0 npsi-felisa solar fs write-up
TRANSCRIPT
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
1/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
1 |
P a g e
Executive Summary
This Facilities Study is conducted for the 50 MW Negros PH Solar Inc.’s Solar Power Project in
Brgy. Felisa, Mansilingan, Bacolod City, Negros Occidental. This study aims to identify the
necessary connection equipment to connect the proposed power plant to the grid. The connection
configuration presented in this study is based on the connection requirement of NGCP as
documented in the System Impact Study for the project.
The connection arrangement is compliant with the requirements of the Philippine Grid Code and
other applicable regulatory issuances. The proposed project will connect to the grid through a 69
kV transmission facility approximately 1 km in length. The connection will be a ”tapped”
connection along the existing 69 kV transmission line owned by NGCP. Power generated from
the proposed power plant will be delivered to CENECO, NOCECO and to the grid through NGCP’s
Bacolod Substation.
After a series of discussion, it was agreed with the local NGCP that no switching substation will
be installed at the tapping point. Aerial disconnect switch will be installed next to the tapping point
and another one on the tapping pole isolating the CENECO/NONECO line.
In compliance with the requirement of ERC Resolution 16 series of 2011, the power plant’s
disconnection means will be the existing feeder breaker and corresponding disconnect switchesat Bacolod Substation. Included in this study are the telecommunication and protection equipment
needed in by the power plant. From the results of the System Impact Study, no other
improvements or additions will be required for the transmission network beyond the connection
point.
The following are the results of the FS:
1. No issue on the proposed connection scheme as this is to be owned by the developer
following provisions of the Section 9 of the Electric Power Industry Reform Act of 2001;
2. Negros PH will follow NGCP’s Open Access Policy requirements and procedures;
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
2/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
2 |
P a g e
3. Negros PH will consider the protection arrangement as required by NGCP, as the Grid
Owner;
4. Telecommunication and SCADA equipment will be advanced following the prescription of
the Energy Regulatory Commission under NGCP’s Draft Determination;
5. Protection equipment shall be provided, owned, operated and maintained by NGCP and
NPHSI at their respective sides; and
6. Technical specifications for equipment that are related to the interconnection facility and
interfacing of plant to NGCP’s system as SO shall be in accordance with applicable ERC
issuances (e.g. Philippine Grid Code) as well as NGCP’s standards. Proponent is even
willing to procure the accredited equipment manufacturers in ensure compliances.
It is considered that the assistance of NGCP, which plays critical roles as Transmission Provider,
System Operator and Metering Provider, is crucial to ensure the timely completion and successful
commissioning of the project.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
3/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
3 |
P a g e
1.0 Introduction
1.1 Project Background
Negros PH Solar Inc is developing a solar project in Negros island in a land totalling
to 150 hectares. Many of the landowners are prominent local business people with
good reputation. NPHSI aims to secure approximately 280 hectares to build a 200
MW solar in the future.
The interconnection is via the Bacolod – San Enrique 69 KV line which remains a
subtransmission asset. Following previous case precedents, the line has to be filed
for reclassification with the Energy Regulatory Commission.
Initially, this FS is only focused on 50 MW on Site 1 at Felisa given the tight
schedule set by the Department of Energy on the Feed-in Tariff:
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
4/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
4 |
P a g e
1.2 Scope/Purposes
This Facilities Study applies the findings in the SIS in identifying the necessary equipment
for the connection of the proposed project to the transmission system.
Specifically the study presents the following:
- Substation equipment specification
- Transmission Line requirements
- Identify the appropriate telecommunication and protection facility
The proposed layout of the solar farm is shown below. Note that the layout is for the full
development. This study will not give emphasis on plant’s specification.
Initial development based on the System Impact Study (re-run) will be redesigned such
that it will optimize the utilization of the area with aimed to put it closer to the tapping point
for immediate completion.
It must be emphasized however that the FS does not cover the plant’s configuration and
specifications including its high-voltage equipment such as inverter transformer and step-
up transformers including the switching equipment at the plant switchyard. The FS covers
starting the coordination of protection of the plant’s connection line to NGCP’s system
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
5/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
5 |
P a g e
including the SCADA and Telecom equipment which are all Grid assets pursuant to Article
4.3 of the Philippine Grid Code.
1.3 Description of Connection Facility
The scope of this facility study includes only the interconnection equipment needed to
connect the proposed generation plant to the grid. Included thus in this report are the
facilities and equipment from the generating plant “take‐of f” substation up to the tapping
point.
The receiving substation will be NGCP’s Bacolod Substation. The feeder circuit breaker
and its associated disconnect switches will serve as the disconnecting means for the
project in compliance with the requirements of ERC Resolution 16 Series of 2011. The
control of these equipment is at NGCP’s Bacolod Substation.
The connecting 69kV transmission line is designed to utilize steel/concrete poles which
are selected for this application to minimize the overall cost of the line in addition to the
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
6/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
6 |
P a g e
benefits of ease of transportation and installation. The 69kV transmission line will connect
at the existing Bacolod – San Enrique 69kV line as illustrated below. The location of the
solar take-off substation to the existing line is about
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
7/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
7 |
P a g e
safely and reliably integrated to the Visayas grid, Phase 2 can only be implemented
by the Negros-Panay 230 KV Project.
In agreement with NGCP, the technical assessment has to be conducted and it will
be discussed further in succeeding section.
In order to aid in determining the appropriateness of the equipment related to the
interconnection to NGCP’s system, relevant information have to be considered in
the FS.
i. Demand
ii. Capacity Additions Considered
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
8/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
8 |
P a g e
iii. Short Circuit Level at Bacolod
VISAYAS GRID FORECAST FAULT LEVELGenerator Impedance Used ‐ Subtransient (Xd")
(As of June 30, 2015)
BUS STATION KV
MAXIMUM FAULT
CURRENT, AmpTHEVENIN IMPEDANCE, Ohm
PHASE GROUND Z1_R Z1_X Z2_R Z2_X Z0_R Z0_X
37500 BACOLOD SS 138 4,034 4,464 3.47768 21.54910 3.70430 21.97810 2.42858 16.16490
35500 BACOLOD_69KV 69 6,578 9,007 0.98017 7.88087 1.03798 7.99257 0.29642 3.00741
Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence
VISAYAS GRID FORECAST FAULT LEVELGenerator Impedance Used ‐ Subtransient (Xd")(Projected 2016)
BUS STATION KV
MAXIMUM FAULT
CURRENT, AmpTHEVENIN IMPEDANCE, Ohm
PHASE GROUND Z1_R Z1_X Z2_R Z2_X Z0_R Z0_X
37500 BACOLOD SS 138 5,202 5,701 2.33511 14.7341 2.57988 14.4069 1.62274 11.8726
35500 BACOLOD_69KV 69 9,408 12,512 0.62706 4.80683 0.68234 4.75931 0.20064 2.03129
Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence
iv. Transmission Expansion Considered
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
9/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
9 |
P a g e
v. Technical Assessment
Results of the SIS shall be discussed in the attachment to be provided in the final
appendix.
2.0 Objective
Following the requirements prescribed under Module B15 of the Open Access
Transmission Service (OATS) Rules, the purpose of the facility study is to determine
the details of the connection scheme and specifications of the equipment to be used
to conform with the requirement of NGCP and in accordance with the provisions of
the Philippine Grid Code as amended in 2007, The Renewable Energy Act otherwise
known as RA 9513 and RA 9136 (EPIRA).
The primary objective of the Interconnection Facilities Study is to determine the
interconnection scheme to the transmission system. It intends to identify the major
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
10/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
1 |
P a g e
equipment related to interconnection and the necessary secondary devices which are
crucial infrastructures related to the role of NGCP as System Operation.
3.0 Connection Configuration
Anticipating the approval of the new PGC, it is considered safe that in the selection of
connection scheme it will be better to adopt the definition in amendment no. 2, which
states as quoted below:
“GCR 4.4.1 Requirements Relating to the ConnectionPoint
GCR 4.4.1.1 The Generator ’s Equipment shall be connected to the Grid or to
the Distribution System at the voltage level(s) agreed to by the Grid Operator
or the Distributor and the Generator based on Grid Impact Studies.
GCR 4.4.1.2 The Connection Point shall be controlled by a circuit breaker that
is capable of interrupting the maximum short circuit current at the point of
connection.
GCR 4.4.1.3 Disconnect switches shall also be provided and arranged to
isolate the circuit breaker for maintenance purposes.”
In the layout below, it already considered that mandatory requirements set by the PGC.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
11/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
11 |
P a g e
Figure 2: Basic layout of the substation
While the corresponding plan is:
Figure 3: Basic plan of the substation
4.0 Asset Boundary
In accordance with the Resolution 16 Series of 2011issued by the Energy Regulatory
Commission (ERC) dated 6 July 2011 Section 4.2 Connection Assets for Generation
Customers of Transmission Provider, 3rd paragraph, A generation company
may develop and own or operate a dedicated point-to-point limited facilities
provided,that such facilities are required only for the purpose of connecting to
the transmission system, and are used solely by the generating facility subject to priorauthorization by the ERC and following the convention in Annex C of said
resolution, the asset boundary between NPHSI and NGCP shall be at the at the tapping
point at San Enrique 69 KV line as illustrated below:
Following requirements at the tapping point, below are the illustration of the tapping point
but will be subject to the approval of NGCP prior to the construction stage.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
12/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
12 |
P a g e
Figure 4: Illustration of asset boundary
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
13/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
13 | P a g e
Figure 5: Details of the tap-connection
NPHSI shall execute the Fixed Asset Boundary Document as one of the attachments
of the Transmission Service Agreement.
The document will precisely show the Connection Point and shall specify the following:
a. Equipment and ownership
b. Accountable Managers
c. Safety Rules and procedures during Local Safety Instruction and the Safety
Coordination of any other persons for safety
d. Operational procedures and the responsible party for operation and control
e. Maintenance agreement and the responsible party for undertaking the
maintenance
f. Any agreement pertaining to emergency situation
5.0 Receiving Substation Facility Requirements
The existing Bacolod Substation 69kV switchyard will be maintained as is. The
“tapped” connection will not require modifications at the switchyard. Only
communication facility via optical groundwire will be installed at this substation.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
14/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
14 | P a g e
5.1.1 General Technical Requirements
The electrical equipment shall be designed in such a way as to bear without
damage and permanent deformation the consequences of over voltage of internal
or atmospheric origin and each electrical component can withstand the maximum
stresses under fault conditions.
Outdoor installations shall be protected against solar radiation by means of
adequate covers, where required, with non-deteriorating material.
All equipment shall be designed to be insensitive to any signals emitted by wireless
communication equipment.
All metallic frames shall be securely connected to the general earthing system in
compliance with accepted standards.
The center line spacing and clearances above ground level of the conductors
shall be as shown in the detailed design drawings.
The minimum clearance between live metal parts and ground shall be 837.5 mm.
while, the minimum clearance between live metal parts of two phases shall be 1500
mm. The practical distance between phase center lines shall be 1500 mm. and the
minimum height of live conductors above ground shall be 3000 mm, however, the
upper edge of an earthed insulator support shall have a height of, at least, 2300 mm.
above the ground level.
Creepage distance of equipment bushing, insulator strings, station post insulators
and rigid support insulators shall be equal or greater than the resultant of the 21mm/KV multiplied by the maximum nominal voltage. Outdoor equipment shall
be painted with RAL 7035 color, while indoor equipment (including inside cubicle)
shall be painted with RAL 7032 color.
Phase indication plates with color and code letters, which shall be luminous
and made of weather resistant materials, shall be provided on the substation steel
structures to indicate the phases of bus, incoming lines and transformer feeders
and shall be as follows: Phase A is Red and code is “A”; Phase B is Yellow and
code is “B”; and Phase C is Blue and code is “C”.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
15/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
15 | P a g e
Outdoor and indoor equipment and panels shall be labeled in accordance with the
Site and Equipment Identification and Labeling (SElL) standard of NGCP as
mandated by the Grid Code. NGCP, therefore, must provide guidance to
the developer on the appropriate nomenclature of the major devices
interphasing with NGCP’s System Operation.
5.1.2 Codes and Standards
All engineering, fabrication, construction/erection, startup and testing provided
by the Contractor shall be in accordance with applicable codes and standards,
regulations and guides. The applicable codes, standards and regulations will
consist of the substation requirements as the basis, and also include those for the
Contractor's nation as follows:
1) Philippine Standards and Codes
2) United States Standards and Codes (IEEE/ANSI/NEMA/NFPA etc.)
3) International Electro-technical Commission (IEC)
4) DIN (German)
5) BS (British standard)
6) JIS (Japanese Industrial Standard)
7) CNS (China National Standard)
5.2 Power Transformer
The Power Transformer i s rated 50/65 MVA (ONAN/ONAF), 13.2/69 kV,
60Hz, and capable of changing its tap ratio by+/- ten percent (10%), with
a step size of 1.25%. The HV bushings of the Power Transformer shall be
of the resin paper impregnated and non-draw lead type. Aside from the
insulation, polarization index, oil dielectric, polarity and ratio tests that are
required by NGCP to be conducted on the power transformer prior to
connection, other routine tests specified under the applicable ANSI/IEEE
standard and the manufacturer's standard test regime shall also be
conducted on the power transformer .
The cooling medium shall be oil and its temperature of cooling air shall not
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
16/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
16 | P a g e
exceed 40ºC. Cooler shall be transformer mounted and should be radiator fin
type. Monitoring and control system shall be interfaced at the Substation
Control System.
Transformer shall be equipped with On-load Tap Changer (OLTC) and should
be oil-immersed. Taps shall be ±0.625% by 8 taps. The motor of the OLTC
shall be sourced by 400 VAC, 3-phase at 60 Hz.
5.3 Power Circuit Breaker
The power circuit breakers (PCB) shall be of the SF6 and outdoor type. It
shall be rated at least 69 kV, 60 Hz, with continuous current rating at 60
Hz of at least 2000A rms, with interrupting time of no longer than 50 ms.
and shall be capable of interrupting successfully its rated interrupting current
of at least 4 0 kA rms, for its entire operational life. It shall be capable of
withstanding all system lightning impulse and switching over voltages
less than or equal to its Basic Impulse Level (BIL) or switching surge
withstand capability. Generally, the PCB shall meet or exceed all rated
values listed in applicable ANSI or IEC standards. The PCB shall bedesigned to have the capability of permitting, at least, two complete
closing-opening operations and to withstand swells caused by ground faults.
Each PCB shall be equipped with an operation counter.
Multiple-pole or single-pole tripping devices shall be protected against
accidental operation and conveniently located for manual tripping or local
operation of the PCB. The tripping mechanism shall have two (2) electrically
independent trip coils (circuits) per pole.
PCBs capable of single-pole actuation shall be provided with a phase
discrepancy monitoring and control system for synchronized closing and
opening operation of individual poles.
The PCB shall be capable of switching out line faults (regardless of the
distance between the circuit breakers and faults), no-load lines,
transformers on no-load and reactive loads without causing re-striking when
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
17/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
17 | P a g e
switching.
The PCB shall be equipped with enough auxiliary contacts to
accommodate the required status and alarm indications, plus additional
convertible eight (8) types A and B contacts each. The operating status
and other parameters of the PCB shall be monitored/interfaced with the
Substation Automation System (SACS).
The technical data sheets of the PCB are shown in subsequent Annex.
5.4 Disconnect and Earthing Swtich
Disconnect Switches (DS) shall be provided and arranged so as to isolate
the PCB during maitneannce. The switching device shall be station class,
outdoor, 3phase, two column horizontal center break type and rated 60 Hz,
69 kV, 2000 A rms and have a short-time withstand capability of at least
44 kA rms.
The switching device shall be three pole construction, horizontal mode of
contact separation with reference to the mounting plane, and equipped with
an earthing switch.
The switching device shall withstand and operate without malfunction with
simultaneously acting forces from connection at terminals and short circuit.
The safety factor against break of an insulator shall be at least 1.25 times
the simultaneously acting forces plus operating forces.
The DS shall have the capability of being either motor-operated or manual
through remote, local or manual mode.
The DS shall be equipped with enough auxiliary contacts to accommodate
the required status and alarm indications, plus additional convertible eight
(8) types A and B contacts each.
The operating status of the DS shall be monitored/interfaced with the
SACS, whenever applicable. It shall be equipped with key interlocks,
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
18/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
18 | P a g e
position indicator (both mechanical and light) and damping device.
The switching device shall be electrically interlocked with the associated
circuit breaker to prevent the possibility of making or breaking load current.
To prevent maloperation, the operating mechanism of disconnect
switches and earthing switches shall be interlocked relative to each other
such that when the main disconnect switch is in "closed" position, the
earthing switch cannot be closed and vice versa. Said interlocking
arrangements shall be effective both in local and in remote operation.
The technical data sheets of the Disconnect/Earthing Switch can be seen
in the Annexes.
5.5 Current Transformer (for statistical meter and protection purposes)
Current Transformers (CT) shall be provided for all PCBs. The CTs shall
be single pole. For outdoor installations, the CT's insulation medium shall
be oil. While, for indoor installations, the CT's insulation medium shall be
SF6 gas.
Current Transformers shall be rated at 69 kV, 60Hz. Its current ratio (with
secondary taps) shall be 2 0 00/1500/1000/500:5A. The CTs shall have 4
cores (i.e., 1 core for metering with accuracy class of 0.2 and 3 cores
for relaying with 5P20 accuracy class) per IEC standards. Rated burden
is 30 VA for metering and 100 VA for protection.
The short-time current thermal rating of the CTs shall be at least 4 0 kA
rms while the rated short-time mechanical is 100 KA rms. The cores shall be
designed and built in such a way that no reciprocal electromagnetic
influence or influence from external fields can occur .
The CT shall have adequate output to meet double the total burden
of the equipment connected to it. It shall also have sufficient thermal,
voltage, over-current performance, internal resistance and accuracy for
the satisfactory operation of the equipment connected to its secondary
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
19/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
19 | P a g e
circuit. CT shall withstand the mechanical and thermal stresses caused by
short circuits.
CTs provided for protective purposes shall have over current and saturation
factors not less than those corresponding to the design short circuit level of
the system.
The technical data sheets of the CT (not for billing purposes) are shown in the
Annexes.
5.6 Potential Device
PT shall be of the inductive type, with a marked ratio of 600/345:1 and its
rated secondary voltage shall be 115 VL _J66 .4 VL-G· It shall be of the
accuracy IEC Class 0.3. The burden rating shall be at least 12.5 VA which
can handle the total burden of the cables and all connected devices at the
PT/VT secondary circuit. It shall have three (3) secondary cores/windings,
both, preferably of metering class accuracy. It shall be tested and certified on
ratio accuracy, phase deviation and insulation integrity.
For its rated insulation, the lightning impulse withstand voltage is 350 KV peak
while power frequency withstand voltage is 140 KV rms dry.
The technical data sheets of the Voltage Transformer can be seen in Annex
M, while the test reports of the VTs are shown in the Annexes.
5.7 Surge Arrester
Each arrester shall be station class, outdoor type, metal oxide (i.e., ZnO)
and gapless type with surge counter. Material of insulator can be composite
type.
The surge arrester at the high voltage (69 kV) side shall be rated for
nominal system voltage of 69 kV, while that of the low voltage side shall
be 13.2 kV. The arrester shall be rated 60 Hz, and its Duty Cycle Voltage
rating shall be 60 kV rms, nominal discharge current of 10 kA and the
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
20/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
2 | P a g e
Lightning Impulse Withstand Voltage capability of its post insulator
housing, for outdoor installations, shall be 325 kV.
The arrester assembly shall consist of an arrester unit, line terminal,
earth terminal, insulating base, cyclometer type discharge counter with
integral continuous AC leakage/internal current indicator. Outdoor
installations shall have a supporting structure.
Remote indication of discharge counter registers shall be provided and
interfaced with the SACS, if applicable.
The arrester housing shall have either a hollow insulator with gas filling
(tube design) or directly molded housing material on the MO-blocks caged
by FRP rods ("caged design"). Insulator material shall be either porcelain or
silicon rubber.
The unit shall be hermetically sealed, moisture free. For hollow insulators
(tube design), a pressure relief device is required to limit the internal
pressure so as to prevent explosion or violent shattering of the housing
during short circuit current conditions. For outdoor installations, the arresters
shall be vertically mounted on a horizontal surface.
For outdoor installations, each arrester shall be furnished complete with a
non-corroding clamp type ground connector suitable for copper stranded
conductor. The arrester supporting structure shall be provided with a
grounding pad. Each grounding pad shall be flat and shall be provided with
a non-corroding clamp type connector suitable for, at least, 100 sq.mm. sizedannealed, stranded PVC insulated copper ground conductor. The grounding
pad shall be located about 400 mm above finished ground level.
5.8 Substation Automation Control System
The Substation may be equipped with a microprocessor-based Substation
Automation Control System (SACS) to perform control and monitoring
tasks for all the major and critical equipment in the substation. The SACS
consists of the operator workstations, data highway, process controllers,
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
21/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
21 | P a g e
engineering workstation, servers, gateways, GPS Time, and all necessary
peripherals. The SACS shall be equipped with at least three (3) data
communication ports to satisfy NGCP Supervisory Control and Data
Acquisition (SCADA) requirements. In the event that the substation is not
equipped with a SACS or the number of data communication ports of the
SACS be insufficient to satisfy the SCADA requirement, a Remote Terminal
Unit (RTU), with, at least, three (3) data communication ports shall be
provided by NGCP and shall be connected to the DNP 3.0-configured data
communication port of the SACS, if applicable. Said three (3) data
communication ports shall use the DNP 3.0 data communication
protocol to communicate with the Back-up NationaV Regional Control Center
(BNIRCC) in Cebu; the Back-up Regional Control Center (BRCC) in Mandaue,
also in Cebu; and, the Area Control Center (ACC) in Iloilo.
The SACSIRTU shall be equipped with sufficient digital and analog inputs
and control outputs to monitor and control all necessary parameters of the
various plant and substation equipment, with enough spare input, output and
control modules.
The SACSIRTU shall display, aside from the important substation diagrams
and parameters, the single-line diagram of the major substation equipment,
including the out-going lines, together with their identification names
conforming to NGCP's Site and Equipment Identification and Labeling (SElL)
Standard.
The SACS/RTU shall monitor and communicate the following substation
equipment parameters to the above said NGCP Control Centers:
1) Each Power
Transformer
• MW
• MVAR
• MVA
• Current, A (each phase)
• Voltage, kV (each phase)
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
22/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
22 | P a g e
• Pressure Relief Alarm
• Transformer Differential Relay Alarm
• Buchholz Relay Alarm
• Overcurrent Relay Alarm
• High Winding Temperature Alarm
• Lock-out Alarm
2) Each High Voltage Bus
Voltage
Frequency
Bus differential relay alaRm
3) Power Circuit beaker Status (open, close)
Spring charge alarm
BFR alarm
Auto-reclaose Operation
Open/Close Control Operation
6.0 Transmission Line
6.1 Steel Structure
The structures are made from concrete and designed for 69 kV. The structures are
designed for outdoor, tropical, salt and dust laden and heavily contaminated
atmospheric conditions.
The structures are designed to consider the weight of porcelain insulator strings and
the length of composite insulator strings so that in any maintenance work requiring
replacement of insulator string assembly, both types of insulator assembly can
be used without any restrictions
6.2 Conductor
The conductors to be used at the high voltage (69 kV) shall be 336.4 MCM
ACSR (Linnet), while the line hardware to be used shall be appropriate for said size
of cable.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
23/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
23 | P a g e
The conductor and wire data are as follows:
Particular Data
Size and type ACSR/AS 336.4 MCMC “Linnet” Stranding 26/7Outside diameter 18.26mm Area 198.21 sq.mm.Weight 0.6553 kg/mBreaking strength 6,110 kgs.
6.3 Optical Pilot Ground Wire
The Optical Pilot Ground Wire (OPGW) shall be 1550 nm, single-mode, 36-core fiber based on ITU-T G.652D.
6.4 Conductor Clearances
The Philippine Electrical Code Part II sets safety clearances from ground,
structure and vegetation. Values below are the minimum vertical clearances:
Crossing over at 50ºC no wind final sag Clearance in meterTrack rails of railroad 11.5Public streets and highways 10Rural roads 8.5
Cultivated fields, area accessible only topedestrian along roads in rural areas
7.5
All other types of obstruction Refer to PEC Part II
6.5 Pole Design Criteria
Footing resistance is ≤10 ohms
Design wind velocity is 270 kph
Wind pressure on poles will be in accordance with NESC Rule 252B2
Wind pressure on wires will be in accordance with NESC Rule 250C
6.6 Pole Setting
Pole will be direct buried and below will be followed:
Pole height (in feet) Depth of setting (in feet)On rock On Earth
50 4.5 6.555 5.0 7.0
60 5.5 7.565 6.0 8.0
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
24/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
24 | P a g e
70 6.5 8.5
6.7 Insulator
Porcelain or polymer insulator can be used: suspension or post type. For
porcelain appropriate mechanical and electrical rating shall be used. For the
polymer insulator, appropriate specified mechanical load and routine tests load
rating shall be used.
Electrical Parameters:
Nominal system voltage – 69 KV rms
Maximum system line-to-ground voltage – 41.8 KV rms Maximum peak line-to-ground voltage – 59.1 KV rms
Leakage Distance Requirements
Assumed ESDD – 0.01 – 0.04 mg/sq.mm.
Pollution severity – medium (moderately polluted area to be
considered)
Leakage distance – 20mm/KV
Impulse Overvoltage Requirements
Assumed peak impulse current – 40 KA
Pole footing resistance - ≤10 ohm
Impulse withstand – 400 KV
6.8 Line Hardwares
All line hardwares to be used shall be compatible with all the associated lien
materials to be supplied.
6.9 Pole Resistance
Resistance measurement will be conducted to ensure that all poles to be built
are properly grounded. Pole footing earth resistance shall not exceed 10 ohms
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
25/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
25 | P a g e
otherwise ground rods or counterpoise shall be installed to meet the required
earth resistance.
7.0 Take-off Substation
The proposed power plant “take‐off” substation will located within NPSI-Felisa Solar
Power facilities The following switchyard equipment not including generator ‐related
facilities, will be installed at the substation:
a. One (1) set of power transformer, 50/65MVA, 13.8/69kV
b. One (1) set power circuit breakers, 69 kV, 40 kA
c. Two (2) sets disconnect switches, 69 kV, 2000A
d. One (1) set current transformer, 69 kV, 2000:5A
e. One (1) set voltage transformer, 69 kV, 350/600:1
f. Two (2) sets surge arrester, 60 kV
The tapping connection shall be installed with Disconnect Switch and Line Fault
Indicator as shown in earlier drawings (Figure No. 5).
Excluding generator ‐related equipment, the following auxiliary power system facilities
will be installed at the control building:
a. 400/230 Vdc Distribution Board
b. 125 Vdc Battery, Charger, and Distribution System
c. 48 Vdc Battery, Charger, and Distribution System
d. 240 Vac UPS System
Switchyard conductors to be used shall be 850 mm2 THAL. OHGW shall be 7/8
Aluminum Clad.
Below is the indicative layout of the substation
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
26/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
26 | P a g e
Figure 6: Illustrations of Plan and Layout
Naming conventions of all equipment will follow the GMC’s mandated use of Standard
Equipment Identification and Labelling (SEIL). The proponent shall follow the
prescribed naming to be suggested by NGCP.
8.0 Protection, Control and Monitoring Requirement
Protection relay, control and monitoring equipment should be provided for the “take ‐
off” substation and the new transmission line. These protection schemes were
designed consistent with the requirements of NGCP’s Network Protection Philosophy.
For the “take‐off” substation, the following protection, control, monitoring and
communication equipment should be provided:
a. Protection Main1 and Main 2
b. Transformer Protection Main 1
c. Network Disturbance Monitoring Equipment
d. Control Switchboard
e. Fiber Optic Terminal Equipment
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
27/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
27 | P a g e
Protection equipment at Bacolod Substation will be as‐is.
Communication between the receiving and the “take‐off” substations to provide for
exchange of remote control signal, alarm status, metering data, relay communications
requirements, and voice link shall be implemented through OPGW.
Metering CT and PT will be provided by the Project Proponent while revenue meters
may be supplied by NGCP as metering service provider and will be installed at the
“take‐off” substation.
Technical Data sheet are provided in the Annexes.
9.0 Communication and SCADA Requirements
Section 4.6.1 Communication System for Monitoring and Control of Chapter 4 Grid
Connection Requirements, a communication system shall be established so that Grid
Owner, the System Operator and the Users can communicate with one another as
well as exchange data signals for monitoring and controlling the Grid during normal
and emergency condition. On the other hand, Section 4.6.2 SCADA System for
Monitoring and Control, the Grid Owner shall provide a Remote Terminal Unit (RTU)
for interconnection of the System Operator's Control Center to serve as telemetry
equipment for monitoring real time information and controlling the Equipment at
the User System.
The Communication and SCADA shall be provided to communicate the proposed
50 MW solar project is described in the succeeding article.
Technical Data sheet are provided in the Annexes.
10.0 Revenue Metering
NPHSI has not decided on what metering agreement it will enter with NGCP.
Nevertheless, NPHSI will be guided with the following NGCP standards for the
Revenue Metering as described in succeeding paragraph.
In accordance with Section 8.2.1 Metering Equipment of Chapter 8 of PGC, the
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
28/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
28 | P a g e
Metering E quipment at the Connection point shall consist of :
a. Instrument Transformers;
b. Lightning Protections;
c. Revenue Class Meters;
d. Integrating pulse recorder(s) and time source;
e. All interconnecting wires and associated devices;
f. Data communication devices; and
g. Mounting structures and ground wires for instrument transformers
The technical requirements and the e quipment specifications shall be in
accordance with NGCP's Standard Specifications as described below:
“ A. MINIMUM TECHNICAL REQUIREMENTS FOR THE GRID METERING
FACILITIES:
1. Blondel's Theorem Compliance. The metering circuit for a 3-phase
4- wire Y connection of the Customer circuit, shall be 3-Eiement.
For a 3- Phase 3-Wire Delta connection, the metering circuit shall be
Delta connected 2 Element.
For the 3-Eiement, 4-Wire Y metering circuit, the Neutral Point of the
Potential and Current Transformer Secondaries are to be grounded
at a single point to the system ground mat through the grounding
connection at the meter enclosure.
2. Exclusive Use of Instrument Transformers for Revenue Metering.
To safeguard the security of the metering facility, and to prevent the
simultaneous loss of metering and other functions in case of
instrument transformer failure, the Potential and Current Transformers
shall be exclusively used for revenue metering. The use of the
instrument transformers for both revenue metering applications
and substation protection is not allowed, even with separate
cores/windings.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
29/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
29 | P a g e
3. Voltage or Potential Transformers (VT or PT)
a. Type: Inductive type
b. Secondary Voltage: 115VAC for 34KV and above, 120VAC
for lower voltages
c. Accuracy Class: ANSI Class 0.3/IEC Class 0.2 or better
d. Burden Rating: Must be at least 100% higher than the total
burden of the cables and all connected devices at the PT
secondary circuit.
e. Secondary Cores/Windings: Preferably 2, both of which are
metering class
f. Factory Test Report(s): Test Reports of Ratio Accuracy,
Phase Deviation, and Insulation Integrity
4. Current Transformers (CT)
a. Type: Inductive-type
b. Secondary Current: 0-5A
c Primary Current Range: 1.25 - 1.5 x the expected Full Load
Current. For a CT with multiple ratios, the change of tapping
shall be at the secondary side.
d. Accuracy Class: For Loads: ANSI Class 0.3/IEC Class 0.2 or
Better
For Generators: ANSI Class 0.15/IEC Class 0.2s or Better
e. Burden Rating: Must be at least 100% higher than the total
burden of the cables and all connected devices at the CT
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
30/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
3 | P a g e
secondary circuit.
f. Secondary Cores/Windings: Preferably 2, both of which are
metering class
g. Factory Test Report(s): Test Reports of Ratio Accuracy,
Phase Deviation, and Insulation Integrity. For multiple-ratio
CT's, they shall be factory-tested for accuracy and phase
deviation at all current ratios.
5. Lightning/Surge Arresters. Lightning/surge arresters ofappropriate electrical ratings for the application shall be installed at
the line side of the instrument transformers.
6. Metal Meter Security Enclosure. A steel or aluminum security
enclosure for the main and alternate meter which can be secured by
padlocks and security seals shall be provided. The enclosure shall be
provided with a glass viewing window for visual observation/reading
of meter registers.
7. Instrument Transformer Secondary Cables. The cables shall be
stranded and with a minimum size of No.12 AWG, and whose
resistance shall not cause the burden of the metering circuit to
exceed 50% of the rated burden of the instrument transformers at
a maximum length of 15 meters from the instrument transformer
secondary terminal to the metal enclosure.
All Instrument Transformer Secondariesare to be cabled through
the Meter Enclosure, including unused instrument transformer
secondaries.
8. Rigid Steel Conduits for Instrument Transformer Secondaries,
routed directly to the Meter Security Enclosure without any marshalling
box or conduit openings. Only metering circuit cables must be
contained in the conduits.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
31/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
31 | P a g e
9. Copper Grounding Cable. Cable size is 4/0 Minimum for
connecting the Instrument Transformer housings, grounded
secondaries and the Meter Enclosure to the Substation Ground Mat.
10. Billing Meter(s). The revenue-class meter(s) shall conform with
functional requirements and specifications prescribed under the
Philippine Grid Code and the WESM Metering Manual.
11. Meter Test Block. A 10-pole switch assembly where the instrument
transformer secondary cables terminate and where the meter is
connected for the purpose of isolating the meter from service and
providing a means of injecting test currents and voltages into the meter
when the meter is to undergo accuracy tests.
11.0 Project Bill of Materials
Below is the preliminary requirements of primary devices and accessories at Felisa:
NPSI-Felisa Solar Take-off S/S
ITEMNO.
DESCRIPTIONQUANTIT
YUNIT
A. HV SWITCHYARD EQUIPMENT
1
GENERATOR STEP-UP TRANSFORMER, 13.8/69kV,50/65MVA, 3f, ONAN/ONAF, complete with oil, allappurtenances, accessories, on-load tap changingmechanism,and other required accessories, supportingstructures, anchor bolts, foundations, etc.
1 set
2
POWER CIRCUIT BREAKER, 69kV, 40kA, 2000A, livetank type, suitable for 3 pole operation, complete with allthe required accessories, supporting structures, anchorbolts, foundations, etc.
1 set
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
32/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
32 | P a g e
3DISCONNECT SWICTH, 69kV, 40kA, 2000A, withoutEarthing Switch, pedestal mounted, complete with all therequired accessories, anchor bolts, foundations, etc.
2 sets
4
CURRENT TRANSFORMER, 69kV, 4-core with 1metering (Cl 0.2 30VA) and 3 relaying (5P20 100VA),multi-ratio (2000/1500/1000/800/500:5) complete with allthe required accessories, supporting structures, anchorbolts, foundations, etc.
3 each
5
VOLTAGE TRANSFORMER, 69kV, 600/350:1, inductivetype, two secondary winding, 20VA, complete with all therequired accessories, supporting structures, anchor bolts,foundations, etc.
3 each
6
SURGE ARRESTER, 60kV, Metal Oxide, gapless,
complete with all the required accessories, supportingstructures, anchor bolts, foundations, etc. 6 each
7
COMBINED CT/VT, 69kV, for billing, CT: 2 metering core(Cl 0.2S 20VA) 300/150:5 and PT: two secondary winding(Cl 0.2 50VA) 350:1, complete with all the requiredaccessories, supporting structures, anchor bolts,foundations, etc.
3 each
8
SUBSTATION STEEL STRUCTURES for 69kV hot-dipped galvanized complete with mounting bolts andaccessories in accordance with the technical data sheetsand drawings
1 lot
9
STATION INSULATORS for 69kV, string and post (bussupport), complete with all the required accessories,protection against electrolytic corrosion, grading shields,etc.in accordance with the technical data sheets anddrawings
1 lot
10
BUS CONDUCTOR AND HARDWARE for 69kVconsisting of conductors, hardwares, connectors, fittings,clamps, etc. in accordance with the technical data sheetsand drawings
1 lot
11STATION SERVICE TRANSFORMER, 3-phase,complete with all the required accessories, anchor bolts,foundations, etc. in accordance with the drawings.
a. 75kVA, 13.8kV/400V complete with fuse cutout andlightning arrester
1 set
b. 75kVA, 13.2kV/400V complete with fuse cutout andlightning arrester
1 set
12AUXILIARY POWER SUPPLY SYSTEM, complete withall the required accessories, intruments, relays, etc. inaccordance with the drawings.
a. 400/230 VAC Auxiliary Board 1 lot
b. 125 VDC Auxiliary Board 1 lot
c. 48 VDC Auxiliary Board 1 lot
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
33/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
33 | P a g e
13STORAGE BATTERIES, complete with all the requiredaccessories, support rack, etc. in accordance with thetechnical data sheets and drawings
a. 125 VDC Battery Bank 2 sets
b. 48 VDC Battery Bank 2 sets
14
BATTERY CHARGER/RECTIFIER, 125 and 48VDC,complete with all the required accessories, intruments,relays, etc. in accordance with the technical data sheetsand drawings
a. 125 VDC Battery Charger/Rectifier 2 sets
b. 48 VDC Battery Charger/Rectifier 2 sets
15UPS POWER SUPPLY SYSTEM, complete with all therequired accessories, intruments, relays, etc. inaccordance with the technical data sheets and drawings
1 set
16DIESEL GENERATOR SET, 60 kW, 400V, 0.8 p.f., 60Hz,complete with all the required accessories, intruments,relays, etc.
1 set
17CABLES, provided with filler and binder tapes,termination kits and accessories, etc. in accordance withthe requirements of the technical data sheets.
1 lot
a. XLPE Power Cable, 15kV Insulation 1 lot
b. Power Cable, 600 V Insulation 1 lot
c. Control and instrumentation Cable, 600V Insulation,shielded 1 lot
18CONDUITS AND CABLE TRAY SYSTEM, various sizes,including, supports, fittings and accessories inaccordance with the technical data sheets and drawings
1 lot
19
GROUNDING SYSTEM for the Substation includingOHGW, air terminals, connectors, fittings, hard-drawncopper conductors, ground rods, mold, powder forexothermic connections, molds, flint guns, etc.inaccordance with the technical data sheets and drawings
1 lot
20
LIGHTING SYSTEM, complete with lighting fixtures,lamps, lamp posts with ground terminals includingfoundation if required, conductor, conduits, switches,boxes, etc., for the switchyard, roadways, perimeter andcontrol building and other indoor establishmentinaccordance with the technical data sheets and drawings
1 lot
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
34/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
34 | P a g e
21
CONTROL BUILDING, complete design andconstruction of single-storey building. Reinforcedconcrete/steel structure and pre-painted long spanroofing, roof slab canopy complete with the requiredarchitectural/civil/structural/sanitary/electrical/mechanical to complete to complete the scopeof works for the building in accordance with drawings
1 lot
The transmission connection asset is:
TRANSMISSION LINE
ITEMNO. DESCRIPTION QUANTIT Y UNIT
A. 69kV TRANSMISSION LINE
1
TRANSMISSION LINE comprising of steel poles, poledressing, guying and supports, conductors, insulatorfrom the take-off substation to the designated tappingpoint including reconfiguration of existing NGCP Pole(designated tapping point)
1 km.
2LOAD BREAK SWITCH, 630A, 20kA, 69kV, completewith all the required mounting accessories
2 sets
The secondary devices are summarized as follows:
NPSI-Felisa Solar Take-Off S/S
ITEMNO.
DESCRIPTIONQUANTIT
YUNIT
A. SUBSTATION PROTECTION SYSTEM
113.8/69kV Transformer Protection System, numerical,transformer differential protection
1 set
B. LINE PROTECTION SYSTEM
169kV Line Protection System (Main 1 - line distanceprotection)
1 set
269kV Line Protection System (Main 2 - directionalphase and ground overcurrent protection)
1 set
C. SUBSTATION MONITORING SYSTEM
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
35/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
35 | P a g e
1
Network Disturbance Monitoring Equipment fullycompatible with NGCP Master Station complete withaccessories and necessary interface devices (DI: 96 & AI: 32)
1 lot
D. SUBSTATION CONTROL SYSTEM
1Main Control Switchboard complete with mimicdiagram, meters etc.
1 lot
2Remote Terminal Unit complete with interfaceequipment, I/O modules, etc.
1 lot
E. FIBER OPTIC COMMUNICATION SYSTEM
1
Fiber Optic Terminal Equipment, complete with opticaldistribution frame (ODF), access multiplexers,indicators, pigtails, patchcords and otherappurtenances
1 lot
2Fiber Optic Approach Cable, 36 fibers, 1550nm, singlemode
1 lot
No consideration yet on the civil works and additional electrical works that may only
be determined during the detailed engineering design. Variation works may be
expected depending on actual site conditions.
12.0 Project Cost and Assumptions
Assumption in deriving the project cost is based on accuracy of ±10% and already
considered the applicable taxes and contingencies equivalent to same assumptions.
Applicable taxes already considered the applicability of RA 9513 to the proponent.
Acquisition of right-of-way of the line and site, for purposes of this facilities study, are
already excluded including the engineering activities. Interest during construction is
likewise considered for purposes of this interconnection study.
Exchange rates considered is 1US$ to PhP 45.
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
36/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
36 | P a g e
For NGCP substation, considering that the existing facilities (Bacolod-San Enrique)
will be used as the interconnection facility, it is assumed that there will be no primary
devices upgrading at the side of NGCP’s substation
13.0 Recommendation
The interconnection scheme (configuration and the line), its associated primary
devices and secondary devices (protection arrangement, telecommunication and
SCADA) and metering are presented based on initial assessment and analysis.
However, there are still needed coordination with NGCP as Grid Owner, System
Operator and Wholesale Metering Service Provider on the following:
1. Submission of major equipment and specifications related to interconnection to
conform with the requirements of NGCP. This does not cover however the plant’s
equipment and specifications including the transformers related to the conversion
from DC to AC and stepping-up to the voltage agreed upon with NGCP;
2. Electrical diagrams and drawings covering the grid assets (i.e., SCADA and
Telecom equipment) shall be approved by NGCP;
3. Procurement of brand acceptable to NGCP will be pursued particularly the
protective equipment;
4. The secondary devices (i.e., SCADA and Telecom equipment) which are all grid
assets per Grid Code will be funded but manufacturer’s drawings shall be approved
by NGCP;
5. Protection equipment shall be provided, owned, operated and maintained by
NGCP and NPHSI at their respective sides but the latter may consider of engaging
the maintenance services of NGCP;
6. Protection setting shall be consistent with the prescribed settings of NGCP to
coordinate with its current protection scheme; and
-
8/17/2019 0 NPSI-Felisa Solar FS Write-up
37/37
Interconnection Facilities Study
For Felisa 50 MW Solar Power Plant Negros PH Solar Inc.
7. NPHSI shall coordinate closely with NGCP for the commissioning and testing of
the solar plants following NGCP’s Open Access Policy, Grid Code, OATS Rules
and ERC Resolution No. 7-2014 on the testing of VRE as outline below, the PGC
Minimum Requirements for Large PVS (>20MW):
Specific Requirements Large PVS Field Test LaboratoryTest
Certification
2.1 Generating unitpower output
2.2 Frequency withstand
capability
2.3 Reactive Powercapability
2.4 Performance duringnetwork disturbances
2.5 Voltage Controlsystem
2.6 Active Power Controlsystem
2.7 Power Quality 4.1 Information
Exchange/SCADA Test