  • Pearl GTL Project

    LINDE ENGINEERING

    Contractor Project No : 5887 Shell Project No: HP-3000-QAT

    Project Document Number: T- 4.234.071 Project Rev.: B Page 2 of 15

    Purchase Order Number: 2MH127

    N/A Tag/Item Number(s):

    ASU Unit(s):

    Z PCWBS:

  • QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION

    F B 28.01.2008 Ready For Construction SB UA/MC ZG RFC

    E A 13.11.2007 Company Comments Incorporated IO MC ZG CCI

    D O 10.09.2007 Issued for Company Comments IO MC ZG ICC

    C O 06.09.2007 Issued for Company Comments IO MC ZG ICC

    B1 20.07.2007 Issued for Review IO MC ZG IFR

    A1 Issued for Internal Review IO MC ZG IIR

    Approved By

    GAMA Project Rev Rev. Date Description

    Prepared By

    Checked By Status

    No. No. ORIGINATOR

    Document Title:

    LINDENGINEERING AG METHOD STATEMENT FOR DISPOSAL OF

    EXCAVATED MATERIAL Document No.

    GAM MTS CIV GTL 005 F LOC470

    Gama Qatar Co. W. L. L. Rev. Org. Doc. Seq. Disc.

    Code Geogr. Area

    Vendor Code No Code Type No Project Document Number: T-4.234.071 Rev No: B

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 4 of 15

    QQQ AAA TTT AAA RRR

    TABLE OF CONTENTS

    1. PURPOSE _____________________________________________________________________5 2. SCOPE ________________________________________________________________________5 3. HSSE _________________________________________________________________________5 4. REFERENCES _________________________________________________________________6 5. DEFINITIONS _________________________________________________________________6 6. RESOURCES___________________________________________________________________7

    6.1. Equipment ________________________________________________________________________7 6.2. Manpower ________________________________________________________________________7 6.3. Responsibility _____________________________________________________________________7

    7. METHOD OF EXECUTION ______________________________________________________8 7.1. Pre-Commencement Works__________________________________________________________8 7.2. Loading & Transportation __________________________________________________________8 7.3. Dumping & Grading _______________________________________________________________9 7.4. Stockpiling of Usable Material _______________________________________________________9

    8. QUALITY ASSURANCE__________________________________________________________9 9. ATTACHMENTS_______________________________________________________________10

    9.1. Job Safety Analysis________________________________________________________________10 9.2. Dumping Area____________________________________________________________________10

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 5 of 15

    QQQ AAA TTT AAA RRR

    1. PURPOSE

    The purpose of this method statement is to clarify the disposal of excavated material works at the Air Separator Units Construction for Shell GTL (Pearl) Project by Gama Qatar located inside the Ras Laffan Industrial City in Qatar.

    This document describes the methods to be used for disposal of excavated material to the location designated by the Contractor and approved by the Company and RLIC.

    Also some of the excavated material; that will be used for backfilling later, shall be transported to an area which is located in the site for stockpiling. This stockpiling area will be designated by the Contractor and approved by the Company and RLIC.

    The disposal area is located in the premises of Ras Laffan Port; but maybe changed to another location if requested by RLIC, the Company and/or the Contractor.

    The material to be disposed shall probably consist of Natural Soil and excavated Rock material. Although it is planned to store excavated Natural Soil (the definitions are as for material types as described in T-4.234.070 Method Statement for Excavation) at site for future use, some portion of the same material may be dumped to the designated disposal area as required.

    2. SCOPE

    This method statement covers the disposal of excess usable and unusable soils after segregation of excavated materials. However, the method for obtaining usable fill material from the excavated soil is beyond the scope covered in this document.

    3. HSSE

    All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan Industrial City and international standards/codes, and Company and Contractor requirements and instructions.

    All personnel will go through Gama, Linde and Company Safety Induction courses as well as other trainings as identified by their supervisor. Please see Document Number GTL-GM-001-A-5635 for details.

    A Job Safety Analysis (JSA) specific for this work including a Risk Assessment, is prepared as per Gama procedure GTL-GM-001-A-5626 and is attached herein. Such JSA addresses the hazards associated with each task within the scope of this Method Statement and introduces the controls that will be implemented to reduce the associated risks to acceptable levels. The JSA will be used by the Site Supervisor as the basis of his TSTI / TSTO and Toolbox Talks.

    All personnel will have PPE required for their specific tasks in addition to the minimum PPE (coveralls, safety goggles, safety shoes, high-visibility vests, gloves) at site at all times as required.

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 6 of 15

    QQQ AAA TTT AAA RRR

    4. REFERENCES

    Qatar Construction Standard T.4-095.955 Project HSSE Program Overall T.4-095.303 Project HSSE Construction Plan T.4-129.849 Permit to Work Procedure T-13.376.490 Project Specific Specification for Site Preparation DEP 34.11.00.11 Site Preparation and Earthworks including Tank Foundations and Tank Farms

    T-13.376.352 Amendments and/or Supplements to Site Preparation and Earthworks including Tank Foundations and Tank Farms GTL-GM-001-A-5606 Traffic Safety Plans T-4.234.144 QC Documents for Site Preparation and Earthworks

    5. DEFINITIONS

    Company : QSGTL and/or its PMC (JK) Contractor : Linde Engineering AG Subcontractor or Gama : Gama Qatar Co. W.L.L. QCP : Quality Control Procedure QCR : Quality Control Record ITP : Inspection and Test Plan QA/QC : Quality Assurance / Quality Control RLIC or RLC : Ras Laffan Industrial City

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 7 of 15

    QQQ AAA TTT AAA RRR

    6. RESOURCES

    6.1. EQUIPMENT

    The below-listed equipment will be used as and when required.

    Backhoe Excavators Wheel Loader Dozer

    Water Tanker Dump Trucks Grader

    All equipment shall be inspected and approved by the Contractor and/or the Company.

    6.2. MANPOWER Site Engineer Foreman HSSE Officer HSSE personnel

    Banksmen Operators Drivers Flagmen

    All personnel shall be inducted and trained before attempting work on site and have valid certificates and/or licenses.

    6.3. RESPONSIBILITY

    6.3.1. Site Manager

    The Site Manager will provide inputs to the project execution plan to ensure that proper strategies & philosophy are addressed.

    6.3.2. Civil Works Manager

    The Civil Works Manager is responsible for the overall management of the project construction team to ensure that safe and effective operations are conducted and properly documented.

    6.3.3. QA/QC Department

    QA/QC Department shall ensure quality of the works and compliance with project requirements during all phases of the works.

    6.3.4. HSSE Manager

    Responsible for the safety control works for all construction sites under the jurisdiction of his department, he will inform the site of various kinds of safety policies, plans, etc. he will also be an adviser and approver of the JSA.

    6.3.5. Site Engineer / Supervisor

    The Site Engineer / Supervisor will perform the necessary studies and calculations and will supervise the work. He will ensure that the work is being carried out effectively in accordance with the established Method Statements and JSA.

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 8 of 15

    QQQ AAA TTT AAA RRR

    7. METHOD OF EXECUTION

    All activity shall be closely monitored and supervised at the work site, road operations and the final dumping areas. Dumping areas shall be frequently inspected by supervision to ensure areas are free of road hazards, soft spots, etc. that could cause the trucks to tip over.

    7.1. PRE-COMMENCEMENT WORKS

    Before each activity the following must be taken into account.

    7.1.1. Work Permit

    Prior to implementing an operation, all necessary permits will be obtained.

    7.1.2. Traffic Management Plan

    Works shall not interrupt any kind of vehicle traffic on any emergency access road. If to ensure smooth execution of the works in an area a need for a temporary closure has been deemed necessary a road impact notice will be provided. However, no such diversion shall take place without prior written consent of the Contractor or the Company.

    In order not to encourage the drivers commit traffic violations, they shall be paid according to the days they have worked, not the trips they completed.

    Traffic rules of the State of Qatar shall apply to the drivers outside the boundaries of Ras Laffan Industrial City; and RLIC rules and regulations shall apply within RLIC premises. In site, the speed limit for trucks shall be 30 km/h, and the use of seatbelts shall be mandatory at all times.

    All rules and regulations of RLIC shall be strictly followed.

    All loads shall be effectively covered to cover to keep material from spilling on to the roads. Roads shall be swept clean of all soil deposits that are accumulated or deposited on to the road.

    7.2. LOADING & TRANSPORTATION

    After excavation, excavated Rock or Soil shall be loaded into dump trucks by Loaders or Excavators. The material shall then be transported to the disposal area where sufficient number of banksmen shall control the flow of traffic. The trucks shall keep their dumpers covered by sheets while transporting material. The drivers shall leave their trucks while the truck is being loaded. In order to minimize fall exposure, the canvas sheets covering the tippers shall be pulled into position by ropes from the ground.

    For the storage of material excavated from Phase I, the storage location on the South-Eastern side of Phase II Area (as shown in Attachment 2) will be used. Should the area prove not sufficient, it can safely be extended since there will be no activities in the area until 2008. For the disposal and storage of material excavated from Phase II another area should be jointly determined.

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 9 of 15

    QQQ AAA TTT AAA RRR

    7.3. DUMPING & GRADING

    The material shall be dumped to the dumping area within the Ras Laffan Port (as per RLIC regulations and requirements) in loose layers of 70 ~ 100 cm thickness, depending on the type of the soil being disposed of. These will be graded by graders and/or Dozers to the level. One Dozer shall be kept permanently at the disposal area during the works. One banksman shall accompany the dumping and grading activities in the Port area.

    7.3.1. Wet Material

    Where wet material is to be excavated and stored, a dewatering system will be put in place prior to the works. Wet material shall be let to dry on this area. Storage of excavated material will be done as far away as possible from the excavation line and the distance will not be less than 1.5 times the excavation depth in any circumstance. Such material shall only be hauled after being dried in order to prevent any spill on the way to the dumping area.

    7.4. STOCKPILING OF USABLE MATERIAL

    Since excavated soil will be used as a filling material in the later phases of the project, it shall be stocked at a location designated by the Contractor or the Company. The method for obtaining usable material from the excavated material will be carried our as per the Method Statement of Processing of Excavated material to Obtain Usable Fill Material (T-4.234.072).

    8. QUALITY ASSURANCE

    A Quality Assurance System shall be operated conforming to related standards. Controls and checks shall be established and documented through T-4.234.144.

  • Doc. Title : GAM-MTS-CIV-GTL-005 Rev. F Method Statement for Disposal of Excavated Material

    Date : 28.01.2008

    T-4.234.071 Rev. B Page 10 of 15

    QQQ AAA TTT AAA RRR

    9. ATTACHMENTS

    9.1. JOB SAFETY ANALYSIS

    9.2. DUMPING AREA

  • JSA For: T-4.234.071

    Normal Approvals: Name DateJSA by:

    Job Supervisor:

    Name DateDiscipline Superindent (Linde)

    HSSE Representative (Linde)

    2.Permit To Work.

    LINDE EMERGENCY TELEPHONE NO. HSSE MANAGER: Pearl HOT LINE :

    Approval required for hazardous work detailed in the Linde Work Permit Procedure.Changing conditions and emergency proceduresStop work. Switch off equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing employees are reported to Linde HSSE Dept. When all clear is given check with Linde HSSE before returning to work.

    1. The following Personal Protective Equipment shall be worn: Approved coveralls, safety googles, safety helmet, safety shoes and gloves. Signature

    OTHERS (List Below):

    Additional Approvals (Determined by Job Supervisor in correlation with Linde HSSE Manager).

    Department/Section doing JSA: HSSE & Construction JSA Members:Job Performers:

    General job requirements / Common Personal Protective Equipment.

    Signature

    JOB SAFETY ANALYSIS FORM

    Page No: 1 of 4 Job being analysed: Disposal of Excavated Material

    NEW REVISED

    QQQ AAA TTT AAA RRR

  • RISKRANK

    1.1 Mis-use or lack of knowledge to use the equipment.

    1.1.1 A well experienced, licensed, trained and qualified by third party operator will be provided.

    1.1.2 Competency check.1.2 Equipment breakdown. 1.2.1 Good condition, third party inspected

    equipment only be used.1.2.1.11.2.1.2

    Preventive maintenance is in place.Vehicle spot checks.

    1.2.2 This equipment will be check daily to maintain its good condition.

    1.2.3 Do not use any equipment having red tag.

    1.3 1.3.1 Ensure sufficient numbers of competent banksmen will be provided in the working area.

    1.3.2 Area of loading will barricaded to un-authorized person.

    1.3.3 A competent and experience supervision will be provided.

    1.4 1.4.1 Experienced & licensed driver will be allowed to drive of any vehicle.

    1.4.2 All traffic rules and regulation will be followed such as speed limits, use of seat belts.

    1.4.3 Sufficient trained banksmen and flagmen will be provided.

    1.4.4 A competent and experience supervision will be provided.

    1.4.5 Job safety analysis and other precautions as required should be implemented and monitored.

    1.4.1.5

    1.4.6 Area will be barricaded and signs will be posted.

    1.5 Heat stress. 1.5.1 Cold drinking water and sunshades will be provided. Additional precaution will be informed through daily TBT / TSTI.

    1.5.2 Proper implementation of Heat Stress Program. Drink plenty of water.

    1.5.3 Supervisor shall monitor his work force closely for early signs of heat exposure, i.e. heat cramps, heat exhaustion etc.

    1.5.4 Locate water close to work activities.

    1B

    1 Loading of Excavated Material.

    MED

    B

    C

    MED3D

    LOW

    Tipping of materials.

    Employees to be trained on heat related illnessesMonitor the Heat Stress Flags; incase of a black flag, stop all work.

    Audible Reverse alrams should be installed on all vehicles and equipment

    3

    1.4.1.11.4.1.21.4.1.3

    1.4.1.4

    Driver competency check.Stop work if visibility is impaired.All drivers shall have valid Qatari driving licenses, all operators shall have 3rd party certifications.Safe access shall be maintained at site for vehicles and equipment.

    1.5.1.1

    1.5.1.2

    Collision to other vehicle and personnel and driving at dusty environment.

    LOW1B

    C

    LOW2B

    LOW2B

    LOW

    B 2 LOW

    C

    RP CITEM ACTIVITY CPCONSEQUENCESHAZARDS / POTENTIAL ADDITIONAL

    SCOPE : DISPOSAL OF EXCAVATED MATERIAL

    Residual RiskInitial Risk

    JOB SAFETY ANALYSIS / RISK ASSESSMENTFOR T-4.234.071

    CONTROLSMAIN

    CONTROLS

    3 MED

    1.3.1.11.3.1.2

    Level surface.Do not move vehicle while dump box is up.

    LOW

    2

    2

    QQQ AAA TTT AAA RRR

  • RISKRANK

    RP CITEM ACTIVITY CPCONSEQUENCESHAZARDS / POTENTIAL ADDITIONAL

    SCOPE : DISPOSAL OF EXCAVATED MATERIAL

    Residual RiskInitial Risk

    JOB SAFETY ANALYSIS / RISK ASSESSMENTFOR T-4.234.071

    CONTROLSMAIN

    CONTROLS

    QQQ AAA TTT AAA RRR

    2.1 Equipment breakdown 2.1.1 Good condition, inspected equipment only to be used. This equipment will be check daily to maintain its good condition. Do not use any equipment having red tag.

    2.1.1.1 Vehicle spot checks.

    2.1.2 Preventive maintenance is in place.

    2.2.1 Experience & licenced driver will be allowed to drive of any vehicle and the driver should be trained of defensive driving training.

    2.2.2 All traffic rules and regulation will be followed such as speed limits, use of seat belts.

    2.2.3 Ensure sufficient numbers of competent banksmen will be provided in the working area.

    2.2.4 A competent and experience supervision will be provided.

    2.2.5 Job safety analysis and other precaution should be implemented and monitored.

    2.2.6 Area will be barricaded and signs will be posted.

    2.2.7 Approved transportation route & re-routing map for vehicle traffic in accordance with RLIC, Company & Contractor rules.

    2.3 Falling of backfilling materials.

    2.3.1 Ensure precise cover for the dumptrucks will be provided and properly secure.

    2.3.2 No overloading of materials on the trucks.

    B 1

    1

    2.2.1.12.2.1.22.2.1.32.2.1.4

    2.2.1.5

    Driver competency check.Defensive driving course.Stop work if visibility is impaired.All drivers shall have valid Qatari driving licenses, all operators shall have 3rd party certifications.Safe access shall be maintained at site for vehicles and equipment.

    B

    LOW

    3

    B

    LOW

    LOW

    2 Transportation to Disposal Site.

    Collision to other vehicle and personnel while travelling and driving conditions at dusty environment

    2.2

    MED3D

    LOW2B

    LOW2C

  • RISKRANK

    RP CITEM ACTIVITY CPCONSEQUENCESHAZARDS / POTENTIAL ADDITIONAL

    SCOPE : DISPOSAL OF EXCAVATED MATERIAL

    Residual RiskInitial Risk

    JOB SAFETY ANALYSIS / RISK ASSESSMENTFOR T-4.234.071

    CONTROLSMAIN

    CONTROLS

    QQQ AAA TTT AAA RRR

    3.1 3.1.1 Driver will ensure soil stability and banksmen will be provided.

    3.1.2 Area to be backfilled will be inspected and proper route will be designated.

    3.1.3 A competent and experienced supervision will be provided.

    3.2 Equipment breakdown. 3.2.1 Good condition, inspected equipment only be used.

    3.2.1.13.2.1.2

    Preventive maintenance is in place.Vehicle spot checks.

    3.2.2 This equipment will be check daily to maintain its good condition.

    3.2.3 Do not use any equipment having with red tag.

    3.3 3.3.1 Only experienced & licenced driver will be allowed to drive any vehicle.

    3.3.2 All traffic rules and regulation will be followed such as speed limits, use of seat belts.

    3.3.3 Ensure sufficient numbers of competent banksmen will be provided in the working area.

    3.3.4 A competent and experience supervision will be provided.

    3.3.5 Job safety analysis and other precaution should be implemented and monitored.

    3.3.6 Area will be barricaded and signs will be posted.

    3.4 Dust hazard. 3.4.1 Dustmask will be provided to each personnel and continuous monitoring for proper usage.

    3.4.1.1 Spraying of water around the dusty area.

    3.4.2 Operators should avoid overloading of topsoil and ensure tarpaulin cover are properly in place.

    Unloading & Disposal.

    3

    LOW1

    LOW1B

    2 LOW

    2 LOW

    LOW3B

    LOW2C

    Driver competency check.Defensive driving course.Stop work if visibility is impaired.All drivers shall have valid Qatari driving licenses, all operators shall have 3rd party certifications.Safe access shall be maintained at site for vehicles and equipment.Audible reversing alarms will be installed on all equipment and vehicles

    B

    B

    B

    Dumping will be done on a level ground surface.Do not run truck while dump box is in dumping position.

    3.3.1.13.3.1.23.3.1.33.3.1.4

    3.3.1.5

    3.3.1.6

    3.1.1.1

    3.1.1.2MED

    Collision to other vehicle and personnel and driving at dusty environment.

    D 3 MED

    Dump trucks tumble down while dumping.

    C 3

  • 70-m

    50-m

    005 - Disposal Rev. E 28.01.08.pdf

    GAM-MTS-CIV-GTL-005 Disposal of Excavated Material Rev. E.pdf