finish, float dates, and duration. Theprogress schedule shall be updated monthly.
5. Indicate estimated percentage of completion for each item of Work ateach submission.
6. Indicate submittal dates required for shop drawings, product data,samples, and product delivery dates.
7. Update of schedule will be as required by Saudi Aramco (minimum once a
month).
C. As-built Drawings:
1. The Contractor shall prepare as-built drawings for delivery to SaudiAramco.
2. The Contractor shall use the original Contract Drawings which have been"Issued for Construction" and original mylar shop drawings which havebeen "Released for Construction," as the basis for the development of the
as-built drawings. The Contractor shall replace the furnished ContractDrawings with updated electronic files.
3. The as-built drawings shall contain all information reflecting theconstructed condition of the facility as recorded on the Record Drawingincluding equipment and/or fixtures installed by the Contractor.
4. The as-built drawings shall be stamped "AS-BUILT". The letter size shallbe 25 mm x 15 mm (height x width).
5. The as-built drawings shall be submitted in accordance with the "ShopDrawing" procedure of Section 01340. After acceptance the Contractor
shall deliver the following:
a. One complete set of accepted original as-built drawings.
b. One complete set of blueline or blackline prints of the approvedas-built drawings.
![Page 4: 01720 Record Document](https://reader031.vdocuments.us/reader031/viewer/2022021220/577ce1051a28ab9e78b4a251/html5/thumbnails/4.jpg)
7/29/2019 01720 Record Document
http://slidepdf.com/reader/full/01720-record-document 4/4
CERTIFIED
_ __________ DATE: ________
PROJECTENGINEER
____________ DATE
DISCIPLINEENGINEER
__ ________ _ DATE: ________
Saudi Aramco 2616-ENG (3/99)
SAUDI ARAMCO OIL COMPANY
15-Sep-07
OPERATIONS
______________ DATE:_________
R E V .
N O .
D A T E J O
B / E W O
D E S C R I P T I O N
E N G ’ G
C E R T
P M T
O P E R N S .
SAUDI ARABIA
PLANT NO.CONSTRUCTION SPECIFICATIONS
CONSTRUCTIONAGENCY
______________ DATE:
__
COMMUNITY SUPPORT BUILDINGS
Section 01720
SHT. NO.
4OF4
INDEX REV. NO.DWG. TYPE DRAWING NO.
JOB/EWO#
¿
À
¾
RABIGH
KAUST TOWN CENTER RESIDENTIAL &K55 A VE-417361
BI-25-00002
00
DOC
E D S D
V E R I F I C A T I O N
C O N
T R O L N U M B E R
B y :
D a t e :
R E V I S I O N
C E R T I F I C A T I O N
T H I S I N D I C A T E S T H A T R E V . N O .________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R T I F I C A T I O N R E Q U I R E M E N T S , ,
B Y D R A W I N G C O M P L E T I O N C E R T I F I C A T E
( D C C ) N O . :__________________________
c. One set of the drawing index of the complete set of as-builtdrawings.
d. All CADD (Computer Aided Design) generated drawings on CDROM.
e. All electronic files shall be as builted by the Contractor.
6. Prior to issuance of Initial Acceptance of the work a number of drawingsmay be selected by Saudi Aramco for processing as noted above and theContractor shall be required to meet these requirements forreproducibility. This testing will be for the purpose of demonstrating thework meets minimum standards. Upon successful demonstration ofreproducibility Saudi Aramco will proceed to microfilm the full set ofdrawings, and a set of prints will be prepared from the microfilmedblowback. Any drawings which do not meet the clarity and legibilityrequirements will be redone by the Contractor at no added cost to SaudiAramco.
D. Record Specifications: During the progress of the Work maintain one copy of thespecifications, including addenda, change orders and similar modifications issuedin printed form during construction and mark-up variations in the actual workcomparison with the text of specifications and modifications, selection of options,and similar information on work where it is concealed or cannot otherwise bereadily discerned at a later date by direct observation. Note related recorddrawing information and product data where applicable.
E. Record shop Drawing Information: During the progress of the Work maintain theoriginal of each accepted shop drawing information submittal, other than shopdrawings, as defined in Section 01340. Mark-up variations in the actual work in
comparison with the submitted information. Include both variations from themanufacturer's instructions and recommendations for installation. Give particularattention to concealed products and portions of the work which cannot otherwisebe readily discerned at a later date by direct observation. Note related changeorders and mark-up of record drawings and specifications.
F. Record Miscellaneous Submittals: During the progress of the Work maintain therecord miscellaneous submittals as required by 1.2.
G. Record samples: During the progress of the work maintain the record samples asrequired by 1.2.
Part 2 - Products (Not Used)
Part 3 - Execution (Not Used)
- END OF SECTION -