01300 submittals

Upload: ulyjohnignacio

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 01300 SUBMITTALS

    1/11

    SECTION 01300

    SUBMITTALS

    1.01 GENERAL

    A. Designated Recipient Submittals:

    Make submissions as specified in this Section to the Engineer designated by theGOTEVT, and only by the Contractor as follows:

    B. Reviewers of Submittals:The Engineer will designate the reviewer of each submittal.

    C. Identification and Certification of Submittals:

    1. Identify each submittal with contract identification, the corporate names of theContractor, and the Subcontractor, supplier or manufacturer as may be applicable,and the date of submittal.

    2. Provide on each shop drawing and sample a clear space for the review stamp andcomments of reviewer and Contractor. Where a clear space cannot be provided,secure a tag to the submittal.

    3. Submittals shall bear the Contractor's stamp and written certification that they havebeen coordinated, checked for compliance with the Contract and approved by theContractor.

    D. Payment for Transmittal of Submittals:

    The Contractor shall be responsible for payment of the costs for transmittal ofsubmittals to the designated recipients, and the return of the submittals from thedesignated recipients to the Contractor.

    1.02 PROCEDURES FOR TRANSMITTAL OF SUBMITTALS

    A. Accompany submissions by a transmittal form provided by the Contractor in A4 sizeand in a format and with text suitable for the project, all as approved by the Engineer.

    B. Provide the following printed or typed information on each transmittal form:

    1. GOTEVT's Contract Identification and number.2. Name of Contractor, and when appropriate the name of the Subcontractor and/or

    supplier or manufacturer who has prepared the submittal.3. Name of Contractor's employee responsible for Contractor's review.4. Transmittal number which shall be consecutive throughout the works.5. Date of submission.6. Number each new submission item consecutively. Add a suffix (alphabetical or

    numerical but of consistent type throughout the work) to submission number foreach resubmission. Suffixes shall be consecutive.

    7. Number of submitted items and a description of the item.

    8. The Specifications Section number relevant to the submittal, with further referenceto the paragraph number of the section if required for precise identification. Do

    Vocational Training Center, Section 01300, Page 1 of 11

  • 7/30/2019 01300 SUBMITTALS

    2/11

    not make submission of items from more than one Specifications Section on thesame transmittal form.

    9. Drawing number, title and date of each shop drawing transmitted.10. Parts, areas, etc. of the Works to which samples pertain and date on which sample

    products are scheduled for incorporation in the Works.

    11 Contractor's remarks pertinent to the submittal including exceptions to ordeviations from the Contract and the reasons therefor.

    C. Provide spaces on the transmittal forms for information to be inserted as designatedfollowing:

    1. Date of submittal was received by designated recipient.2. Date submittal is returned by designated recipient to Contractor.3. Number of submitted items and a description of the item.4. Action taken.5. Reviewer's remarks including major deviations from the Contract or reasons

    for C ACTION if there are no notes on the submission itself.

    D. Submittals which, in the reviewer's opinion, are incomplete, contain errors, or have notbeen checked or have been only checked superficially will be returned for resubmissionwithout detailed review.

    F. Distribute finally reviewed shop drawings and samples to the installers and provideadditional submittals to the Engineer and reviewer as directed.

    1.03 SUBMITTAL REVIEW AND PROCEDURES FOR SUBSEQUENT ACTION

    A. Submissions will be returned by the Engineer to the Contractor stamped or marked bythe reviewer and indicating the appropriate action to be taken by the Contractor asfollows:

    1. A Action

    Fabrication, Manufacture, construction or purchasing may proceed, except in caseswhen validation of the submittal is required by jurisdictional authorities.

    When jurisdictional authority approval is required, Contractor may not proceedwith fabrication, manufacture, construction or purchasing until such time that

    formal approval by the jurisdictional authority has been obtained by theContractor.

    2. B Action

    Fabrication, manufacture, construction or purchasing may proceed subject to theincorporation of the reviewer's comments, except in cases when validation of thesubmittal is required by jurisdictional authorities.

    When jurisdictional authority approval is required, Contractor may not proceedwith fabrication, manufacture, construction or purchasing until such time that

    formal approval by the jurisdictional authority has been obtained by theContractor.

    Vocational Training Center, Section 01300, Page 2 of 11

  • 7/30/2019 01300 SUBMITTALS

    3/11

    If, for any reason, the Contractor cannot comply with the reviewer's comments,the Contractor shall make suitable revisions to the submittals and resubmit them asspecified under "C" Action submissions.

    Advise the Engineer as to compliance with the reviewer's comments and resubmitsubmittals evidencing such compliance within 14 calendar days of receiving themin order for them to be stamped by the Engineer with an "A" Action. "B" Actionsubmittals shall have a 14 days validity for use on site.

    The Contractor shall only utilize "A" or non-dated "B" Action submittals in theconstruction of the Works.

    3. C Action:

    The submission does not comply with Contract requirements, and fabrication,

    manufacture and construction shall not proceed. The Contractor shall makerevisions and resubmit. Submissions with C Action stamp will not be permitted onthe site and shall not be used for the Works.

    B. Failure of the Contractor to process submittals for review shall not relieve thecontractor of his responsibilities under the Contract.

    C. Do not proceed with work dependent on submittals until the submittals have beenverified by the Contractor, reviewed, and marked with the appropriate action. Makinggood work which has proceeded in error because of non-compliance with theserequirements shall be at the Contractor's expense. Review of submittals shall not

    relieve the Contractor of his responsibility for execution of the Works in accordancewith Contract Documents.

    D. The Contractor shall not be relieved of responsibility for deviations from the Contractor errors of any kind in the submittals or from the necessity of furnishing workrequired by the Contract which may have been omitted from the submittals markedwith the appropriate Action. The review of individual items in submittals shall not beconstrued as a review of the complete assembly in which it functions.

    E. No authorization of an increase in Contract Sum or time shall be implied by commentsmarked on submittals or submittal transmittals by the reviewer.

    F. Review of submittals shall not absolve the Contractor from the responsibility ofcorrectly locating all items in the Works. The Contractor shall pay all costs forrevisions to work caused by improper location in the Works.

    G. Approval of Substitutions, Alternatives and Deviations:Whenever and wherever the Contractor proposes to make substitutions to thespecified construction method or process, or proposes the use of non-listedmanufacturers, products or to deviate from the materials specified, the Contractormust make a full submission as required in the Contract Documents. The Engineershall evaluate such proposal as provided for in this Section and forward his

    recommendation to the GOTEVT for his consideration. The contractor is advised that

    Vocational Training Center, Section 01300, Page 3 of 11

  • 7/30/2019 01300 SUBMITTALS

    4/11

    only the GOTEVT has the final authority to approve or reject the proposedsubstitutions, alternatives and/or deviations.

    The GOTEVT shall have fourteen (14) calendar days following submittal to issue hisapproval in writing which shall be in addition to the submittal review schedule noted in

    Section 01300 paragraph 1.04

    H. The Contractor, not the GOTEVT, shall be responsible for extra costs for alterationsto the Works caused by discrepancies, errors or omissions in submissions irrespectiveof whether the submissions have been reviewed or not.

    1.04 SCHEDULE OF SUBMISSIONS

    A. Make submissions in a sequence in accordance with the needs of the constructionschedule and review requirements so that progress of the Works is not impeded.

    B. Prepare and submit to the Engineer for his review a preliminary schedule of allspecified and proposed submissions within the number of days stipulated in theContract from notice to proceed.

    C. Include on schedule a brief description of each submittal for shop, composite andinsert layout drawings, indicate proposed drawing title, number and scale.

    D. Indicate on schedule which Division of the Specifications governs the work included inthe submission.

    E. Schedule shall allow for retention of each submittal as follows in this anticipated

    sequence:

    1. Five working days (7 calendar days) in Engineer's office.2. Fifteen working days (21 calendar days) in Reviewer's office.3. Five working days (7 calendar days) in Engineer's office:

    a total of 25 working days (35 calendar days). In all cases the Contractor shall ensurethat sufficient time is allowed for the Engineer Review. Transmission time forsubmittal is not included in aforementioned period.

    The GOTEVT shall have fourteen (14) calendar days following submission to issue his

    approval in writing which shall be in addition to the submittal review schedule.

    F. Indicate on schedule, time allowed for transmittal of submittals for review, and forcorrections required by reviewer's possible requests for re-submissions.

    G. Should the Engineer disagree with the submittal schedule dated, he will establish otherdates necessary to maintain progress of the Works that he considers reasonable. TheContractor comply with the submittal schedule as may be amended by the Engineerand as the Engineer may further amend as construction progresses.

    H. An extension of time will not be allowed because the Contractor has failed to have

    submissions and re-submissions made in sufficient time to allow for processing andreview.

    Vocational Training Center, Section 01300, Page 4 of 11

  • 7/30/2019 01300 SUBMITTALS

    5/11

    1.05 RESUBMISSIONS

    A. Procedures for re-submissions accompanied by transmittal forms shall be made asspecified for initial submissions except that the submission and transmittal numbers and

    dates will differ.

    B. Indicate on submittals the revisions requested by the reviewer and any precedingrevisions with resubmission dates that may have been made.

    C. Do not include an initial submission on a transmittal form for a resubmission.

    D. Do not include a group of re-submissions on the same transmittal form.

    E. Re-submissions shall be repeated by the Contractor in a timely fashion to the approvalof the Engineer until the Engineer has indicated A Action on the submittals.

    1.06 CONSTRUCTION SCHEDULES

    A. Submit proposed construction schedule in a format approved by the GOTEVT andwithin the time stipulated in the Contract Documents.

    B. Resubmit construction schedule to incorporate revisions that the Engineer mayconsider desirable and reasonable.

    C. As construction progresses, submit three copies of up-dated construction scheduleseach month to Engineer. Up-dated schedules shall include further revisions that the

    Engineer may consider desirable and reasonable.

    1.07 SHOP DRAWINGS

    A. Submit shop drawings for which submission is required in other Sections of theSpecifications. Include with final shop drawings detailed information, templates andinstallation instructions required for incorporation and connection of the workconcerned.

    B. In addition to shop drawings specified in other Sections, submit shop drawingsrequired by jurisdictional authorities in accordance with their requirements.

    C. The Contractor shall check and verify dimensions and conditions at the site as requiredfor shop drawing preparation and when requested by the Engineer, Subcontractors orother contractors for their preparation of shop drawings. Such information shall be

    provided promptly to prevent delay in the Works and shall be submitted to theEngineer as a matter of record.

    D. The Contractor shall review shop drawings prior to submission to the Engineer, and heshall by stamp and signature so indicate that his review has been performed. Inchecking each submission, the contractor shall annotate the shop drawings withmatters relative to the Works. When checking shop drawings, the Contractor shall

    verify all dimensions, quantities and field conditions.

    Vocational Training Center, Section 01300, Page 5 of 11

  • 7/30/2019 01300 SUBMITTALS

    6/11

    E. Indicate on each submission any deviations from the Contract Documents that havebeen incorporated in the shop drawings. The Contractor shall be responsible forchanges made from the Drawings and Specifications which are not indicated orotherwise communicated in writing with the submission.

    F. On each shop drawing, the Contractor shall indicate on the aforementioned stampunder his signature that the drawing conforms to the requirements of the ContractDocuments.

    G. Incorporate only dimensional system utilized for Drawings, except where substitutesare otherwise approved. Make soft conversions from imperial system to metric, orvice versa, when required for incorporation of units of one dimensional system intoconstruction of the other.

    H. Number shop drawings for each Section of the Specifications consecutively, and retainthe numbering system for submission of all revisions.

    I. Produce shop drawings in negative form on clear reproducible 0.075 mm thick stablepolyester film using a high standard of draughting skills.

    Format, titles, drawing number, scales and extent of details shall be approved by theEngineer.

    J. Information provided on shop drawings shall include but shall not be limited to the

    following:

    1. Proposed methods of construction, manufacture and/or fabrication.

    2. Fabrication and erection dimensions.3. Erection Layout.4. Installation dimensions5. Provisions for allowable construction tolerances and deflections

    provided for creep and live loading.6. Details to indicate construction arrangements of the parts and their

    connections, and interconnections with other work.7. Location and type of anchors, and exposed fastenings.8. Materials and finishes.9. Physical dimensions of materials including thickness and gauges.10. Schedule for reinforcement bending, equipment and other items.

    11. Suppliers' catalogues, brochures, data sheets, standard drawings,specifications, and other descriptive data.12. Diagrams of systems, equipment and controls.13. Piping, duct and conduit systems.14. Descriptive names of equipment.15. Mechanical and electrical characteristics when applicable.16. Relationships and installation details of mechanical and electrical

    equipment to the spaces in which they will be installed.17. Information to verify that superimposed loads will not affect

    function, appearance, and safety of the work detailed as well as of interconnectedwork.

    18. Assumed design loading, and dimensions and material specifications for load-bearing members.

    Vocational Training Center, Section 01300, Page 6 of 11

  • 7/30/2019 01300 SUBMITTALS

    7/11

    19. Dimensions and dimensioned locations of proposed chases, sleeves, cuts, and holesin structural members.

    K. Submit one reproducible shop drawing and one print copy to the Engineer who willperform a preliminary review, acknowledge such review, and return reproducible to

    the Contractor for the Contractors transmittal to the reviewer. The reviewer will markup the reproducible with his comments, make a print for his records, and return thereproducible to the Engineer. The Engineer will return the reviewed reproducible tothe Contractor who shall make a print and submit to the GOTEVT for record

    purposes.

    L. Six copies of brochures, engineering data sheets, catalogue cuts and standard diagramsmay be substituted for shop drawings where applicable. Provide additional copies ifrequested by the Engineer.

    M. Do not add new details or information to shop drawings after they have been finally

    reviewed, except when specific approval is solicited and is given. Follow submissionprocedures as specified for drawings, but presentation may be made in letter form.

    N. Fabricate work exactly as shown on shop drawings. If shop practice dictatesrevisions, revise drawings and resubmit.

    O. File one reproducible copy of each finally revised and corrected shop drawing at site.

    P. Shop Drawing Review:

    1. Shop drawing review is for the sole purpose of ascertaining general

    conformance with the design concept. This review shall not mean that reviewerand Engineer warrant or represent that the information contained on the shopdrawings is either accurate or complete, responsibility for which shall remain withthe Contractor submitting same, and such review shall not relieve the Contractorof his responsibility for errors or omissions in the shop drawings or of hisresponsibility for meeting design, details and all other requirements of the ContractDocuments.

    2. The Contractor is responsible for confirmation and co-relation ofdimensions at the job site, for information that pertains solely to fabrication

    processes or to techniques of construction and installation, and for totalcoordination of the Works.

    3. The Contractor shall not be awarded any extra time or compensation formodifications required to design drawings as a result of coordination and othermodifications required during the course of the work.

    1.08 COORDINATION AND COMPOSITE SHOP DRAWINGS

    A. The Contractor shall coordinate the shop drawings prepared by one section with therequirements of other sections before shop drawings are submitted for review toensure the proper and complete installation of all parts of the works.

    B. Prepare interference and equipment placing drawings to ensure that all components

    will be properly accommodated within the space provided.

    Vocational Training Center, Section 01300, Page 7 of 11

  • 7/30/2019 01300 SUBMITTALS

    8/11

    C. Prepare drawings to indicate coordination and methods of installation of a system withother systems where their relationship is critical. Ensure that all details of equipment,apparatus, and connections are coordinated.

    D. Ensure that clearance required by jurisdictional authorities and for proper maintenance

    are indicated on drawings.

    E. In addition to specified shop drawings, the Contractor shall prepare composite shopdrawings showing coordination of the architectural, structural, mechanical andelectrical work to ensure its proper, integrated and complete installation. Preparecomposite shop drawings to show dimensions, architectural and structural details,ductwork, piping, conduit, equipment, fixtures and other installations to ensureadequate clearances for installation and servicing. Prepare composite shop drawingsat a scale consistent with requirements and clarity but in no instance at less than 1:100scale.

    F. Review composite shop drawings with all parties affected by the drawings at a meetingarranged by the Contractor. Each Section shall indicate the extent of his work on thecomposite shop drawing and shall indicate his approval by signing the reproducible ofthe drawing. The Contractor shall distribute approved composite shop drawings tothe Engineer and to each concerned party and other contractors for their information.

    G. Submit coordination and composite shop drawings to the Engineer for review only incases where conflicts affect the intent of the Contract Documents. Procedures andconditions specified following for shop drawings shall also apply to coordination andcomposite shop drawings.

    H. Submit shop drawings for each Section following distribution of composite shopdrawings.

    I. Distribute coordination and composite shop drawings well in advance of fabricationand installation of work affected. Place no orders for affected equipment withoutsubmission of coordination Drawings to the supplier.

    1.09 INSERT AND SLEEVE LOCATION DRAWINGS

    A. Submit insert and sleeve location drawings for the Engineer's information only whereinserts and sleeves are required for installation of work. The Engineer may

    additionally request insert and sleeve location drawings for his review.

    B. Indicate on location drawings the location and size of inserts, sleeves, anchor bolts,openings and miscellaneous items to be incorporated in the Works.

    C. Show type, size, load capacity, and working load which will be imposed on each insertand anchor bolt. Provide a capacity: working load safety factor ratio of 5:1 or better.

    D. Submit insert and sleeve location drawings well in advance of construction of workincorporating the applicable built-in work.

    E. The Contractor shall be responsible for final coordination of all insert and sleevelocations required to complete the Works.

    Vocational Training Center, Section 01300, Page 8 of 11

  • 7/30/2019 01300 SUBMITTALS

    9/11

    1.10 REPRODUCTION OF SUBMITTED DRAWINGS

    A. The Contractor shall include in the Contract the cost of reproducing shop drawings,and coordination and composite shop drawings required by submission procedures.

    1.11 SAMPLES

    A. Submit samples for which submission requirement is specified in other Sections of theSpecifications.

    B. For each submission, unless otherwise approved, submit six samples of adequate sizeto represent the material in its intended use in the works.

    C. The Engineer will receive samples, perform a preliminary review, acknowledge suchreview, and return samples to the Contractor for his transmittal to the reviewer. The

    Engineer will also transmit samples to GOTEVT if necessary. The reviewer willreview and communicate his approval or disapproval, as the case may be, to theGOTEVTs. The Engineer will advise the Contractor accordingly.

    D. Submit all interior finish samples at the same time to facilitate coordinated review ofcolors and finishes. Review will not commence until all samples are received.

    E. Where both sample and shop drawing review is required at the same time, one will notbe reviewed without the receipt of the other.

    F. Store duplicates of all submitted samples at the site.

    G. Samples shall represent material composition, color, texture, natural markings, andother physical qualities. Submit an extreme range of samples when the degree ofmarking of color cannot be represented by a single sample.

    H. Submit samples in labeled containers wherever possible.

    I. Label samples with Contract identification and number, Contractor, Subcontractor,and date.

    J. Approved samples shall serve as a model against which the products incorporated in

    the Works shall be judged.

    K. Each product incorporated in works shall be precisely the same in all details as theapproved sample.

    L. Should any change of material, color, texture, finish, dimensions, performance,function, operation, construction, joining, fastening, fabrication techniques, servicecharacteristics, and other qualities be made to a product after approval has been given,submit for approval of the revised characteristics in writing and resubmit samples ofthe product for approval if requested.

    1.12 SUBCONTRACTORS AND MANUFACTURERS INFORMATION

    Vocational Training Center, Section 01300, Page 9 of 11

  • 7/30/2019 01300 SUBMITTALS

    10/11

    A. Submit list of Subcontractors for the works to include.

    1. Legal corporate name of the Subcontractor with head officeaddress, and telephone and fax or telex numbers.

    2. Legal corporate name of the Subcontractors Saudi Arabian

    representative with address, and telephone and fax or telex numbers.3. Description of Subcontractors work.

    B. Submit a list of products to be supplied for the works to include.

    1. Type and description of product.2. Trade name of product.3. Origin of product.4. Standard to which product conforms.5. Manufacturer of product with head office address, and telephone and

    fax or telex numbers.

    6. Saudi Arabian representative of manufacturer with address, andtelephone and fax or telex numbers.

    C. Submit manufacturers printed instructions, specifications, recommendations andcomplete information concerning proprietary products incorporated in the works.

    1.13 AFFIDAVITS

    A. Submit affidavits which may be required when a product substitution is proposed, orwhen proof of compliance to reference standards is made, or as may be specified inother sections of the Specifications.

    B. Affidavits shall verify that products and/or methods meet requirements specified in theContract documents, and shall include test reports of approved testing laboratories tovalidate claims contained in affidavit.

    C. Submit affidavits in duplicate and with notarized signature by a responsible officer ofthe certifying company.

    1.14 QUALITY CONTROL REPORTS

    A. Submission requirements for quality control reports is specified in Section 01400.

    1.15 CONSTRUCTION PROGRESS RECORDS

    A. Video Record:

    Video Photography, recorded on VHS format, shall show the general extent of theworks, form both interior and exterior views. The video monthly record shall includecoverage of each and every activity that is requested by the Engineer. Acomprehensive commentary shall accompany the visual display.

    B. Photographic Record

    Vocational Training Center, Section 01300, Page 10 of 11

  • 7/30/2019 01300 SUBMITTALS

    11/11

    1. Work shall include progress photographs of construction taken form two interiorand three exterior viewpoints each mount made by a professional photographer.Take on photograph from each viewpoint.

    2. Photographs shall show general extent of the works by both exterior and interiorviews. Each viewpoint will be selected, and the number of monthly repetitive

    photographs taken from exactly the same viewpoint decided by the Engineer.3. Submit eight 200 mm x 254 mm glossy color prints of each photograph Engineer

    at the first of each month.4. Title each photograph at the bottom so that nothing pertinent is blocked out.

    Include on title: project name, Contractors name, direction of view, and datewhen taken.

    END OF SECTION

    Vocational Training Center, Section 01300, Page 11 of 11