0 npsi-felisa solar fs write-up

Upload: negros-solar-ph

Post on 06-Jul-2018

266 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    1/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    1 |

    P a g e 

    Executive Summary

    This Facilities Study is conducted for the 50 MW Negros PH Solar Inc.’s Solar Power Project in

    Brgy. Felisa, Mansilingan, Bacolod City, Negros Occidental. This study aims to identify the

    necessary connection equipment to connect the proposed power plant to the grid. The connection

    configuration presented in this study is based on the connection requirement of NGCP as

    documented in the System Impact Study for the project.

    The connection arrangement is compliant with the requirements of the Philippine Grid Code and

    other applicable regulatory issuances. The proposed project will connect to the grid through a 69

    kV transmission facility approximately 1 km in length. The connection will be a ”tapped”

    connection along the existing 69 kV transmission line owned by NGCP. Power generated from

    the proposed power plant will be delivered to CENECO, NOCECO and to the grid through NGCP’s

    Bacolod Substation.

     After a series of discussion, it was agreed with the local NGCP that no switching substation will

    be installed at the tapping point. Aerial disconnect switch will be installed next to the tapping point

    and another one on the tapping pole isolating the CENECO/NONECO line.

    In compliance with the requirement of ERC Resolution 16 series of 2011, the power plant’s

    disconnection means will be the existing feeder breaker and corresponding disconnect switchesat Bacolod Substation. Included in this study are the telecommunication and protection equipment

    needed in by the power plant. From the results of the System Impact Study, no other

    improvements or additions will be required for the transmission network beyond the connection

    point.

    The following are the results of the FS:

    1. No issue on the proposed connection scheme as this is to be owned by the developer

    following provisions of the Section 9 of the Electric Power Industry Reform Act of 2001;

    2. Negros PH will follow NGCP’s Open Access Policy requirements and procedures; 

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    2/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    2 |

    P a g e 

    3. Negros PH will consider the protection arrangement as required by NGCP, as the Grid

    Owner;

    4. Telecommunication and SCADA equipment will be advanced following the prescription of

    the Energy Regulatory Commission under NGCP’s Draft Determination;

    5. Protection equipment shall be provided, owned, operated and maintained by NGCP and

    NPHSI at their respective sides; and

    6. Technical specifications for equipment that are related to the interconnection facility and

    interfacing of plant to NGCP’s system as SO shall be in accordance with applicable ERC

    issuances (e.g. Philippine Grid Code) as well as NGCP’s standards. Proponent is even

    willing to procure the accredited equipment manufacturers in ensure compliances.

    It is considered that the assistance of NGCP, which plays critical roles as Transmission Provider,

    System Operator and Metering Provider, is crucial to ensure the timely completion and successful

    commissioning of the project.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    3/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    3 |

    P a g e 

    1.0 Introduction

    1.1 Project Background

    Negros PH Solar Inc is developing a solar project in Negros island in a land totalling

    to 150 hectares. Many of the landowners are prominent local business people with

    good reputation. NPHSI aims to secure approximately 280 hectares to build a 200

    MW solar in the future.

    The interconnection is via the Bacolod – San Enrique 69 KV line which remains a

    subtransmission asset. Following previous case precedents, the line has to be filed

    for reclassification with the Energy Regulatory Commission.

    Initially, this FS is only focused on 50 MW on Site 1 at Felisa given the tight

    schedule set by the Department of Energy on the Feed-in Tariff:

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    4/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    4 |

    P a g e 

    1.2 Scope/Purposes

    This Facilities Study applies the findings in the SIS in identifying the necessary equipment

    for the connection of the proposed project to the transmission system.

    Specifically the study presents the following:

    -  Substation equipment specification

    -  Transmission Line requirements

    -  Identify the appropriate telecommunication and protection facility

    The proposed layout of the solar farm is shown below. Note that the layout is for the full

    development. This study will not give emphasis on plant’s specification.

    Initial development based on the System Impact Study (re-run) will be redesigned such

    that it will optimize the utilization of the area with aimed to put it closer to the tapping point

    for immediate completion.

    It must be emphasized however that the FS does not cover the plant’s configuration and

    specifications including its high-voltage equipment such as inverter transformer and step-

    up transformers including the switching equipment at the plant switchyard. The FS covers

    starting the coordination of protection of the plant’s connection line to NGCP’s system

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    5/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    5 |

    P a g e 

    including the SCADA and Telecom equipment which are all Grid assets pursuant to Article

    4.3 of the Philippine Grid Code.

    1.3 Description of Connection Facility

    The scope of this facility study includes only the interconnection equipment needed to

    connect the proposed generation plant to the grid. Included thus in this report are the

    facilities and equipment from the generating plant “take‐of f” substation up to the tapping

    point.

    The receiving substation will be NGCP’s Bacolod Substation. The feeder circuit breaker

    and its associated disconnect switches will serve as the disconnecting means for the

    project in compliance with the requirements of ERC Resolution 16 Series of 2011. The

    control of these equipment is at NGCP’s Bacolod Substation. 

    The connecting 69kV transmission line is designed to utilize steel/concrete poles which

    are selected for this application to minimize the overall cost of the line in addition to the

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    6/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    6 |

    P a g e 

    benefits of ease of transportation and installation. The 69kV transmission line will connect

    at the existing Bacolod – San Enrique 69kV line as illustrated below. The location of the

    solar take-off substation to the existing line is about

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    7/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    7 |

    P a g e 

    safely and reliably integrated to the Visayas grid, Phase 2 can only be implemented

    by the Negros-Panay 230 KV Project.

    In agreement with NGCP, the technical assessment has to be conducted and it will

    be discussed further in succeeding section.

    In order to aid in determining the appropriateness of the equipment related to the

    interconnection to NGCP’s system, relevant information have to be considered in

    the FS.

    i. Demand

    ii. Capacity Additions Considered

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    8/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    8 |

    P a g e 

    iii. Short Circuit Level at Bacolod

    VISAYAS GRID FORECAST FAULT LEVELGenerator Impedance Used ‐ Subtransient (Xd")

    (As of June 30, 2015)

    BUS STATION KV

    MAXIMUM FAULT

    CURRENT, AmpTHEVENIN IMPEDANCE, Ohm

    PHASE GROUND Z1_R Z1_X Z2_R Z2_X Z0_R Z0_X

    37500  BACOLOD SS  138  4,034 4,464 3.47768 21.54910 3.70430 21.97810 2.42858 16.16490

    35500  BACOLOD_69KV   69  6,578 9,007 0.98017 7.88087 1.03798 7.99257 0.29642 3.00741

    Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence 

    VISAYAS GRID FORECAST FAULT LEVELGenerator Impedance Used ‐ Subtransient (Xd")(Projected 2016)

    BUS STATION KV

    MAXIMUM FAULT

    CURRENT, AmpTHEVENIN IMPEDANCE, Ohm

    PHASE GROUND Z1_R Z1_X Z2_R Z2_X Z0_R Z0_X

    37500  BACOLOD SS  138  5,202 5,701 2.33511 14.7341 2.57988 14.4069 1.62274 11.8726

    35500  BACOLOD_69KV   69  9,408 12,512 0.62706 4.80683 0.68234 4.75931 0.20064 2.03129 

    Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence 

    iv. Transmission Expansion Considered

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    9/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    9 |

    P a g e 

    v. Technical Assessment

    Results of the SIS shall be discussed in the attachment to be provided in the final

    appendix.

    2.0 Objective

    Following the requirements prescribed under Module B15 of the Open Access

    Transmission Service (OATS) Rules, the purpose of the facility study is to determine

    the details of the connection scheme and specifications of the equipment to be used

    to conform with the requirement of NGCP and in accordance with the provisions of

    the Philippine Grid Code as amended in 2007, The Renewable Energy Act otherwise

    known as RA 9513 and RA 9136 (EPIRA).

    The primary objective of the Interconnection Facilities Study is to determine the

    interconnection scheme to the transmission system. It intends to identify the major

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    10/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    1 |

    P a g e 

    equipment related to interconnection and the necessary secondary devices which are

    crucial infrastructures related to the role of NGCP as System Operation.

    3.0 Connection Configuration

     Anticipating the approval of the new PGC, it is considered safe that in the selection of

    connection scheme it will be better to adopt the definition in amendment no. 2, which

    states as quoted below:

    “GCR 4.4.1 Requirements Relating to the ConnectionPoint 

    GCR 4.4.1.1 The Generator ’s Equipment shall be connected to the Grid or to

    the Distribution System at the voltage level(s) agreed to by the Grid Operator

    or the Distributor and the Generator based on Grid Impact Studies.

    GCR 4.4.1.2 The Connection Point shall be controlled by a circuit breaker that

    is capable of interrupting the maximum short circuit current at the point of

    connection.

    GCR 4.4.1.3 Disconnect switches shall also be provided and arranged to

    isolate the circuit breaker for maintenance purposes.” 

    In the layout below, it already considered that mandatory requirements set by the PGC.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    11/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    11 |

    P a g e 

    Figure 2: Basic layout of the substation

    While the corresponding plan is:

    Figure 3: Basic plan of the substation

    4.0 Asset Boundary

    In accordance with the Resolution 16 Series of 2011issued by the Energy Regulatory

    Commission (ERC) dated 6 July 2011 Section 4.2 Connection Assets for Generation

    Customers of Transmission Provider, 3rd paragraph, A generation company

    may develop and own or operate a dedicated point-to-point limited facilities

    provided,that such facilities are required only for the purpose of connecting to

    the transmission system, and are used solely by the generating facility subject to priorauthorization by the ERC and following the convention in Annex C of said

    resolution, the asset boundary between NPHSI and NGCP shall be at the at the tapping

    point at San Enrique 69 KV line as illustrated below:

    Following requirements at the tapping point, below are the illustration of the tapping point

    but will be subject to the approval of NGCP prior to the construction stage.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    12/37

     

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    12 |

    P a g e 

    Figure 4: Illustration of asset boundary

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    13/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    13 | P a g e  

    Figure 5: Details of the tap-connection

    NPHSI shall execute the Fixed Asset Boundary Document as one of the attachments

    of the Transmission Service Agreement.

    The document will precisely show the Connection Point and shall specify the following:

    a. Equipment and ownership

    b. Accountable Managers

    c. Safety Rules and procedures during Local Safety Instruction and the Safety

    Coordination of any other persons for safety

    d. Operational procedures and the responsible party for operation and control

    e. Maintenance agreement and the responsible party for undertaking the

    maintenance

    f. Any agreement pertaining to emergency situation

    5.0 Receiving Substation Facility Requirements

    The existing Bacolod Substation 69kV switchyard will be maintained as is. The

    “tapped” connection will not require modifications at the switchyard. Only

    communication facility via optical groundwire will be installed at this substation.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    14/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    14 | P a g e  

    5.1.1 General Technical Requirements

    The electrical equipment shall be designed in such a way as to bear without

    damage and permanent deformation the consequences of over voltage of internal

    or atmospheric origin and each electrical component can withstand the maximum

    stresses under fault conditions. 

    Outdoor installations shall be protected against solar radiation by means of

    adequate covers, where required, with non-deteriorating material.

     All equipment shall be designed to be insensitive to any signals emitted by wireless

    communication equipment.

     All metallic frames shall be securely connected to the general earthing system in

    compliance with accepted standards.

    The center line spacing and clearances above ground level of the conductors

    shall be as shown in the detailed design drawings.

    The minimum clearance between live metal parts and ground shall be 837.5 mm.

    while, the minimum clearance between live metal parts of two phases shall be 1500

    mm. The practical distance between phase center lines shall be 1500 mm. and the

    minimum height of live conductors above ground shall be 3000 mm, however, the

    upper edge of an earthed insulator support shall have a height of, at least, 2300 mm.

    above the ground level.

    Creepage distance of equipment bushing, insulator strings, station post insulators

    and rigid support insulators shall be equal or greater than the resultant of the 21mm/KV multiplied by the maximum nominal voltage. Outdoor equipment shall

    be painted with RAL 7035 color, while indoor equipment (including inside cubicle)

    shall be painted with RAL 7032 color.

    Phase indication plates with color and code letters, which shall be luminous

    and made of weather resistant materials, shall be provided on the substation steel

    structures to indicate the phases of bus, incoming lines and transformer feeders

    and shall be as follows: Phase A is Red and code is “A”; Phase B is Yellow and

    code is “B”; and Phase C is Blue and code is “C”. 

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    15/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    15 | P a g e  

    Outdoor and indoor equipment and panels shall be labeled in accordance with the

    Site and Equipment Identification and Labeling (SElL) standard of NGCP as

    mandated by the Grid Code. NGCP, therefore, must provide guidance to

    the developer on the appropriate nomenclature of the major devices

    interphasing with NGCP’s System Operation. 

    5.1.2 Codes and Standards

     All engineering, fabrication, construction/erection, startup and testing provided

    by the Contractor shall be in accordance with applicable codes and standards,

    regulations and guides. The applicable codes, standards and regulations will

    consist of the substation requirements as the basis, and also include those for the

    Contractor's nation as follows:

    1) Philippine Standards and Codes

    2) United States Standards and Codes (IEEE/ANSI/NEMA/NFPA etc.) 

    3) International Electro-technical Commission (IEC) 

    4) DIN (German) 

    5) BS (British standard) 

    6) JIS (Japanese Industrial Standard) 

    7) CNS (China National Standard)

    5.2 Power Transformer

    The Power Transformer i s rated 50/65 MVA (ONAN/ONAF), 13.2/69 kV,

    60Hz, and capable of changing its tap ratio by+/- ten percent (10%), with

    a step size of 1.25%. The HV bushings of the Power Transformer shall be

    of the resin paper impregnated and non-draw lead type.  Aside from the

    insulation, polarization index, oil dielectric, polarity and ratio tests that are

    required by NGCP to be conducted on the power transformer prior to

    connection, other routine tests specified under the applicable ANSI/IEEE

    standard and the manufacturer's standard test regime shall also be

    conducted on the power transformer . 

    The cooling medium shall be oil and its temperature of cooling air shall not

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    16/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    16 | P a g e  

    exceed 40ºC. Cooler shall be transformer mounted and should be radiator fin

    type. Monitoring and control system shall be interfaced at the Substation

    Control System.

    Transformer shall be equipped with On-load Tap Changer (OLTC) and should

    be oil-immersed. Taps shall be ±0.625% by 8 taps. The motor of the OLTC

    shall be sourced by 400 VAC, 3-phase at 60 Hz.

    5.3 Power Circuit Breaker

    The power circuit breakers (PCB) shall be of the SF6 and outdoor type. It

    shall be rated at least 69 kV, 60 Hz, with continuous current rating at 60

    Hz of at least 2000A rms, with interrupting time of no longer than 50 ms.

    and shall be capable of interrupting successfully its rated interrupting current

    of at least 4 0 kA rms, for its entire operational life. It shall be capable of

    withstanding all system lightning impulse and switching over voltages

    less than or equal to its Basic Impulse Level (BIL) or switching surge

    withstand capability. Generally, the PCB shall meet or exceed all rated

    values listed in applicable ANSI or IEC standards. The PCB shall bedesigned to have the capability of permitting, at least, two complete

    closing-opening operations and to withstand swells caused by ground faults.

    Each PCB shall be equipped with an operation counter.

    Multiple-pole or single-pole tripping devices shall be protected against

    accidental operation and conveniently located for manual tripping or local

    operation of the PCB. The tripping mechanism shall have two (2) electrically

    independent trip coils (circuits) per pole. 

    PCBs capable of single-pole actuation shall be provided with a phase

    discrepancy monitoring and control system for synchronized closing and

    opening operation of individual poles. 

    The PCB shall be capable of switching out line faults (regardless of the

    distance between the circuit breakers and faults), no-load lines, 

    transformers on no-load and reactive loads without causing re-striking when

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    17/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    17 | P a g e  

    switching. 

    The PCB shall be equipped with enough auxiliary contacts to

    accommodate the required status and alarm indications, plus additional

    convertible eight (8) types A and B contacts each. The operating status

    and other parameters of the PCB shall be monitored/interfaced with the

    Substation Automation System (SACS). 

    The technical data sheets of the PCB are shown in subsequent Annex.

    5.4 Disconnect and Earthing Swtich

    Disconnect Switches (DS) shall be provided and arranged so as to isolate

    the PCB during maitneannce. The switching device shall be station class,

    outdoor, 3phase, two column horizontal center break type and rated 60 Hz,

    69 kV, 2000 A rms and have a short-time withstand capability of at least

    44 kA rms.

    The switching device shall be three pole construction, horizontal mode of

    contact separation with reference to the mounting plane, and equipped with

    an earthing switch. 

    The switching device shall withstand and operate without malfunction with

    simultaneously acting forces from connection at terminals and short circuit.

    The safety factor against break of an insulator shall be at least 1.25 times

    the simultaneously acting forces plus operating forces.

    The DS shall have the capability of being either motor-operated or manual

    through remote, local or manual mode.

    The DS shall be equipped with enough auxiliary contacts to accommodate

    the required status and alarm indications, plus additional convertible eight

    (8) types A and B contacts each. 

    The operating status of the DS shall be monitored/interfaced with the

    SACS, whenever applicable. It shall be equipped with key interlocks,

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    18/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    18 | P a g e  

    position indicator (both mechanical and light) and damping device. 

    The switching device shall be electrically interlocked with the associated

    circuit breaker to prevent the possibility of making or breaking load current. 

    To prevent maloperation, the operating mechanism of disconnect

    switches and earthing switches shall be interlocked relative to each other

    such that when the main disconnect switch is in "closed" position, the

    earthing switch cannot be closed and vice versa. Said interlocking

    arrangements shall be effective both in local and in remote operation.

    The technical data sheets of the Disconnect/Earthing Switch can be seen

    in the Annexes. 

    5.5 Current Transformer (for statistical meter and protection purposes)

    Current Transformers (CT) shall be provided for all PCBs. The CTs shall

    be single pole. For outdoor installations,  the CT's insulation medium shall

    be oil. While, for indoor installations, the CT's insulation medium shall be

    SF6 gas. 

    Current Transformers shall be rated at 69 kV, 60Hz. Its current ratio (with

    secondary taps) shall be 2 0 00/1500/1000/500:5A. The CTs shall have 4

    cores (i.e., 1 core for metering with accuracy class of 0.2 and 3 cores

    for relaying with 5P20 accuracy class) per IEC standards. Rated burden

    is 30 VA for metering and 100 VA for protection.

    The short-time current thermal rating of the CTs shall be at least 4 0 kA

    rms while the rated short-time mechanical is 100 KA rms. The cores shall be

    designed and built in such a way that no reciprocal electromagnetic

    influence or influence from external fields can occur . 

    The CT shall have adequate output to meet double the total burden

    of the equipment connected to it. It shall also have sufficient thermal,

    voltage, over-current performance, internal resistance and accuracy for

    the satisfactory operation of the equipment connected to its secondary

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    19/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    19 | P a g e  

    circuit. CT shall withstand the mechanical and thermal stresses caused by

    short circuits.

    CTs provided for protective purposes shall have over current and saturation

    factors not less than those corresponding to the design short circuit level of

    the system. 

    The technical data sheets of the CT (not for billing purposes) are shown in the

     Annexes. 

    5.6 Potential Device

    PT shall be of the inductive type, with a marked ratio of 600/345:1 and its

    rated secondary voltage shall be 115 VL _J66 .4  VL-G·  It shall be of the

    accuracy IEC Class 0.3. The burden rating shall be at least 12.5 VA which

    can handle the total burden of the cables and all connected devices at the

    PT/VT secondary circuit. It shall have three (3) secondary cores/windings,

    both, preferably of metering class accuracy. It shall be tested and certified on

    ratio accuracy, phase deviation and insulation integrity.

    For its rated insulation, the lightning impulse withstand voltage is 350 KV peak

    while power frequency withstand voltage is 140 KV rms dry.

    The technical data sheets of the Voltage Transformer can be seen in Annex

    M, while the test reports of the VTs are shown in the Annexes.

    5.7 Surge Arrester

    Each arrester shall be station class, outdoor type, metal oxide (i.e., ZnO)

    and gapless type with surge counter. Material of insulator can be composite

    type.

    The surge arrester at the high voltage (69 kV) side shall be rated for

    nominal system voltage of 69 kV, while that of the low voltage side shall

    be 13.2 kV. The arrester shall be rated 60 Hz, and its Duty Cycle Voltage

    rating shall be 60 kV rms, nominal discharge current of 10 kA and the

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    20/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    2 | P a g e  

    Lightning Impulse Withstand Voltage capability of its post insulator

    housing, for outdoor installations, shall be 325 kV.

    The arrester assembly shall consist of an arrester unit, line terminal,

    earth terminal, insulating base, cyclometer type discharge counter with

    integral continuous AC leakage/internal current indicator. Outdoor

    installations shall have a supporting structure. 

    Remote indication of discharge counter registers shall be provided and

    interfaced with the SACS, if applicable.

    The arrester housing shall have either a hollow insulator with gas filling

    (tube design) or directly molded housing material on the MO-blocks caged

    by FRP rods ("caged design"). Insulator material shall be either porcelain or

    silicon rubber.

    The unit shall be hermetically sealed, moisture free. For hollow insulators

    (tube design), a pressure relief device is required to limit the internal

    pressure so as to prevent explosion or violent shattering of the housing

    during short circuit current conditions. For outdoor installations, the arresters

    shall be vertically mounted on a horizontal surface.

    For outdoor installations, each arrester shall be furnished complete with a

    non-corroding clamp type ground connector suitable for copper stranded

    conductor. The arrester supporting structure shall be provided with a

    grounding pad. Each grounding pad shall be flat and shall be provided with

    a non-corroding clamp type connector suitable for, at least, 100 sq.mm. sizedannealed, stranded PVC insulated copper ground conductor. The grounding

    pad shall be located about 400 mm above finished ground level.

    5.8 Substation Automation Control System 

    The Substation may be equipped with a microprocessor-based Substation

     Automation Control System (SACS) to perform control and monitoring

    tasks for all the major and critical equipment in the substation. The SACS

    consists of the operator workstations, data highway, process controllers,

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    21/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    21 | P a g e  

    engineering workstation, servers, gateways, GPS Time, and all necessary

    peripherals. The SACS shall be equipped with at least three (3) data

    communication ports to satisfy NGCP Supervisory Control and Data

     Acquisition (SCADA) requirements. In the event that the substation is not

    equipped with a SACS or the number of data communication ports of the

    SACS be insufficient to satisfy the SCADA requirement, a Remote Terminal

    Unit (RTU), with, at least, three (3) data communication ports shall be

    provided by NGCP and shall be connected to the DNP 3.0-configured data

    communication port of the SACS,  if applicable. Said three (3) data

    communication ports shall use the DNP 3.0 data communication

    protocol to communicate with the Back-up NationaV Regional Control Center

    (BNIRCC) in Cebu; the Back-up Regional Control Center (BRCC) in Mandaue,

    also in Cebu; and, the Area Control Center (ACC) in Iloilo.

    The SACSIRTU shall be equipped with sufficient digital and analog inputs

    and control outputs to monitor and control all necessary parameters of the

    various plant and substation equipment, with enough spare input, output and

    control modules.

    The SACSIRTU shall display, aside from the important substation diagrams

    and parameters, the single-line diagram of the major substation equipment,

    including the out-going lines, together with their identification names

    conforming to NGCP's Site and Equipment Identification and Labeling (SElL)

    Standard.

    The SACS/RTU shall monitor and communicate the following substation

    equipment parameters to the above said NGCP Control Centers: 

    1) Each Power

    Transformer

    •  MW 

    •  MVAR

    •  MVA

    •  Current, A (each phase)

    •  Voltage, kV (each phase)

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    22/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    22 | P a g e  

    •  Pressure Relief Alarm

    •  Transformer Differential Relay Alarm

    •  Buchholz Relay Alarm

    •  Overcurrent Relay Alarm

    •  High Winding Temperature Alarm

    •  Lock-out Alarm

    2) Each High Voltage Bus

      Voltage

      Frequency

      Bus differential relay alaRm

    3) Power Circuit beaker  Status (open, close)

      Spring charge alarm

      BFR alarm

      Auto-reclaose Operation

      Open/Close Control Operation

    6.0 Transmission Line

    6.1 Steel Structure

    The structures are made from concrete and designed for 69 kV. The structures are

    designed for outdoor, tropical, salt and dust laden and heavily contaminated

    atmospheric conditions.

    The structures are designed to consider the weight of porcelain insulator strings and

    the length of composite insulator strings so that in any maintenance work requiring

    replacement of insulator string assembly, both types of insulator assembly can

    be used without any restrictions 

    6.2 Conductor

    The conductors to be used at the high voltage (69 kV) shall be 336.4 MCM

     ACSR (Linnet), while the line hardware to be used shall be appropriate for said size

    of cable.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    23/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    23 | P a g e  

    The conductor and wire data are as follows:

    Particular Data

    Size and type  ACSR/AS 336.4 MCMC “Linnet” Stranding 26/7Outside diameter 18.26mm Area 198.21 sq.mm.Weight 0.6553 kg/mBreaking strength 6,110 kgs.

    6.3 Optical Pilot Ground Wire

    The Optical Pilot Ground Wire (OPGW) shall be 1550 nm, single-mode, 36-core fiber based on ITU-T G.652D.

    6.4 Conductor Clearances

    The Philippine Electrical Code Part II sets safety clearances from ground,

    structure and vegetation. Values below are the minimum vertical clearances:

    Crossing over at 50ºC no wind final sag Clearance in meterTrack rails of railroad 11.5Public streets and highways 10Rural roads 8.5

    Cultivated fields, area accessible only topedestrian along roads in rural areas

    7.5

     All other types of obstruction Refer to PEC Part II

    6.5 Pole Design Criteria

      Footing resistance is ≤10 ohms 

      Design wind velocity is 270 kph

      Wind pressure on poles will be in accordance with NESC Rule 252B2

      Wind pressure on wires will be in accordance with NESC Rule 250C

    6.6 Pole Setting

    Pole will be direct buried and below will be followed:

    Pole height (in feet) Depth of setting (in feet)On rock On Earth

    50 4.5 6.555 5.0 7.0

    60 5.5 7.565 6.0 8.0

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    24/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    24 | P a g e  

    70 6.5 8.5

    6.7 Insulator

    Porcelain or polymer insulator can be used: suspension or post type. For

    porcelain appropriate mechanical and electrical rating shall be used. For the

    polymer insulator, appropriate specified mechanical load and routine tests load

    rating shall be used.

    Electrical Parameters:

      Nominal system voltage – 69 KV rms

      Maximum system line-to-ground voltage – 41.8 KV rms  Maximum peak line-to-ground voltage – 59.1 KV rms

    Leakage Distance Requirements

      Assumed ESDD – 0.01 – 0.04 mg/sq.mm.

      Pollution severity  –  medium (moderately polluted area to be

    considered)

      Leakage distance – 20mm/KV

    Impulse Overvoltage Requirements

      Assumed peak impulse current – 40 KA

      Pole footing resistance - ≤10 ohm 

      Impulse withstand – 400 KV

    6.8 Line Hardwares

     All line hardwares to be used shall be compatible with all the associated lien

    materials to be supplied.

    6.9 Pole Resistance

    Resistance measurement will be conducted to ensure that all poles to be built

    are properly grounded. Pole footing earth resistance shall not exceed 10 ohms

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    25/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    25 | P a g e  

    otherwise ground rods or counterpoise shall be installed to meet the required

    earth resistance.

    7.0 Take-off Substation

    The proposed power plant “take‐off” substation will located within NPSI-Felisa Solar

    Power facilities The following switchyard equipment not including generator ‐related

    facilities, will be installed at the substation:

    a. One (1) set of power transformer, 50/65MVA, 13.8/69kV

    b. One (1) set power circuit breakers, 69 kV, 40 kA

    c. Two (2) sets disconnect switches, 69 kV, 2000A

    d. One (1) set current transformer, 69 kV, 2000:5A

    e. One (1) set voltage transformer, 69 kV, 350/600:1

    f. Two (2) sets surge arrester, 60 kV

    The tapping connection shall be installed with Disconnect Switch and Line Fault

    Indicator as shown in earlier drawings (Figure No. 5).

    Excluding generator ‐related equipment, the following auxiliary power system facilities

    will be installed at the control building:

    a. 400/230 Vdc Distribution Board

    b. 125 Vdc Battery, Charger, and Distribution System

    c. 48 Vdc Battery, Charger, and Distribution System

    d. 240 Vac UPS System

    Switchyard conductors to be used shall be 850 mm2 THAL. OHGW shall be 7/8

     Aluminum Clad.

    Below is the indicative layout of the substation

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    26/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    26 | P a g e  

    Figure 6: Illustrations of Plan and Layout

    Naming conventions of all equipment will follow the GMC’s mandated use of Standard

    Equipment Identification and Labelling (SEIL). The proponent shall follow the

    prescribed naming to be suggested by NGCP.

    8.0 Protection, Control and Monitoring Requirement

    Protection relay, control and monitoring equipment should be provided for the “take ‐

    off” substation and the new transmission line. These protection schemes were

    designed consistent with the requirements of NGCP’s Network Protection Philosophy.

    For the “take‐off” substation, the following protection, control, monitoring and

    communication equipment should be provided:

    a. Protection Main1 and Main 2

    b. Transformer Protection Main 1

    c. Network Disturbance Monitoring Equipment

    d. Control Switchboard

    e. Fiber Optic Terminal Equipment

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    27/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    27 | P a g e  

    Protection equipment at Bacolod Substation will be as‐is.

    Communication between the receiving and the “take‐off” substations to provide for

    exchange of remote control signal, alarm status, metering data, relay communications

    requirements, and voice link shall be implemented through OPGW.

    Metering CT and PT will be provided by the Project Proponent while revenue meters

    may be supplied by NGCP as metering service provider and will be installed at the

    “take‐off” substation. 

    Technical Data sheet are provided in the Annexes.

    9.0 Communication and SCADA Requirements

    Section 4.6.1 Communication System for Monitoring and Control of Chapter 4 Grid

    Connection Requirements, a communication system shall be established so that Grid

    Owner, the System Operator and the Users can communicate with one another as

    well as exchange data signals for monitoring and controlling the Grid during normal

    and emergency condition. On the other hand, Section 4.6.2 SCADA System for

    Monitoring and Control, the Grid Owner shall provide a Remote Terminal Unit (RTU)

    for interconnection of the System Operator's Control Center to serve as telemetry

    equipment for monitoring real time information and controlling the Equipment at

    the User System.

    The Communication and SCADA shall be provided to communicate the proposed

    50 MW solar project is described in the succeeding article.  

    Technical Data sheet are provided in the Annexes.

    10.0 Revenue Metering

    NPHSI has not decided on what metering agreement it will enter with NGCP.

    Nevertheless, NPHSI will be guided with the following NGCP standards for the

    Revenue Metering as described in succeeding paragraph.

    In accordance with Section 8.2.1 Metering Equipment of Chapter 8 of PGC, the

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    28/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    28 | P a g e  

    Metering E quipment at the Connection point shall consist of : 

    a. Instrument Transformers; 

    b. Lightning Protections;

    c. Revenue Class Meters; 

    d. Integrating pulse recorder(s) and time source;

    e. All interconnecting wires and associated devices;

    f. Data communication devices; and

    g. Mounting structures and ground wires for instrument transformers 

    The technical requirements and the e quipment specifications shall be in

    accordance with NGCP's Standard Specifications as described below:

    “ A. MINIMUM TECHNICAL REQUIREMENTS FOR THE GRID METERING

    FACILITIES:

    1. Blondel's Theorem Compliance. The metering circuit for a 3-phase

    4- wire Y connection of the Customer circuit, shall be 3-Eiement.

    For a 3- Phase 3-Wire Delta connection, the metering circuit shall be

    Delta connected 2 Element.

    For the 3-Eiement, 4-Wire Y metering circuit, the Neutral Point of the

    Potential and Current Transformer Secondaries are to be grounded

    at a single point to the system ground mat through the grounding

    connection at the meter enclosure.

    2. Exclusive Use of Instrument Transformers for Revenue Metering.

    To safeguard the security of the metering facility, and to prevent the

    simultaneous loss of metering and other functions in case of

    instrument transformer failure, the Potential and Current Transformers

    shall be exclusively used for revenue metering. The use of the

    instrument transformers for both revenue metering applications

    and substation protection is not allowed, even with separate

    cores/windings.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    29/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    29 | P a g e  

    3. Voltage or Potential Transformers (VT or PT)

    a. Type: Inductive type

    b. Secondary Voltage: 115VAC for 34KV and above, 120VAC

    for lower voltages

    c. Accuracy Class: ANSI Class 0.3/IEC Class 0.2 or better

    d. Burden Rating: Must be at least 100% higher than the total

    burden of the cables and all connected devices at the PT

    secondary circuit.

    e. Secondary Cores/Windings: Preferably 2, both of which are

    metering class

    f. Factory Test Report(s): Test Reports of Ratio Accuracy,

    Phase Deviation, and Insulation Integrity

    4. Current Transformers (CT) 

    a. Type: Inductive-type

    b. Secondary Current: 0-5A

    c Primary Current Range: 1.25 - 1.5 x the expected Full Load

    Current. For a CT with multiple ratios, the change of tapping

    shall be at the secondary side.

    d. Accuracy Class: For Loads: ANSI Class 0.3/IEC Class 0.2 or

    Better

    For Generators: ANSI Class 0.15/IEC Class 0.2s or Better

    e. Burden Rating: Must be at least 100% higher than the total

    burden of the cables and all connected devices at the CT

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    30/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    3 | P a g e  

    secondary circuit.

    f. Secondary Cores/Windings: Preferably 2, both of which are

    metering class

    g. Factory Test Report(s): Test Reports of Ratio Accuracy,

    Phase Deviation, and Insulation Integrity. For multiple-ratio

    CT's, they shall be factory-tested for accuracy and phase

    deviation at all current ratios.

    5. Lightning/Surge Arresters. Lightning/surge arresters ofappropriate electrical ratings for the application shall be installed at

    the line side of the instrument transformers.

    6. Metal Meter Security Enclosure.  A steel or aluminum security

    enclosure for the main and alternate meter which can be secured by

    padlocks and security seals shall be provided. The enclosure shall be

    provided with a glass viewing window for visual observation/reading

    of meter registers.

    7. Instrument Transformer Secondary Cables. The cables shall be

    stranded and with a minimum size of No.12 AWG, and whose

    resistance shall not cause the burden of the metering circuit to

    exceed 50% of the rated burden of the instrument transformers at

    a maximum length of 15 meters from the instrument transformer

    secondary terminal to the metal enclosure.

     All Instrument Transformer Secondariesare to be cabled through

    the Meter Enclosure, including unused instrument transformer

    secondaries.

    8. Rigid Steel Conduits for Instrument Transformer Secondaries,

    routed directly to the Meter Security Enclosure without any marshalling

    box or conduit openings. Only metering circuit cables must be

    contained in the conduits.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    31/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    31 | P a g e  

    9. Copper Grounding Cable. Cable size is 4/0 Minimum for

    connecting the Instrument Transformer housings, grounded

    secondaries and the Meter Enclosure to the Substation Ground Mat.

    10. Billing Meter(s). The revenue-class meter(s) shall conform with

    functional requirements and specifications prescribed under the

    Philippine Grid Code and the WESM Metering Manual.

    11. Meter Test Block. A 10-pole switch assembly where the instrument

    transformer secondary cables terminate and where the meter is

    connected for the purpose of isolating the meter from service and

    providing a means of injecting test currents and voltages into the meter

    when the meter is to undergo accuracy tests.

    11.0 Project Bill of Materials

    Below is the preliminary requirements of primary devices and accessories at Felisa:

    NPSI-Felisa Solar Take-off S/S

    ITEMNO.

    DESCRIPTIONQUANTIT

     YUNIT

     A. HV SWITCHYARD EQUIPMENT

    1

    GENERATOR STEP-UP TRANSFORMER, 13.8/69kV,50/65MVA, 3f, ONAN/ONAF, complete with oil, allappurtenances, accessories, on-load tap changingmechanism,and other required accessories, supportingstructures, anchor bolts, foundations, etc. 

    1 set

    2

    POWER CIRCUIT BREAKER, 69kV, 40kA, 2000A, livetank type, suitable for 3 pole operation, complete with allthe required accessories, supporting structures, anchorbolts, foundations, etc. 

    1 set

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    32/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    32 | P a g e  

    3DISCONNECT SWICTH, 69kV, 40kA, 2000A, withoutEarthing Switch, pedestal mounted, complete with all therequired accessories, anchor bolts, foundations, etc.

    2 sets

    4

    CURRENT TRANSFORMER, 69kV, 4-core with 1metering (Cl 0.2 30VA) and 3 relaying (5P20 100VA),multi-ratio (2000/1500/1000/800/500:5) complete with allthe required accessories, supporting structures, anchorbolts, foundations, etc.

    3 each

    5

    VOLTAGE TRANSFORMER, 69kV, 600/350:1, inductivetype, two secondary winding, 20VA, complete with all therequired accessories, supporting structures, anchor bolts,foundations, etc.

    3 each

    6

    SURGE ARRESTER,  60kV, Metal Oxide, gapless,

    complete with all the required accessories, supportingstructures, anchor bolts, foundations, etc. 6 each

    7

    COMBINED CT/VT, 69kV, for billing, CT: 2 metering core(Cl 0.2S 20VA) 300/150:5 and PT: two secondary winding(Cl 0.2 50VA) 350:1, complete with all the requiredaccessories, supporting structures, anchor bolts,foundations, etc.

    3 each

    8

    SUBSTATION STEEL STRUCTURES for 69kV  hot-dipped galvanized complete with mounting bolts andaccessories in accordance with the technical data sheetsand drawings 

    1 lot

    9

    STATION INSULATORS for 69kV, string and post (bussupport), complete with all the required accessories,protection against electrolytic corrosion, grading shields,etc.in accordance with the technical data sheets anddrawings 

    1 lot

    10

    BUS CONDUCTOR AND HARDWARE  for 69kVconsisting of conductors, hardwares, connectors, fittings,clamps, etc. in accordance with the technical data sheetsand drawings 

    1 lot

    11STATION SERVICE TRANSFORMER, 3-phase,complete with all the required accessories, anchor bolts,foundations, etc. in accordance with the drawings. 

    a. 75kVA, 13.8kV/400V complete with fuse cutout andlightning arrester

    1 set

    b. 75kVA, 13.2kV/400V complete with fuse cutout andlightning arrester

    1 set

    12AUXILIARY POWER SUPPLY SYSTEM, complete withall the required accessories, intruments, relays, etc. inaccordance with the drawings. 

    a. 400/230 VAC Auxiliary Board 1 lot

    b. 125 VDC Auxiliary Board 1 lot

    c. 48 VDC Auxiliary Board 1 lot

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    33/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    33 | P a g e  

    13STORAGE BATTERIES,  complete with all the requiredaccessories, support rack, etc. in accordance with thetechnical data sheets and drawings 

    a. 125 VDC Battery Bank 2 sets

    b. 48 VDC Battery Bank 2 sets

    14

    BATTERY CHARGER/RECTIFIER,  125 and 48VDC,complete with all the required accessories, intruments,relays, etc. in accordance with the technical data sheetsand drawings 

    a. 125 VDC Battery Charger/Rectifier 2 sets

    b. 48 VDC Battery Charger/Rectifier 2 sets

    15UPS POWER SUPPLY SYSTEM, complete with all therequired accessories, intruments, relays, etc. inaccordance with the technical data sheets and drawings 

    1 set

    16DIESEL GENERATOR SET, 60 kW, 400V, 0.8 p.f., 60Hz,complete with all the required accessories, intruments,relays, etc.

    1 set

    17CABLES, provided with filler and binder tapes,termination kits and accessories, etc. in accordance withthe requirements of the technical data sheets. 

    1 lot

    a. XLPE Power Cable, 15kV Insulation 1 lot

    b. Power Cable, 600 V Insulation 1 lot

    c. Control and instrumentation Cable, 600V Insulation,shielded 1 lot

    18CONDUITS AND CABLE TRAY SYSTEM, various sizes,including, supports, fittings and accessories inaccordance with the technical data sheets and drawings

    1 lot

    19

    GROUNDING SYSTEM for the Substation includingOHGW, air terminals, connectors, fittings, hard-drawncopper conductors, ground rods, mold, powder forexothermic connections, molds, flint guns, etc.inaccordance with the technical data sheets and drawings 

    1 lot

    20

    LIGHTING SYSTEM, complete with lighting fixtures,lamps, lamp posts with ground terminals includingfoundation if required, conductor, conduits, switches,boxes, etc., for the switchyard, roadways, perimeter andcontrol building and other indoor establishmentinaccordance with the technical data sheets and drawings 

    1 lot

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    34/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    34 | P a g e  

    21

    CONTROL BUILDING, complete design andconstruction of single-storey building. Reinforcedconcrete/steel structure and pre-painted long spanroofing, roof slab canopy complete with the requiredarchitectural/civil/structural/sanitary/electrical/mechanical to complete to complete the scopeof works for the building in accordance with drawings 

    1 lot

    The transmission connection asset is:

    TRANSMISSION LINE

    ITEMNO. DESCRIPTION QUANTIT Y UNIT

     A. 69kV TRANSMISSION LINE

    1

    TRANSMISSION LINE comprising of steel poles, poledressing, guying and supports, conductors, insulatorfrom the take-off substation to the designated tappingpoint including reconfiguration of existing NGCP Pole(designated tapping point)

    1 km.

    2LOAD BREAK SWITCH, 630A, 20kA, 69kV, completewith all the required mounting accessories 

    2 sets

    The secondary devices are summarized as follows:

    NPSI-Felisa Solar Take-Off S/S

    ITEMNO.

    DESCRIPTIONQUANTIT

     YUNIT

     A. SUBSTATION PROTECTION SYSTEM

    113.8/69kV Transformer Protection System, numerical,transformer differential protection

    1 set

    B. LINE PROTECTION SYSTEM

    169kV Line Protection System (Main 1 - line distanceprotection)

    1 set

    269kV Line Protection System (Main 2 - directionalphase and ground overcurrent protection)

    1 set

    C. SUBSTATION MONITORING SYSTEM

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    35/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    35 | P a g e  

    1

    Network Disturbance Monitoring Equipment fullycompatible with NGCP Master Station complete withaccessories and necessary interface devices (DI: 96 & AI: 32)

    1 lot

    D. SUBSTATION CONTROL SYSTEM

    1Main Control Switchboard complete with mimicdiagram, meters etc.

    1 lot

    2Remote Terminal Unit complete with interfaceequipment, I/O modules, etc.

    1 lot

    E. FIBER OPTIC COMMUNICATION SYSTEM

    1

    Fiber Optic Terminal Equipment, complete with opticaldistribution frame (ODF), access multiplexers,indicators, pigtails, patchcords and otherappurtenances

    1 lot

    2Fiber Optic Approach Cable, 36 fibers, 1550nm, singlemode

    1 lot

    No consideration yet on the civil works and additional electrical works that may only

    be determined during the detailed engineering design. Variation works may be

    expected depending on actual site conditions.

    12.0 Project Cost and Assumptions

     Assumption in deriving the project cost is based on accuracy of ±10% and already

    considered the applicable taxes and contingencies equivalent to same assumptions.

     Applicable taxes already considered the applicability of RA 9513 to the proponent.

     Acquisition of right-of-way of the line and site, for purposes of this facilities study, are

    already excluded including the engineering activities. Interest during construction is

    likewise considered for purposes of this interconnection study.

    Exchange rates considered is 1US$ to PhP 45.

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    36/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    36 | P a g e  

    For NGCP substation, considering that the existing facilities (Bacolod-San Enrique)

    will be used as the interconnection facility, it is assumed that there will be no primary

    devices upgrading at the side of NGCP’s substation 

    13.0 Recommendation

    The interconnection scheme (configuration and the line), its associated primary

    devices and secondary devices (protection arrangement, telecommunication and

    SCADA) and metering are presented based on initial assessment and analysis.

    However, there are still needed coordination with NGCP as Grid Owner, System

    Operator and Wholesale Metering Service Provider on the following:

    1. Submission of major equipment and specifications related to interconnection to

    conform with the requirements of NGCP. This does not cover however the plant’s

    equipment and specifications including the transformers related to the conversion

    from DC to AC and stepping-up to the voltage agreed upon with NGCP;

    2. Electrical diagrams and drawings covering the grid assets (i.e., SCADA and

    Telecom equipment) shall be approved by NGCP;

    3. Procurement of brand acceptable to NGCP will be pursued particularly the

    protective equipment;

    4. The secondary devices (i.e., SCADA and Telecom equipment) which are all grid

    assets per Grid Code will be funded but manufacturer’s drawings shall be approved

    by NGCP;

    5. Protection equipment shall be provided, owned, operated and maintained by

    NGCP and NPHSI at their respective sides but the latter may consider of engaging

    the maintenance services of NGCP;

    6. Protection setting shall be consistent with the prescribed settings of NGCP to

    coordinate with its current protection scheme; and

  • 8/17/2019 0 NPSI-Felisa Solar FS Write-up

    37/37

    Interconnection Facilities Study

    For Felisa 50 MW Solar Power Plant Negros PH Solar Inc. 

    7. NPHSI shall coordinate closely with NGCP for the commissioning and testing of

    the solar plants following NGCP’s Open Access Policy, Grid Code, OATS Rules

    and ERC Resolution No. 7-2014 on the testing of VRE as outline below, the PGC

    Minimum Requirements for Large PVS (>20MW):

    Specific Requirements Large PVS Field Test LaboratoryTest

    Certification

    2.1 Generating unitpower output

       

    2.2 Frequency withstand

    capability

       

    2.3 Reactive Powercapability

       

    2.4 Performance duringnetwork disturbances

         

    2.5 Voltage Controlsystem

       

    2.6 Active Power Controlsystem

       

    2.7 Power Quality    4.1 Information

    Exchange/SCADA Test