26 Aug 2010: Progress Meeting. 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings. Agenda. Introductions By-Task Progress Problems Miscellaneous Lab Visit. Introductions. Researchers: Project Management Committee: Visitors:. Project Background. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/1.jpg)
26 Aug 2010: Progress Meeting
0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream
Crossings
![Page 2: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/2.jpg)
Agenda
• Introductions
• By-Task Progress
• Problems
• Miscellaneous
• Lab Visit
![Page 3: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/3.jpg)
Introductions• Researchers:
• Project Management Committee:
• Visitors:
![Page 4: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/4.jpg)
Project Background
• Develop knowledge to address the issue of solids accommodation in Texas Department of Transportation low-water crossing structures (not bridges).
• To develop design guidelines to assist in building multiple barrel systems that mimic the necessary stream behavior to facilitate solids migration.
![Page 5: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/5.jpg)
Progress by Tasks
• Brief by-task report.– Task 1: Literature Review– Task 2: Screening Tools– Task 3: Quantitative Modeling– Task 4: Data Analysis– Task 5: Reporting
![Page 6: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/6.jpg)
Task 1: Literature Review
• TM1 submitted.– Copies on server
• Database(s) assembled.– QA/QC complete, still finding
inconsistencies, but small fraction of the database.
![Page 7: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/7.jpg)
Task 2: Screening tool(s).
• Database dependent– QA/QC on-going as just reported– Tools in-progress to allow database use.
![Page 8: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/8.jpg)
Task 3: Quantitative modeling.
• Laboratory system functional.– Have solids in-place and will demonstrate
today.– Have USGS provided satellite uplink to
capture measurements.– Most instruments are ready– Camera lens choices and other methods
still in-progress before begin production experiments.
![Page 9: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/9.jpg)
Task 4: Data Analysis.
• 2-D/2-phase computer program (UH researchers) to guide experiments.
• MIKE-3D CFD computer program (TTU) to extrapolate to larger scales.
• CAP-R (Culvert Analysis Program – R) to provide design and performance guidance.
http://waterdata.usgs.gov/tx/nwis/uv/?site_no=333509101470800&PARAmeter_cd=00065,00060,00062,72020,00054
![Page 10: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/10.jpg)
Task 5: Reporting.
• SAR due end of August
• Monthly reports on server; July 2010 should be there.
• TM1 submitted
![Page 11: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/11.jpg)
Problems Encountered
• Taking TTU longer to start experiments than anticipated.– Weir calibration
• Nuisance issues.– Leaks, computers failing, etc.
![Page 12: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/12.jpg)
Miscellaneous
• Anticipate some additional model building expenses first quarter FY11.
• Would like to visit some systems in FY11.
![Page 13: 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings](https://reader031.vdocuments.us/reader031/viewer/2022020716/568147cd550346895db50ad8/html5/thumbnails/13.jpg)
Laboratory Tour