^ newbrkf'bwer authority william j. cahill, jr. chief ...bases, revision 1, january 10, 1995,...
TRANSCRIPT
![Page 1: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/1.jpg)
0123 Main Street9White Plains, New York 100
914-681-6840914-287-3309 (FAX)
^ NewbrkF'bwer40 Authority
William J. Cahill, Jr.
Chief Nuclear Officer
March 3, 1995IPN-95-028
U. S. Nuclear Regulatory CommissionAttn: Document Control DeskMail Station P1 -137Washington, D. C. 20555
SUBJECT:
REFERENCES:
Indian Point 3 Nuclear Power PlantDocket No. 50-286Response to NRC Request for Additional Information RegardingProposed Emergency Action Levels (TAC M89887)
1. NRC letter, N. F. Conicella to W. J. Cahill, Jr. dated December16, 1994 regarding the same subject (DSR 288538).
2. NYPA letter, W. A. Josiger to USNRC (IPN-94-030/JPN-94087) dated July 12, 1994 regarding upgraded EmergencyAction Levels.
Dear Sir:
The Authority's response to the NRC staff's recent RAI (Request for AdditionalInformation, Reference 1) regarding upgraded Emergency Action Levels (EALs) for theIndian Point 3 Nuclear Power Plant is Attachment 1.
Also attached are four associated documents which have been revised to reflect theAuthority's response to the NRC staff's questions. Attachment I1is Revision 1 of theEALs. Attachment Ill is the EAL Technical Bases Report. Attachment IV is the FissionProduct Barrier Evaluation, and Attachment V is the Indian Point 3 specific EAL guideline(PEG). These documents supersede and replace those included with Reference 2.
The Authority plans to implement these upgraded EALs after the restart of IndianPoint 3, but not before May 31, 1995.
9503070258 950303PDR ADOCK 05000286F PDR
\V
![Page 2: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/2.jpg)
-2
No commitments are being made by the Authority in this submittal. If you haveany questions, please contact Ms. Charlene D. Faison.
Very truly yours,
Wiliam JCaill, Jr.Chief Nuclear Officer.Nuclear Generation
List of Attachments:
1. Indian Point 3 Emergency Action Levels, Response to Request for AdditionalInformation
11. Indian Point 3 Emergency Action Levels, Revision 1, Based on Proposed Responseto NRC RAls, January 10, 1995
Ill. New York EAL Upgrade Project, Indian Point 3 Emergency Action Levels, TechnicalBases, Revision 1, January 10, 1995, Operations Support Services, Inc.,OSSI-92-402A-4-1P3
IV. Fission Product Barrier Evaluation, Revision 1, New York Power Authority, IndianPoint Station Unit 3, January 10, 1995, OSSI 92-402A-2-1P3
V. EAL Upgrade Project, Plant Specific EAL Guideline, PEG, Indian Point Unit 3,Revision 1, January 10, 1995
cc: Next page
![Page 3: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/3.jpg)
cc: All with attachments.
Regional AdministratorU.S. Nuclear Regulatory Commission475 Allendale RoadKing of Prussia, PA 19406
Resident Inspector's OfficeIndian Point Unit 3U.S. Nuclear Regulatory CommissionP.O. Box 337Buchanan, NY 10511
Mr. Nicola F. Conicella, Project ManagerProject Directorate I-1Division of Reactor Projects I/IlU.S. Nuclear Regulatory CommissionMail Stop 14B32Washington, DC 20555
![Page 4: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/4.jpg)
RBC-D W/LTR MIDl 3/3/95... .9503070258
NOTICE
THE ATTACHED FILES ARE OFFICIALRECORDS OF THE INFORMATION &RECORDS MANAGEMENT BRANCH.THEY HAVE BEEN CHARGED TO YOUFOR A LIMITED TIME PERIOD ANDMUST BE RETURNED TO THERECORDS &ARCHIVES SERVICESSECTION, T5 C3. PLEASE DO NOTSEND DOCUMENTS CHARGED OUTTHROUGH THE MAIL. REMOVAL OFANY PAGE(S) FROM DOCUMENTFOR REPRODUCTION MUST BEREFERRED TO FILE PERSONNEL.
~- NOTICE 3 qi-2̂ .
![Page 5: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/5.jpg)
Attachment I to IPN-95-028
Indian Point 3Emergency Action Levels
Response to NRC Request for Additional Information
New York Power AuthorityDocket No. 50-286
![Page 6: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/6.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
GENERAL RAIs
Remponse to General RAI #1 (page 1)
As stated in the RAI, ICs are a subset of power plant conditions which represent a potential or actualradiological emergency. EALs are "a pre-deterined, site-specific, observable threshold for a plant ICthat places the plant in a given emergency class." When a site-specific, observable threshold (EAL) isreached, entry into its associated emergency class is required irrespective of the IC from which the EAL isderived. As stated in the RAI, ICs provide criteria that may be relevant to emergency classification basedon the users "judgment." Therefore, it follows that use of judgment may be required for those conditionsin which no "pre-determined, site-specific, observable threshold" can be defined.
Since ICs lack "site-specific, observable thresholds" for emergency classification, for those postulatedconditions in which no site specific observable threshold exists, the users judgment must be based on thegeneric definition of the associated emergency classification.
EAL Category 9.0 "Other" defines EALs in each emergency class which are based upon the user'sjudgment. Category 9.0 is used when the plant condition does not meet any of the EAL thresholds ofCategory 1.0 throughi Category 8.0 but it is determined that the plant condition meets either theemergency class definition criteria or the NUMARC/NESP-007 fission product barrier loss or potentialloss criteria. To address the concerns raised by the staff in this RAI. the bases document has been revisedto include each of the NUMARC/NESP-007 ICs. SDeCific reference to these ICs is now incornorated inthe iudgmnent EALs providing a mechanism for the user to determine how an EAL (or several diverseEALs) is related to the plant conditions of concern.
Response to General RAI #2 (vage 2)
Though not specifically stated, it is inferred that this RAI is in reference to EALs 5.2.3, 5.2.4 and 5.2.5.
For any actual or imminent release, dose projections performed in accordance with IP-lOOT, "Determiningthe Magnitude ofRelease", use of actual meteorology is specified. Therefore, implicit in the performanceOf any dose projection is the use of actual meteorology.
To address the staff s concern that classification based uvon these EALs be as the result of an "actual orimminent" release of gaseous radioactivity, the EALs have been revised to include the "Actual orImminent" terminology,
Response to General RAI #3 (naee 2)
[Par. 11NUMARC/NESP-007 does not require that the generic fission product barrier matrix be implemented on asite-specific basis. On September 22 -23, 1992 the Emergency Action Levels Implementation Workshopwas conducted by NUMARC. Specifically stated in presentations and in the workshop training materials(Section 3 page PF-39, page BF-30 and the PWR Fission Product Barrier Matrix Breakout Session GuideSection 7) attached, was the fact that the matrix format is not required. It only requires that compliancewith all combinations are documented. NUMARC/NESP-007 does not preclude the development ofEALsbased on an evaluation of fission product barrier loss/ potential loss conditions as part of the developmentprocess. The fission product barrier loss matrix as presented in NUMARC/NESP-007 was" chosen toclearly show the synergism among the EALs and support more accurate dynamic assessments." Further,NUMARC/NESP-007 states "The guidance presented here is not intended to be applied to plants as-is.
![Page 7: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/7.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
The EAL guidance is intended to give the logic for developing site-specific EALs using site-specific EALpresentation methods." The Fission Product Barrier Evaluation and the subsequent binning of the IP3fission product barrier based EAUs into categories was specifically performed to support the user's abilityto "dynamically assess how far present conditions are from escalating to the next higher emergency class."By defining logical event categories and subcategories in which to place these EALs, the ability to performa dynamic assessment is enhanced. The usability and correctness of the 1P3 method ofEAL presentationhas been demonstrated and documented in numerous dynamic simulator scenarios during EAL validationexercises.
The Fission Product Barrier Evaluation demonstrates that the 1P3 fission product barrier-based EALs aretechnically correct and meet the intent ofNUMARC/NESP-007. To address the stafrs concerns, thoseEALs which are derived from the Fission Product Barrier Evaluation have been annotated to indicate thefission Droduct barrier lossnotntial loss which they reoresent. In addition. the bases document has beenrevised to include the fission Droduct barrier lossgte~ntial loss indicators in a matrix format.
[Para. 21NUMARC/NESP-007 states "The presentation method shown for Fission Product Barriers was chosen toclearly show the synergism among the EALs and to support more accurate dynamic assessments." It doesnot 'state or imply that this method of presentation is necessary either to depict the synergism or to providethe ability for dynamic assessments. Rather, it is provided as a guide for the EAL writer to ensure that theselected presentation methodology properly reflects the desired synergistic quality and assessmentcapability. While NUMARC/NESP-007 does not define the term "dynamic assessment", it is assumedthat it means the ability to evaluate fission product barrier loss and potential loss indicators underevolving plant conditions. Unlike the NUMARC/NESP-007 matrix format, the 1P3 EAL presentationmethod places similar EALs into categories and subcategories that focus the user's attention to the specificEAL threshold that corresponds to the plant condition of concern. This provides a logical classificationand escalation path of related indicators and thus allows for rapid assessment of emergency conditionsassociated with fission product barrier loss. It is important to note that the 1P3 EAL categories andsubcategories are not simply representations or abbreviations of the NUMARC/NESP-007 ICs. Rather,each 1P3 category and associated subcategory is a pathway from broad indicators ofpotential emergencyevents to a set of specific threshold conditions that require emergency classification.
The EALs derived from the Fission Product Barrier Evaluation take into account the intended 'synergism'of the fission product barrier basis information which cannot be adequately addressed by theNUMARC/NESP-007 matrix format. An example would be a condition in which RCS leakcage intocontainment is in excess ofnormal makeup capacity (RCS potential loss) in conjunction with a secondaryside release with primary to secondary leakage in excess of technical specifications (Containment loss).Under a matrix format, this combination of conditions would require a Site Area Emergency (SAE)declaration because NUMARC/NESP-007 requires an SAE for the potential loss ofthe fuel clad or RCSwith the loss of another barrier. This is clearly not intended. NUMARCINESP-007 containment lossindicator #4 basis states that the Site Area Emergency associated with the containment loss indication isintended to be escalatory from RCS breaches associated with SG tube ruptures.
The Fission Product Barrier Evaluation does not rely on single indications as stated in the RAI. For themajority of the bounding conditions defined in the Fission Product Barrier Evaluation the indicatorssubsumned into other combinations of conditions consist of those indicators which are either:
" Completely bounded by another combination for the same indicator, or* Are a subset of another indicator.
In the case cited (>300 PtCi/cc DEI-13 1 in conjunction with primary system leakage > 75 gpm), thecombination was omitted in the Fission Product Barrier Evaluation because this condition would result inexceeding the 17 R/hr SAE EAL. The 17 R/hr SAE EAL is based on >300 iiCi/cc DEI-131I inconjunction with primary system leakage into containment.
![Page 8: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/8.jpg)
Implementatiodn
*SiteSpecific
Analysis
Required
*MatrixFormatisnotRequired
But
YouMustDocument ComplianceWith
AllPossibleCombinations
*EALBasesWillBe
Valuable
-fortraining
-for futureEALrevisions
*Not A
SmallProject
*NeedSupport fromOther GroupsEspeciallyOperations
andEngineering
PR39NUMARI~
P-j--9
![Page 9: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/9.jpg)
Implementation
*SiteSpecificAnalysisRequired
*Matrix
Formatisnot R
eq-uired;but
Youmustdocumentcompliancewith
all possiblecombinations
*EALbaseswillbevaluable
-Fortraining
-Forfuture
EALrevisions
*Notasmallproject
*Need
supportfromothergroups
especially,,OperationsandEngineering.
NUMARC
BF-30
![Page 10: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/10.jpg)
PWR FissionProductBarriersSeptember 22, and 23, 1992
NRC liaison: William Reckley
Role: Provide NRC perspectiveImprove NRC knowledge of industr'y concern
Purpose of Breakout Session
Open forum to elicit comments and questions related to the methodology, discuss-lesson"learned from the pilot programs, and scenario examples with cross reference to EALs.[Quick Review-of PWR Fission Product Barriers Matrix* Barriers
* Mode Applicability
Use of EOP information, CSFs, EOP transitions, etc.* Layout of Matrix
Pilot Program Lessons
* Management acceptance of the concept.* Operations support and acceptance of the need for improvement and themethodology.
* Team approach [Task Force: (Care Group) Ops, EEP, HP, Training (LiaisonGroup), Maintenance, Security, Industrial Safety, Licensing].* Expect resistance to the Matrix. There are benefits but alternatives are possible.
Scenarios
Loss of Reactor Coolant ScenariosRCS Unidentified leakage of 5 gpm. T/S Shutdown ______'Leakage increases to 15 gpm -----Leakage increases to 65 gpm UE %)gpm EAL no longer exists (based on charging/highhead capacity)
![Page 11: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/11.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
TO address the staff's concerns, the EALs have been reised to add this combination as a gmeific fissionDroduct barrier EAL. This EAL has been added in light of the assumptions which are made in thederivation of the containment radiation monitor value associated with the fuel clad loss EAL as well asvariables in the bounding assumptions (i.e. differences in time after shutdown and coolant volumereleased).
[Pani.31(Subpara. 11Loss ofcontainment cooling will not result in a containment pressure (3.0 psig) sufficient to result in acontainment isolation. In addition, procedural requirements require the containment to be vented underthis condition to maintain pressure well below the isolation setpoint.
A faulted steam generator could result in a containment isolation signal. To address those conditions inwhich a valid containment isolation sional is not the result of a breach of the RCS. but as a result ofafaulted SG inside contairnent, classification would be made based on EAL 4.1.1 which has been modifiedto address Phase "A". Phase "B" or CVI isolation failures. regadless of initiating event.
[Subpara. 21NUMARC/NESP-007 state in the basis for containment barrier loss #I: "Conditions leading tocontainment RED path result from RCS barrier and/or Fuel Clad Barrier Loss. Thus, this EAL isprimarily a discriminator between Site Area Emergency and General Emergency representing a potentialloss of the third barrier." Therefore, entry into Containment RED path by itself is intended to result in aGeneral Emergency.
As stated in the 1P3 PEG, in order to reach containment RED path, a containment pressure of 47 psigmust be exceeded. This pressure is well in excess of the maximum pressure attained from the DBALOCA and is greater than the maximum pressure attained for all analyzed steam line breaks insidecontainment specified in the IP3 FSAR. Therefore, to attain such a containment pressure, the energysource must be as a result ofa severely degraded core (metal water reaction) in conjunction with RCSbreach or a severe ATWS condition in conjunction with RCS breach. Per NUMARC/NESP-007 IC SS2such an ATWS leads to imminent or potential loss of fuel clad.
Reference in this iustification to core cooling and heat sink RED path has been deleted from the FissionProduct Barrier Evaluation.
![Page 12: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/12.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
[Subpara. 31Per the IP3 EALs, core cooling RED only requires declaration of a Site Area Emergency. Justification#10 in the Fission Product Barrier Evaluation referenced in this RAI was in error and should have read"... and warrants declaration of a Site Area Emergency." The Fission Product Barrier Evaluation has beenrevised to correct this error and to reference the vRoer Justifications.
[Subpara. 41Per the 1P3 EALs, core cooling RED and functional restoration procedures not effective within 15 minutesis the threshold for a General Emergency. Justification #11 referenced in this RAI has been revised andthe Fission Product Barrier Evaluation has been revised to reflect the yrovr references.
tSubpara. 51The justification was not intended to infer that a loss of RCS subcooling can only occur from a loss ofRCS. Rather, that any core cooling ORANGE or RED path represents a loss of subcooling resulting froma loss ofRCS. Justification #12 has been reworded to reflect the following basis.
ORANGE path core cooling is entered when either CET> 700OF or RVLIS water level - top of fuel (REDpath ifboth conditions exist or CETs> 1200 IF). The RCS pressure corresponding to 700 IF isapproximately 3100 psig. This pressure is more than 600 psig greater than the pressurizer safety valve liftpressure and 365 psig greater than the RCS safety limit. If the RCS is intact under this condition, RCSbarrier loss is imminent. RCS inventory is never intentionally reduced to the top of fuel (39%RVLIS)under hot conditions or power operations. A reduction in RCS volume of this magnitude indicates asignificant breach of the RCS barrier since no intentional valving configuration would result in such adecrease. Any condition which results in an inventory loss of this magnitude must be attributed to anRCS breach caused by a RCS line break or unisolated primary system discharging in excess of makeupcapacity. It would be extremely poor judgment to assume that a loss of the RCS barrier has not occurredunder either of these conditions. It should be noted that vessel water level below the top of fuel isconsidered a RCS barrier loss in the BWR fission product EALs. There is no difference in themechanisms which could cause vessel level to dop below the top of fuel between BWRs and PWRs.Important to this basis is, for the purpose of emergency declaration, the potential release of fissionproducts to the environment. In the case where the fuel clad is actually or potentially breached, theassumption that the fission products would be contained, even in the absence of other RCS loss indicatorsnot immediately apparent with vessel level below the top of fuel is inappropriate. Figure 4.16 of NUREG1228 "Source Term Estimation During Response to Severe Nuclear Power Plant Accidents" shows howeach of the critical safety functions is related to fission product barrier maintenance as regards preventingradioactivity releases. Core heat removal (core cooling) along with RCS pressure control and RCS heatremoval (heat sink) are shown to be directly related to RCS boundary maintenance.
It should also be noted that NUTMARC/NESP-007 considers RED path heat sink a potential loss of RCS,yet the conditions requiring entry into tis path are based on insufficient SG level and feedwater flow.These conditions are not direct threats to RCS barrier integrity but may lead to RCS pressure conditionswhich in turn may lead to RCS barrier breach. NUMARC/NESP-007 provides no technical basis tosupport how a RED path heat sink represents a potential loss ofRCS boundary. it would appear that theRCS inventory loss conditions requiring entry into core cooling ORANGE or RED path are much moredirectly indicative of actual or potential RCS breach than is entry into RED path heat sink.
ISubpara. 6]The Fission Product Barrier Evaluation and EALs associated with the combinations referenced have berevised to include the speified combinations: Coolant activity > 300 uCi/cc 1-131 eauivalent incombination with vriMar sMste leaka> 75 gin. RCS subcooling < SI inititon setvint due to RCS
leakaf. RED oath Inteitrty or> 0.06 uCi/cc on R-l1 and R-12 due to RCS leakae
[Pama 41
![Page 13: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/13.jpg)
OBJECTV
000-a000000000
~000go000
0-*
wo
-a001
o00
e0/
.
IPLA
DESIGN
GOALS
REACTIVTY
Figure
4.16
I Relationshipamongcriticalsafetyfunctions,maintainingfission
productbarriers,and
preventingarelease
Source:
NUREG-1210
CRITICAL JSAF
FUNCTIONS
![Page 14: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/14.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
It is still.appropriate to define, where possible, distinct EALs which are indicative of multiple barrierloss/potential loss. This minimize the time to classify while assuring multiple conditions are readilyevaluated and properly classified. Based on exhaustive operator interviews, the use of a fission productbarrier matrix format has been determined to be overly burdensome and confusing for the user resulting inmissed or inorrect classifications. Tins concern has been expressed by other licensees who haveattempted to implement NUMARC/NESP.007 fission product barrier EALs with only a matrix format.
Because of the complexity of the NUJMARC/NESP-007 fission product barrier loss/potential lossdefinition of the Site Area Emergency, some licensees have attempted to deviate from NUMARC andsimplif the fission product barrier losstpotential loss definition by removing the intended reducedweighting of the containment The reduced weighting of the containment at the SAE classification is asignificant part ofthe basis in the intended synergism between barrier loss indicators. The 1P3 FissionProduct Barrier Evaluation maintains this intended synergism of NUMARC while eliminating theinherent complexity. The 1P3 EAL format has been validated by operating crews utilizing scenarios in theplant-specific simulator to test each EAL. The results of this validation have been documented andfeedback incorporated into the EALs to futher ensure their usability.
![Page 15: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/15.jpg)
Indian Point 3 Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Remnu to General RAI #4 (Date 5)
NUMARC/NESP-007 Section 3.9 states:
"Plantemergencyoperating proceduires(EOPs)are designed to maintainand/orrestorea set ofCSFswhich are listed in the orderofpriorilyofrestorationeffortsduring accidentconditions.ff.
7Tere are diverse and reduindantplantsystems to support each CSF. By monitoring theCSFsinsteadof the individualsystem component status, the impactofmultiple events isinherently addressed,e.g. the number ofoperablecomponents available to maintain thefunction.
The EOPscontaindetailedinstructionsregardingthe monitoringof thesefunctions andprovidesa schemefor classifying the significanceof the challenge to the functions. InprovidingEALs basedon these schemes, the emergencyclassificationcanflow from theEOPassessmentratherthan being basedon aseparateEAL assessment. This isdesirableas it reducesambiguity andreducesthe time necessaryto classify the event."
As stated by NUMARC, each CSF is supported by diverse and redundant plant systems. The entryconditions for CSFSTs are also supported by diverse and redundant instrumentation. Containment REDpath is not a single indicator but a defined, measurable and operationally significant condition which isknown to be indicative of multiple fission product barrier losses. The 1P3 EAL scheme does not relysolely on this condition to determine when a general emergency due to the loss of fission product barriersmust be declared. Nor does it preclude the declaration of a general emergency based on other fissionproduct barrier loss EALs which may or may not manifest themselves under a given condition. The EP3EAL scheme does require classification of aGeneral Emergency because, in and of itself, this conditionrepresents a loss of the fuel clad, RCS barriers and a potential loss of containment barrier.
Res~onse to General RAI #5 (pat 5)
Refer to Response to General RAI #3 [Para. 31 [Subpara. 5]
![Page 16: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/16.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITONAL INFORMATION
SPECIFC RAY,
Resnonue to Specific RAI #1 (nauc 5)A.EAL # 5.1.1has been revised to reference Rerformance of an assessment of the release. The EAL has alsobeen revised to include criteria reauiring declaration if the assessment is not accomulished within 60mnues-B.R-19 is a liquid effluent process monitor. This release path only applies to NUMARC/NESP-007 ICAUl.1 and AAIl. The upper range ofR-14 is1E6 cpm. The value associated with the Alert criteria isin excess of this instruments range and is therefore indicated as N/A. Subsequent to the original NRCsubmittal, IP3 replaced Monitor R-024 with a new Backup Hi-Range Vent Monitor. The Bottom range ofthis monitor is 140 Ci/sec. This value is greater than the SAE trigger threshold is therefore indicated asN/A. A value of 360 Ci/ sec as obtained from this monitor will indicate a GE.
Steam dump and main steam safety valve monitors are not specified since release from these paths aredependent upon system flow rate which in turn is dependent upon the number ofvalves open and the RCSpressure over the duration of the release. Due to the wide range of release rates possible for a givenmonitor reading, no single trigger value would be appropriate. Releases from these paths are classifiedunder the subcategory 5.2 EALs.
The IP3 PEG has been revised to lDrovide these iustifications.
Response to Specific RAY #2 (DaLpe 6)0
EAL # 5.1.2 has been revised to reference verformance ofan assessment ofthe release. The EAL has alsobeen revised to include criteria reauiring declaration if the assessment is not accomplished within 15minutes.
Response to Specific RAI #3 (Daee 7)
As stated in the basis for IC AA2 in the 'P3 PEG: "There is no indication that water level in the spent fuelpool or refueling cavity has dropped to the level of the fuel other than by visual observation. Since AA2.2addresses visual observation of fuel uncovery, EAL AA2.3 is unnecessary. Since there is no levelindicating system in the fuel transfer canal, visual observation of loss of water level would also berequired, EAL AA2.4 is unnecessary." Therefore, EAL 2.4.3 addresses the concerns of these exampleEALs.
![Page 17: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/17.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Response to Snecific RAI #4 (name 7)0
The conditional "and" criteria was added to be consistent with the IC from which this EAL was derived aswell as with the technical bases. As stated in NUMARCINESP-007: "It is this impaired ability to operatethe plant that results in the actual or potential degradation of the level of safety of the plant The cause ormagnitude of the increase in radiation levels is not a concern of this IC." The NUMARC AA3 IC states"...radiation levels within the fakcility that impedes operation of systems required to maintain..." Thereforethe intent if the IC is not to declare simply upon the existence of such as radiation level, rather, to declareifaccess is impeded. If access to the area is not required then access is not impeded. The 1P3 PEG hasbeen revised to reflect the EAL and bases wordiniz.
Response to Specific RAI #5 (pate 8)
EAL N5.1.3 has been revised to reference uerfor-mance ofan assessment of the release. The EAL has alsobeen revised to include criteria reauirina declaration if the assessment is not accomplished within 15minutes.
The source terms utilized to determine the values in Table 5.1 are those utilized in the 1P3 dose projectionprocedure IP-lO0l, "Determining the Magnitude ofRelease". The IP-1001 dose assessment methodologyuses dose conversion factors derived from WASH-1400 inventories and RG 1.4 design base fractions.Annual average (ODCM) meteorology was applied in determining the effluent monitor values.
Response to Specific RAI #6 (name 9)
EAL # 5.1.4 has been revised to reference wurformance ofan assessment of the release. The EAL has alsobeen revised to include criteria rouiring declaration if the assessment is not accomplished within 15minutes.
Table 5.2 has been revised to quantift doses in rem. The term "TEDERate has been changed to"External ENxoosr Rate. The term "CDE Thyroid Rate has been changed to Thyroid Exposure Rate(for 1 hr. of inhalation)".
Resnonse to Specific RAI #7 (nate 10)
Refer to Response to General RAI #3 [Para. 31 [Subpara. 51 for justification of use of ORANGE or REDpath core cooling as a RCS loss indicator. Use of this CSF as a RCS loss indicator is not a conservatism,but rather one of multiple indications of potential Fuel Clad and RCS barrier loss available to the user.While this CSF indicator by itself requires declaration of a Site Area Emergency, it is not inconsistentwith NUMARC. For example, NUMARC/NESP-007 specifies RED path Heat Sink as both a potentialloss of fuel clad and RCS barriers. Even though NUMARC/NESP-007 does not provide a basis for howRED path heat sink relates to RCS barrier potential loss, none the less, a Site Area Emergency is requiredbased on this singular CSF.
Resnoms to Specific RAI #7 (name 11 -this RAI is also identified as #7)
In the case cited (>300 ILCi/cc DEI-13 1 in conjunction with primary system leakage > 75 gpm), thecombination was originally omitted in the Fission Product Barrier Evaluation because this conditionwould result in exceeding the 17 R/hr SAE EAL (refer to response to general RAI #3, para. 3, subpara 3).The 17 R/hr SAE EAL was based on >300 ;&Ci/cc DEI-13 1 in conjunction with primary system leakage
![Page 18: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/18.jpg)
Indian Point 3 Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
into containment However, this EM. has been added in light of the assumptions which are made in thederivation ofthe containment radiation monitor value rssociated with the fuel clad loss EM. as well asvariables in the bounding assumptions (i.e. differences in time after shutdown and coolant volumereleased).
The Fission Product Barrier Evaluation and EALs associated with the combinations referenced have beenrevised to include the s&Oecqid combinations: Coolant activity > 300 uCi/cc; 1-131 eouivalent incombination with DriMa sMtm leakage > 75 gnm. RCS subcooling < SI initiation setooint due to RCSleakaae. RED Rath Intgritv. or> 0.06 uCi/cc on R-l1 and R-12 due to RCS leakage.
Regarding the combination ofa primary to secondary leak in excess of the RCS barrier loss threshold (75gpm) with unisolable release of secondary side to atmosphere and failed fuel (300 lLCi/cc: DEI-13 1), thiscondition would be classified as a General Emergency as cited in the RAI.
EAL 4.2.2 states:
"Unisolated faulted (outside VC) ruptured steam generatorANDAny indicators of fuel clad damage, Table 4.2"
The technical bases of this EM. states:
"This EM. is intended to address the full spectrum of Steam Generator (SG) tube rupture eventsin conjunction with a loss of containment due to a significant secondary line break with actual orpotential loss of the fuel clad integrity. This EM. addresses ruptured SG(s) with an unisolablesecondary line break corresponding to the loss of 2 of 3 fission product barriers (RCS barrier andcontainment barrier) with the actual or potential loss of the third (fuiel cladding). This allows thedirect release of radioactive fission and activation products to the environment. Resultant offsitedose rates are a function of many variables. Examples include: coolant activity, actual leak rate,SG carry over, iodine partitioning&and meteorology.
The indications utilized should be consistent with the diagnostic activities of the emergencyoperating procedures (EOPs), if available. This should include indication of reduction in primarycoolant inventory, increased secondary radiation levels, and an uncontrolled or completedepressurization of the ruptured SG. Secondary radiation increases should be observed viaradiation monitoring of condenser air ejector discharge, SG blowdown, main steam, and/or SGsampling system. Determination of the "uncontrolled" depressurization of the ruptured SGshould be based on indication that the pressure decrease in the ruptured steam generator is not afunction of operator action. This should prevent declaration based on a depressurization thatresults from an EOP induced cooldown of the RCS that does not involve the prolonged release ofcontaminated secondary coolant from the affected SG to the environment. This EM.encompasses steam breaks, feed breaks, and stuck open safety or relief valves.
Table 4.2 presents fuiel clad loss and potential loss indicators:
" ORANGE path in F-O.2, Core Cooling: Refer to EM. #1.1.1 basis* RED path in F-0.3, Heat Sink: Refer to EM. #1.2.1 basis" Coolant activity>300 1LCi/cc of1-13 1: Refer to EM. #2.1.2 basis" Containment rad monitor reading > 17 R/hr: Refer to EM. #2.2.2 basis
This condition represents a loss ofboth RCS and primary containment with the loss or potentialloss offuiel cladding and thus warrants declaration of a General Emergency."
![Page 19: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/19.jpg)
Indian Point 3 Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Also, EAL 4.1.6 states:
"Either:Any Phase "A*or Phase "B" or containment ventilation isolation valve(s) not closed whenrequired following confirmned LOCAORInability to isolate any primary system discharging outside containment
ANDRadiological release to the environment exists as a resultANDAny indicators of fuel clad damage, Table 4.2"
![Page 20: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/20.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
The technical bases of thisEALste:
"This EAL indicates loss ofboth RCS and containment with loss or potential loss of the fuelcladding and therefore warrants declaration of a General Emergency.
Failure of Phase "A7 or Phase "B" or CVI v'alves to isolate is intended to address incompletecontainment isolation that allows direct release to the environment. It represents a loss of boththe RCS and containment barrier.
The criterion "Inability to isolate any primary system discharging outside containment" addressesany breach of the RCS and containment which is not protected by the Phase "A", Phase "B" orCVI systems or which results from an interfacing system LOCA (not addressed by NUMARC).No leakage threshold is specified since leaks outside containment, particularly under dynamicconditions, are difficult to quantify and may manifest themselves with diverse symptoms.Symptoms of a primary system discharging outside containment may be indicated via massbalance, decreasing RCS inventory without corresponding containment response, or areatemperatures and radiation levels outside containment. It is for this reason that Senior WatchSupervisor/Emergency Director judgment is intended to be used in evaluating this criteria.However, it is intended that the magnitude of the leak associated with this EAL be consistentwith the RCS barrier loss threshold of 75 gpm or greater.
Table 4.2 presents fuel clad loss and potential loss indicators:
" ORANGE path in F-0.2, Core Cooling: Refer to EAL #1.1.1 basis" RED path in F-0.3, Heat Sink: Refer to EAL #1.2.1 basis" Coolant activity > 300 jiCi/cc of 1-13 1: Refer to EAL #2.1.2 basis* Containment rad monitor reading > 17 R/hr: Refer to EAL #2.2.2 basis"
The condition described in the RAI would be classifiable under either of these EALs.
Resnouiue to Specific RA! NO (pan 13)
Phase "A", Phase "B" and Containment Ventilation Isolation (CVI) valves are those valves associatedwith the Phase "A", Phase "B" and CVI isolation logic. Phase "A", Phase "B" and CVI are protectivesubsystems of the Containment Isolation System (CIS) designed to close containment isolation valves inthose systems which either come into direct contact with primary pressure or the containment atmosphereand penetrate the containment barrier. These valves are designed to close under conditions which areindicative of a LOCA (any automatic SI signal - Phase A &CVI or requiring containment spray - Phase B&CVI). Failure of one or more of these valves to close following a confirmed LOCA does not by itselfprovide a pathway outside containment As long as one valve in the line is closed, or if both valves fail toclose but no downstream pathway exists, classification under this EAL would not be required. Thecriterion "AND Radiological pathway to the environment exists" provides this discriminator. There is nointerface between the Phase "A", Phase "B" and CVI systems but each is comprised of diverse systemswhich provide the containment isolation function under LOCA conditions. The determination of theexistence ofa LOCA is consistent with the diagnostic activities specified in E-0 'Reactor Trip or SafetyInjection'.
The criterion "Inability to isolate any primary system discharging outside containment" addresses anybreach of the RCS and containment which is not protected by the Phase "A", Phase "B" or CVI systems orwhich results from an interfacing system LOCA (not addressed by NUMARC). No leakage threshold isspecified since leaks outside containment, particularly under dynamic conditions, are difficult to quantifyand may manifest themselves with diverse symptoms. Symptoms ofa primary system discharging outside
-12-
![Page 21: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/21.jpg)
Indin Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
containment may be indicated via mass balance, decreasing RCS inventory without correspondingcontainment response, or area temperatures and radiation levels outside containment. It is for this reasonthat Senior Watch Supervisor/Emergency Director Judgment is intended to be used in evaluating thiscriteia. However, it is intended that the magnitude of the leak associated with this EAL be consistentwith the RCS barrier loss threshold of 75 gpm or greater.
The technical bases for EALs 4.1.3 and 4.1.6 have been revised to add the clarification that it is intendedthat the magnfitude of the leak associated with this EAL be consistent with the RCS barrier loss thresholdof 75 anm or maer.
Resnonse to Specific RAI #9 (pate 13)
As described in Response to General RAI #3 [Pana. 31 [Subpara. 5], RCS inventory is never intentionallyreduced to the top of fuel (39% RVLIS) under hot conditions or power operations. A reduction in RCSvolum of this magnitude indicates a significant breach of the RCS barrier since no intentional valvingconfiguration would result in such a decrease. Any condition which results in an inventory loss of thismagnitude must be attributed to a RCS breach caused by a RCS line break or unisolated primary systemdischarging in excess of makeup capacity. It would be extremely poor judgment to assume that a loss ofthe RCS barrier has not occurred under this condition. Important to this basis is, for the purpose ofemergency declaration, the potential release of fission products to the environment. in the case where thefuel clad is actually or potentially breached, the assumption that the fission products would be contained,even in the absence ofother RCS loss indicators, with vessel level below the top of fuel is inappropriate.As stated above, it requires a significant RCS inventory loss to attain this level. Therefore, consideringvessel level below the top of fuiel a loss ofRCS is not conservative, but appropriate.
It should also be noted that vessel water level below the top of fuel is considered a RCS barrier loss in theBWR fission product barrier EALs. There is no difference in the mechanisms which could cause vessellevel to drop below the top of fuel between BWRs and PWRs.
There is also a conflict within NUMARC/NESP-007 regarding vessel water level. As stated in the RAI,NUMARC/NESP-007 would only require declaration of an Alert due to vessel level below the top of fuelbased on fission product barrier loss. The fission product barrier loss EALs only apply under poweroperations and hot condition. Yet system malfunction IC SS5 requires declaration of a Site AreaEmergency for vessel level resulting in core uncovery when in cold shutdown or refueling modes. Thiswould mean that without other RCS loss indicators, if the vessel level dropped'to below the fuel under hotconditions, the emergency would have to be upgraded to a Site Area Emergency if the plant achieved coldconditions.
Response to Specific RAI #10 (Daze 14)
Refer to Response to General RAI #3 [Pama 31 [Subpara. 21. It would be inappropriate not to declare aGeneral Emergency based on a valid indication ofcontainment pressure in excess of 47 psig resultingfrom a loss of reactor coolant, regardless of the availability of other futel clad and RCS barrier loss EALs.It is understood that ifother applicable fuiel clad and RCS barrier loss indicators are available, they wouldserve to confirm their respective barrier losses. But NUMARC/NESP.007 does not require confirmationby multiple barrier loss indicators for a single barrier. That is, any one valid barrier loss indicator issufficient to consider that barrier lost The basis supporting declaration of a General Emergency uponentry into RED path containment is that it is indicative of loss of both fuel clad and RCS with potentialloss of containment.
The only source of significant hydrogen concentration in containment is severe fuel damage resultingfrom metal-water reaction and subsequent discharge into the containment atmosphere. A containment
-13-
![Page 22: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/22.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
hydrogen concentration of 4% corresponds to a range of 30% - 40%/ metal-water reaction (Attachment 9to EP- 1028 "Core Damage Assessment") and is well into the possible uncoolable core geometry region(Figure B-10 NUREGIBR-O 150, Vol. 1,Rev. 2). Failure to declare a General Emergency, based on avalid indication, under these conditions is inappropriate.
-14-
![Page 23: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/23.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Reseu to Specific RAI #11 (Dupe 15)
The actuation setpoint for the Phase "B" isolation is 23 psig. This pressure is significantly high toindicate a significant loss OfCoolant accident for containment pressure increases resulting from a loss ofcoolant accident. EAL 4.1.4 has been revised to specify a confirmed Rase "B" isolation signal as a resultof a loss -ofreactor coolant to discriminate from a severe faulting of SGs inside containment.
Table 4.1 identifies fuel clad loss indicators for use in combination w~ith the RCS loss and the containment91MI indicator ("Conffimed phase "B- isolation signal due to LOCA with less than minimum
containment cooling safeguards equipment operating"). Table 4.2 includes fuel clad loss and potentialloss indicators for use in combination with RCS loss and containment loss indicators. RED Rg1L corcoolinz has been added to the fuel clad loss inicator list consistent with the fission Droduct barrierMatrix The term "fuel clad damage indicators " was used to represent both fuel clad loss and potentialloss indictors. The term 'fuel clad loss indicators" was used to represent fuel clad loss indicators only.
Rawaose to Snecific lAX #12 (Daee 16)
Refer to Response to General RAI #3 [Para. 31 [Subpara. 51 for justification of use ofRED path corecooling as a Fuel Clad and RCS loss indicator.
NUMARC/NESP-007 Section 3.9 states:
"Plantemergency operatingprocedures (EO~s)aredesignedto maintainand/orrestorea set ofCSFswhich are listedin the orderofpriorityofrestorationeffortsduringaccidentconditions.".
There are diverseand redundantplant systems to supporteach CSF By monitoringtheCSFs insteadofthe individualsystem component status, the impact ofmultiple events isinherentlyaddressed,e.g. the number of operablecomponents available to maintainthefunction.
The EO~scontain detailedinstructionsregardingthe monitoringofthesefunctions andprovidesa scheme for classifyingthe significanceofthe challenge to thefunctions. InprovidingEA4 s basedon these schemes, the emergency classiicationcanflow from theEOP assessment ratherthan being basedon a separateFAL assessment. This isdesirableas itreducesambiguity andreduces the time necessary to classify the event."
As stated by NUMARC, each CSF is supported by diverse and redundant plant systems. The entryconditions for CSFSTs are also supported by diverse and redundant instrumentation. Core Cooling REDpath is not a single indicator but a defined, measurable and operationally significant condition which isknown to be indicative of multiple fission product barrier losses. The 1P3 EAL scheme does not relysolely on this condition to determine when a General Emergency due to the loss of fission product barriersmust be declared. Nor does it preclude the declaration ofa General Emergency based on other fissionproduct barrier loss EALs which may or may not manifest themselves under a given condition. The IP3EAL scheme does require classification of a General Emergency because, in and of itself, this conditionrepresents a los of the fuel clad RCS barriers and a potential loss of containment barrier.
Resnonse to Smeific AI #13 (Date17)
The conditions defined by this EAL were identified as other site specific indications ofcontainmentbarrier failure that unambiguously indicate loss or potential loss of containment barrier.
![Page 24: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/24.jpg)
Indiain Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Both doors open on VC airlock is a clear breach of the containment barrier. While these doors arenormally interlocked to Preclude this condition, an interlock failure is possible. Since lP3 Tech. Spec.allows this condition for up to 4 hrs., the 4 hr. criteria was specified. This is consistent with theNUMARC/NESP-007 philosophy not to declare events within the Tech. Spec. allowed envelope.
Inability to close containment pressure relief or purge valves which results in a radiological release path tothe environment for >4 hrs. was also identified as a clear breach of containment barrier. Thecontainent pressure relief and purge valves may be periodically opened under routine plant operationsand therefore a condition in which these valves cannot be closed, even though no automatic isolatingevent exists (LOCA) is possible. Since 1P3 Tech. Spec. allows this condition for up to 4 hrs., the 4 hr.criteria was specified. This is consistent with the NUMARC/NESP-007 philosophy not to declare eventswithin the Tech. Spec. allowed envelope.
Response to Specific RAI #14 (oaae 18)
EAL 2.2.1 has been revised to indicate >0.06 u~i/cc on R-1lI and R-12 due to RCS leakage. Reference tocoolant activity has been deleted. The technical bases has been revised to sumurt this changfe.
This EAL is included under the "Reactor Fuel" category and "Containment Radiation" sub category sincethe indication is based on containment radiation monitor readings. These readings are most closelyassociated with the reactor fuiel. The 1P3 EAL presentation method places similar EALs into categoriesand subcategories that focus the user's attention to the specific EAL threshold that corresponds to theplant condition of concern. This provides a logical classification and escalation path of related indicatorsand thus allows for rapid assessment of emergency conditions associated with fission product barrier loss.It is important to note that the IP3 EAL categories and subcategories are not simply representations orabbreviations of the NUMARC/NESP-007 ICs. Rather, each IP3 category and associated subcategory is apathway from broad indicators of potential emergency events to a set of specific threshold conditions thatrequire emergency classification. Those EALs which are derived from the Fission Product BarrierEvaluation have been annotae to indicate the fission nroduct barrier loss/notential loss which te
Response to Smciic RAI #15 (naff 18)A.This EAL is included under the "Reactor Fuel" category and "Containment Radiation" sub category sincethe indication is based on containment radiation monitor readings. These readings are most closelyassociated with the reactor fuel. The 1P3 EAL presentation method places similar EALs into categoriesand subcategories that focus the user's attention to the specific EAL threshold that corresponds to theplant condition of concern. This provides a logical classification and escalation path of related indicatorsand thus allows for rapid assessment of emergency conditions associated with fission product barrier loss.It is important to note that the 1P3 EAL categories and subcategories are not simply representations orabbreviations of the NUMARC/NESP-007 ICs. Rather, each 1P3 category and associated subcategory is apathway from broad indicators ofpotential emergency events to a set of specific threshold conditions thatrequire emergency classification. Those EALs which are derived from the Fission Product BarrierEvaluation have been annotatedt to indicate the fission product barrier losvtential loss which thgy
I.NUMARC/NESP-007 does not specify that multiple fission product barrier loss indicators must be presentto consder that barrier lost. The logic term used between each fission product barrier losstpotential lossindicator in Table 4 ofNUMARC/NESP-007 is "OR". This means that any one indicator is sufficient to
![Page 25: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/25.jpg)
Indian Point 3 Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATI0N
consider the barrier lost or potentially losL Furthermore, NUMARC/NESP-007 does not state that theSam indicator should not be used to indicate the loss cf more than one fission product barrier.
NUMARC/NESP-007 also states in part:
"5. Slgn~fcant Rwiioacdve Inventor in Containment"
"The (site-specifc)readingisa value which indicatessigrnficantfuel damage well in excess ofthe E4LS associatedwith both loss ofFuelCladandloss ofRCS barriers.As statedin Section3.8, amajor releaseofradioactivityrequiringoffsie protective actionsfromn core damage is notpossible unless a majorfailureoffuel claddingallows radioactivematerialto be releasedfromthe core into the reactorcoolant. Regardlessofwhether containmentis challenged, this amountofactivityin containment, if released, couldhave such severe consequences that it is prudentto&tW this asapotentialssofcontainment, such thata GeneralEmergency declarationisl-rtL
It is also important to note that it is not expected that emergency classification would be based oncontainment radiation alone. Provided that other indicators are available, classification would beconfirmed by those redundant indicators. But, in the event of a severe accident, many of the otherindicators of multiple fission product barrier loss may not be available. Therefore, it would be appropriateto rely on this single indicator since it is indicative ofmultiple fission product barrier loss/potential loss.
Refer to the attached site specific analysis used to determine the containment radiation monitor setpoints.
Resueue to Specific RAI 016 (ne 19)A.EAL 8.4.1 has been revised to state an "Earthguake felt in~lant based 1=on a consensus of Control RoomOnerator on dut AND.'
B.NUMARCJNESP-007 quotes the followving paragraph from the referenced EPRI guidance defining a "feltearthquake" as:
"An earthquake of sufficient intensity such that: (a) the inventory ground motion is fet at thenuclear plant site and recognized as anearthquake based on a consensus of Control Room operators on duty at the time, and (b) forplants with operable seismic intuettothe seismic switches of the plant are activated. Formost plants with seismic instrumentation , the seismic switches are set at an acceleration of about0.01 g."
The referenced EPRI guidance clearly states that the "felt" earthquake requires both conditions of theearthquake being feclt and activation of seismic switches..
Response to Specific RAI 017 (name 20)
EA. 8.4.3 has been deleted. The exmple EM. from which it was derived. HUI-3 and its generic basesDrovides no 12ecific imidance for declaration beyond that which the IC provides. Therefore this EML hasbeen subsuimed into the "Other" catezorv EA. 9.1.1. The section 8.4 EALs have been renumbered
-17-
Reson to Specific RAI #18 (naze 21)
![Page 26: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/26.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
EAL 8.2.1 has begn risad to ame -Confirmed fire in ar contiguous to any plant area. Table 8.2 not...".
Remnonue to Snecific RAI #19 (page 21)A., B.EAL 8.1.1 has been risd to include an security event which rEuresents a ootential degrdation in thelevel of aft of the Wlagt
EAL B.1.2 has been revised to include any security event which rEuresents an actual substantialdegradatiOn of the level of saft of the RuLat
EM. 8. 1.3 has been revised to include an security event which Mrerescnts actual or likely failures of plantsystems needed to DRotc the public.
C.EML 8.1.1 has been revised to state "-.but outside vlant vital areas, Table 8.2".
Response to Snecific RAI #20 (pan 22)
Toxic or fammable gases do not in themselves pose any threat to the safe operation of the plant but maypreclude access to areas necessary for safe operation of the plant. Therefore the concern of this EM. areconcentrations which are either life threatening or preclude access to areas needed for safe plantoperation. No specific thresholds have been defined since specific thresholds are dependent upon the typeof toxic or flammable gas involved as well as the amount and type ofpersonal protective equipmentavailable to those individuals requiring access. Therefore, the determination as to whether concentrationsare sufficient to be ife threatening or preclude access to areas required for safe operation is left to thejudgment of the user. Where specific criteria are available to the user it is expected that criteria would beconsidered in this evaluation.
Response to Specific RAI #21 (Dare 23)
EM. 7.2.3 has been revised to sncif entr into ONOP-FP-IA. "Safe Shutdown From Outside the ControlRoom" which urovides xruidance for control room evacuation.
-18-
![Page 27: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/27.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Response to Sneclfl RA! #22 (pn 23)
Revisd EAL 7.2.5 SWat MPARI Control =Wno be established E ONOP-FP- IA. 'Safe Shutdwn From
Beasne to Specific RA! 023 (page 24)
The statement 'At least (site-specific) emergency generators are supplying power to emergency buses"serves no purpose. This HAL is concerned only with the loss of off-site AC power capability. If one of theemergency diesels is not supplying its emergency bus under hot conditions then an Alert would bedeclared based on EAL 6.1.3 (SM). NUMARC provides no criteria for the condition in which offsite ACPower capability Is lost and one emergency diesel generator is not supplying its emergency bus under coldconditions. If neither emergency diesels are supplying their emergency busses, either an Alert would bedeclared based on EAL 6.1.2 or a SAE based on EAL 6.1.4, depending on plant operating mode.
Remponse to Specific RA! #24 (nampe 24)
EALs 7.3.1 and 7.3.3 have been revised to add the words "saftssem annunciators or indications..."
Besnonse to Specific RAI #25 (Dame 25)
The term "unplanned" is not necessary. There would never be a plantned loss off all onsite or offsitecommunications capability. For a planned outage ofcommunicat ions equipment, alternatecommunications systems would always be established.
Response to Specific RA! #26 (Daae 26)
Both DC buses would never be de-energized for any planned activity unless the reactor was defueled.
Response to Specific RA! #27 (naye 27)A.EAL 6.1.2 mode Wfuicabilily has been revised to include the defuiel mode.
B.The statement *Failure of (site-specific) emergency generators to supply power to emergency buses" servesno purpose. This EAL is concerned only with the loss of all AC emergency bus power capability for> 15minutes under hot conditions. By definition, if the emergency busses are de energized for> 15 nun.,neither the AC transformers nor emergency diesel generators were successful in supplying power toemergency busses.
Besnonse to Sneific RA! #28 (Daze 28)
EAL 1. 1.1 and it's associated technical bases have been revised to be consistent with theNUMARCNESP-M7 criteria,
-19-
Responhe to Specific RA! #29 (Dawe 29)
![Page 28: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/28.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
The 1P3 Technical Specifications do not specify required functions to maintain cold shutdown. EAL 7.2.4is derived from IC SA3 which states: "Inability to Maintain Plant in Cold Shutdown." The anticipatorycriteria is provided in the use of the term "cannot be maintained." The definition section of the TechnicalBases Document defines the term as follows: "The value of the identified parameter(s) is not able to bekept above /below specified limits. This determination includes making an evaluation that considers bothcurrent and future system performance in relation to the current value and trend of the parameter(s).Neither implies that the parameter must actually exceed the limit before the action is taken nor that theaction must be taken before the limit is reached." NUMARC/NESP-007 "Questions and Answers"published in June 1993 defines the term 'function' as : "The action which a system subsystem orcomponent is designed to perform." The evaluation of both current and future system performance(function) is inherent in this definition of "cannot be maintained."
Response to Snecafic RAI #30 (Daze 30)
EAL 7.3.3 has been revised to include the term "significant transient".
Response to Specific RAI #31 (page 31)
The proper EAL reference isEAL 6.1.3. This was identified as a typographical error. EAL 6.1.3 hasbeen revised to state "Available safeguard bus AC power reduced to only one of the followiniz....
Response to Specific RA! #32 (namp 32)
The concern of NUMARC IC SS1I and this EAL is the loss of ability to provide AC power to the0safeguards busses and their vital loads. A condition can exist where the supply transformers and/oremergency diesel generators are available but a fault on the bus precludes powering vital loads. Thereforeit is more appropriate and inclusive to define the EAL by the inability to power the safeguards buses ratherthan the loss of the power sources.
Response to Sneific RA! #33 (naze 32)
EAL 1.1.2 and it's associated technical bases have been revised to be consistent with theMUMARC/NESP-007 criteria,
Response to Specific RAI.#34 (Dam 33)
1P3 Technical Specifications Section 1.2 defines hot shutdown as: Reactivity within the limits of Figure3. 10-1 andTavg> 200 OFand< 353 VF. As stated in theRA, EAL 1.1.2 addresses loss ofreactivitycontrol. The NUMARC/NESP-007 basis for SS4 also states that the EAL is intended addresses loss offunictions, including ultimate heat sink. No reference to core cooling is made. However, EAL 1.2.1 andEAL 3.1.3 provide for the declaration of a Site Area Emergency under conditions which loss of functionsthreaten core cooling~ It is also important to differentiate between function and operability of componentsor equipment which support a function. NUMARC1NESP-007 "Questions and Answers" published inJune 1993 defines 'function' as: "The action which a system, subsystem or component is designed toperform. Safety functions, as applied to PWRs are reactivity control, RCS inventory control andsecondary heat removal." NUMARC/NESP-007 Section 3.9 states "There are diverse and redundant plantsystems to support each CSF. By monitoring the CSFs instead of the individual system component status,the impact of multiple events is inherently addressed, e.g., the number ofoperable components available
![Page 29: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/29.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
to maintain the function."' Since it would be impossible to define all possible losses of system componentoperability une which loss of funrction may occur, consistent with Section 3.9 ofNUMARC1NESP-007,the loss of function is defined by CSF status. For secondary heat removal, that CSF is RED path heatsink The Techni-cal base document has been revised to reflect that EALs 1.1.2. 1.2.1 and 3.1.3 alsoserve to su~nrt IC SS4.
Respnse to Specific RAI #35 (Date 33)
The EAL does not imply that the reactor vessel head can be removed while in hot condition. Since thisconfiguration would never occur under hot conditions, that portion of the EAL based on visual observationwould not apply or be evaluated.
As stated in the RAI, oneof theNUMARC ICs from which EAL 3.1.3 is derived is NUMARC IC SS5:"Loss ofWater Level in the Reactor Vessel That Has or Will Uncover Fuel in the Reactor Vessel."' Thereare numerous conditions which can lead to a loss ofRCS inventory to the extent resulting in coreuncovery while in cold shutdown or refuel modes. The one addressed in the generic bases for PWRs is"sequences such as prolonged boiling following loss of decay heat removal." Loss of inventory can alsooccur as a result of drain down events. The concern of this IC and EAL is uncovery of the fuel, regardlessof the cause. Therefore the criteria regarding loss of decay heat removal serves no function. The EALwording "RVLIS cannot be maintained.." provides for the anticipatory criteria.
The mode applicability was expanded to include the inability to maintain RVLIS above top of fuelconsistent with use ofRVLIS level as a fuel clad barrier potential loss and RCS barrier loss indicator.Refer to Response to Specific RAT #10.
The RAI makes reference to local high power densities which can "uncover" fuel and cause fuel damagewithout loss of RCS inventory. While this may be true, this EAL makes no reference to local fueluncover)'. Rather, this EAL addresses loss of inventory indicated by RVLIS. Local uncover would not beobservable by RVLIS. Refer to Response to Specific RAI #10 for justification for use of RVLIS indicationas aloss ofRCS.
Response to Specific RAI #36 (nate 34)A.The wording "is not likely" has been added to EAL 6.1.5 regarding restoration of power.
The wordinz has been revised to reflect the wording: "Actual or immrinent entry into ORANGE or REDvath on F-0.2 Core Coolimg"
B.The concern of NUMARC IC SGT and this EAL is the loss of ability to provide AC power to thesafeguards buses and their vital loads. A condition can exist where the supply transformers and/oremergency diesl generators are available but a fault on the bus precludes powering vital loads. Thereforeit is more appropriate and inclusive to define the EAL by the inability to power the safeguards buses ratherthan the loss of the power sources
Response to Specific RAI #37 (Dae 36)
EAL 1.1.3 has been revised to include the core cooline OR heat removal loixic by inclusion ofRED oathcore cooling in combination with RED path Subcriticality. EAL 1.3.2 has been subsumed into theSubcrit sub-category sinc this is the common condition in combination with either core cooling o
-21-
![Page 30: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/30.jpg)
Indian Point 3Emergency Action LevelsRESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION
Resnoeme to Snecifi RI #38 (pane 36)
Table 7.3 has been revised to inclde Panel "FBF".
-22-
![Page 31: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/31.jpg)
Attachment 11to IPN-95-028
Indian Point 3 Emergency Action Levels, Revision 1,Based on Proposed Response to NRC RAls,
January 10, 1995
New York Power AuthorityDocket No. 50-286
![Page 32: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/32.jpg)
ISincethisdocumentwasprepared,theSrity
haschangedtheJobTitle"Shift
Supervisor"to"ShiftManager."
ThedutiesandresponsibilitiesoftheShift
ManagerarethesameasthosepreviouslyassignedtotheShiftSupervisor.
This
documentwillberevised,priortoimplementation,
toreflectthischange.
IndianPoint 3EmergencyActionLevels
Rev.1
BasedonProposedResponsestoNRCRAIs
Category1.0
CSFSTStatus
Category2.0
ReactorFuel
Category3.0
ReactorCoolant System
Category4.0
Containment
Category5.0
Radioactivity
Release
Category6.0
ElectricalFailures
Category7.0
Equipment Failures
Category8.0
Hazards
Category9.0.
Other
2/16/95
![Page 33: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/33.jpg)
1.0
CSFST
Status
1.1
Subcriticality
1.1.1
Alert
(SA2]
Any
failure
ofan
automatic
trip
signal
to
reduce
power
range<
5%
AND
Manual
trip
issuccessful
Power
Operations,
Hot
Shutdown
1.1.2
site
Area
Emergency
[SS2
]
RED
path
inF-0.1
SUBCRITICALITY
AND
Emergency
boration
isrequired
Power
Operations,
Hot
Shutdown
1.1.3
General
Emergency
[SG2]
RED
path
inF-0.1,
SUBCRITICALITY
AND
Actual
orimminent
entry
into
either:
RED
path
inF-0.2,
CORE
COOLING
OR
RED
path
inF-0.3,
HEAT
SINK
Power
Operations
oWF1.0
Status
1.0
CSFST
Status
1.2
core
Cooling
1.2.1
siteArea
Emergency
[fpl
/fl,
rlj
CSS4]
ORANGE
or
RED
path
inF-0.2,
CORE
COOLING
Power
Operations,
Hot
Shutdown
1.2.2
General
Emergency
[fl1
,ri,
cpl]
RED
path
inF-0.2,
CORE
COOLING
AND
Functional
restoration
procedures
not
effective
within
15min..
PowerOperations,
Hot
Shutdown
1.0
CSFST
Status
4o0
![Page 34: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/34.jpg)
Categolffr.O0
CSFST
Status
1.3
Heat
Sink
1.3.1
site
Area
Emergency
[fpl
,rpl]
[554]
RED
path
inF-0.3,
HEAT
SINK
AND
Heat
sink
isrequired
Power
Operations,
Hot
Shutdown
1.0
CSFST
Status
1.4
Integrity
1.4.1
Alert
[rp1]
RED
path
on
F-0.4,
INTEGRITY
Power
Operations,
HotShutdown
1.0
CSFST
Status
1.5
Containment
1.5.1
General
Emergency
[fl,
ri,
cpl]
RED
path
F-0.5,
CONTAINMENT
resulting
from
loss
ofcoolant
0
![Page 35: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/35.jpg)
,NW
categolr.0
CSFST
Status
Power
Operations,
Hot
Shutdown
![Page 36: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/36.jpg)
2.0
Reactor
Fuel
2.1
Coolant
Activity
2.1.1
Unusual
Event
[SU4]
Coolant
sample
activity:
*1.
0ACi/cc
dose
equivalent
1-131
OR
*100/(E
Bar)
ACi/cc
for
all
noble
gases
with
half-lives
>10
min.
All
2.1.2
Alert
[fl]
Coolant
activity
>300
ACi/cc
1-131
equivalent
Power
operation,
hot
shutdown
2.1.3
Site
Area
Emergency
(fl1
.rpl/rlj
Coolant
activity
>300
pCi/cc
1-131
equivalent
and
any
ofthe
following:
*RED
path
on
F-0.4,
INTEGRITY
oPrimary
system
leakage
>7S
gpm.
*RCS
subcooling
<SI
initiation
setpoint
*>
0.06
p&Ci/cc
on
R-11
and
R-12
due
to
RCS
leakage
Power
operation,
hot
shutdown
IgoIV2..0
:tor
Fuel
2.2
Containment
Radiation
2.2.1
Alert
[rlj
>0.06
p&Ci/cc
on
R-11
and
R-12
due
to
RCS
leakage
Power
operation,
hot
shutdown
2.2.2
Site
Area
Emergency
(fl,
rl]
Containment
radiation
monitor
R-25
or
R-26
>17
R/hr
Power
operation,
hot
shutdown
2.2.3
General
Emergency
(fl1,
rl,
cpl]
Containment
radiation
monitor
R-25
or
R-26
>68
R/hr
Power
operation,
hot
shutdown
2.0
Reactor
Fuel
2.0
Reactor
Fuel
![Page 37: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/37.jpg)
CategoIT'2.o
Reactor
Fuel
2.3
Refueling
Accidents
or
other
.Radiation
Monitor.
2.3.1
Unusual
Event
[AU2]
Spent
fuel
pool
(reactor
cavity
during
refueling)
water
level
cannot
be
restored
and
maintained
above
the
spent
fuel
pool
lowwater
level
alarm
setpoint
All
2.3.2
Alert
[AA2
]
Confirmed
sustained
alarm
on
any
ofthe
following
radiation
monitors
resulting
from
anuncontrolled
fuel
handling
process:
"R-2/R-7
Vapor
Containment
Area
Monitors
"R-5
Fuel
Storage
Building
Area
Monitor
oR-25/26
Vapor
Containment
High
Radiation
Area
Monitors
"R-12
Containment
Gas
Activity
All
2.3.3
Alert
[AA2]
Report
ofvisual
observation
ofirradiated
fuel
uncovered
All
0
![Page 38: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/38.jpg)
CategodT'3.0
Reactor
Coolant
System
3.0
Reactor
Coolant
System
3.1
RCS
Leakage
3.1.1
Unusual
Event
[SU5]
Unidentified
or
pressure
boundary
leakage
>10gpm
OR
Identified-leakage
>25
gpm
Power
operation,
hot
shutdown
3.1.2
Alert
[rpl]
3.*0
Reactor
Coolant
System
3.2
Primary
to
Secondary
Leakage
3.2.1
Unusual
Event
[ci]
Unisolable
release
ofsecondary
side
to
atmosphere
from
the
affected
steam
generator(s)
with
primary
to
secondary
leakage
>0.3
gpm
inany
steam
generator
Power
operation,
hot
shutdown
3.2.2
Primary
system
leakage
>75
gpm
Power
operation,
hot
shutdown
3.1.3
[SS5]
site
Area
Emergency
[fpl
,ri]
Bite
Area
Emergency
[rpl,
cl]
Unisolable
release
ofsecondary
side
to
atmosphere
from
the
affected
steam
generator(s)
with
primary
to
secondary
leakage
>75
gpm
Power
operation,
hot
shutdown
RVLIS
cannot
be
maintained
>39%
with
no
RCPs
running
OR
With
the
reactor
vessel
head
removed,
it
isreported
thatwater
level
inthe
reactor
vessel
isdropping
inan
uncontrolled
manner
and
core
uncovery
is
likely
Power
operation,
hot
shutdown,
cold
shutdown,
refuel
3.2.3
site
Area
Emergency
[fl,cl]
Unisolable
release
ofsecondary
side
to
atmosphere
from
the
affected
steam
generator(s)
with
primary
to
secondary
leakage
>0.3
gpm,in
any
steam
generator
AND
Coolant
activity
>300
pCi/cc
of1-131
Power
operation,
hot
shutdown
40
![Page 39: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/39.jpg)
NW
CtglV.
Reactor
Coolant
System
3.0
Reactor
Coolant
System
3.3
RCB
Subcooling
3.3.1
Alert
[rl]
RCS
subcooling
<SI
initiation
setpoint
Power
operation,
hot
shutdown
![Page 40: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/40.jpg)
Containment
4.0
Containment
4.1
Containment
Integrity
Status
4.1.1
Unusual
Event
[ci)
4.*1
Containment
Integrity
Status
4.*1.3
Both
doors
open
on
aVC
airlock
for
>4
hrs. OR
Inability
to
close
containment
pressure
relief
or
purge
valves
which
results
ina
radiological
release
pathway
to
the
environment
for>4
hrs
OR
Any
Phase
"A"l
or
Phase
"B"
orcontainment
ventilation
isolation
valve(s)
not
closed
when
required
which
results
ina
radiological
release
pathway
to
the
environment
Power
operation,
hot
shutdown
4.1.2
Site
Area
Emergency
[ri,
ci]
Rapid
uncontrolled
decrease
incontainment
pressure
following
initial
increase
OR
Loss
ofprimary
coolant
inside
containment
with
containment
pressure
orsump
level
response
not
consistent
with
LOCA
conditions
site
Area
Emergency
[ri,
cl)
Either:
Any
Phase
"A"l
or
Phase
"B"
orCVI
valve(s)
not
closed
when
required
following
confirmed
LOCA
OR
Inability
to
isolate
any
primary
system
discharging
outside
containment
AND
Radiological
release
to
the
environment
exists
asa
result
Power
operation,
hot
shutdown
4.1.4
cpl]
General
Emergency
[f1,
rl,
Confirmed
phase
"B"
isolation
signal
following
confirmed
LOCA
with
less
than
minimum
containment
cooling
safeguards
equipment
operating,
Table
4.3
AND
Any
indicators
offuel
clad
loss
,Table
4.1
Power
operation,
hot
shutdown
Power
operation,
hot
shutdown
S0
4.0
containment
![Page 41: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/41.jpg)
CategIW4.0
Containment
4.0
Containment
4.1
Containment
Integrity
Status
4.1.5
General
Emergency
[fpl/f1,
rl,cl]
Either:
Rapid
uncontrolled
decrease
in
containment
pressure
following
initial
increase
OR
Loss
ofprimary
coolant
inside
containment
with
containment
pressure
orsump
level
response
not
consistent
with
LOCA
conditions
AND
Any
indicators
offuel
clad
damage,,
Table
4.2
Power
operation,
hot
shutdown
4.1.6
General
Emergency
[fpl/f1,
rl,cl]
Either:
Any
Phase
"All
or
Phase
"B"
or
CVI
valve(s)
not
closed
when
required
following
confirmed
LOCA
OR
Inability
to
isolate
any
primary
system
discharging
outside
containment
AND
Radiological
release
to
the
environment
exists
asa
result
AND
Any
indicators
offuel
clad
damage,
Table
4.2
Power
operation,
hot
shutdown
4.0
Containment
4.2.
SG
Tube
Rupture
v/
Secondary
Release
4.2.1
site
Area
Emergency
[rl,
cl]
Unisolable
secondary
side
line
break
with
SG
tube
rupture
as
identified
inE-3
"Steam
Generator
Tube
Rupture"
Power
operation,
hot
shutdown
4.2.2
General
Emergency
[fpl/f1,rl
cl]
Unisolable
secondary
side
line
break
with
SG
tube
rupture
asidentified
inE-3
"Steam
Generator
Tube
Rupture"
AND
Any
indicators
offuel
clad
damage,
Table
4.2
Power
operation,
hot
shutdown
V
I
0
![Page 42: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/42.jpg)
WCa
tego
f7W%
.0Containment
4.0
Containment
4.3
Combustible
Gas
Concentrations
4.3.1
General
Emergency
(fl,rl,cplJ
34%
hydrogen
concentration
incontainment
Power
operation,
hot
shutdown
1.Coolant
activity
>30
0/h
Ci/c
cof
I131
2.Containment
radiationmonitor
R-25/R
26reading
>17
R/hr
3.RED
path
inF-0.2,
CORE
COOLING
Table
4.2
Fuel
Clad
Damage
Indicators
1.ORANGE
or
RED
path
inF-0.2,
CORE
COOLING
2.RED
path
inF-0.3,
HEAT
SINK
AND
Heat
sink
isrequired
3.Coolant
activity>
300
ACi/cc
ofI
131 4.Containment
radiation
monitor
R-25/R
26
reading
>17
R/hr
Table
4.1
Fuel
Clad
Loss
Indicators
Table
4.3
Minimum
Containment
Cooling
Safeguards
Equipment
Fan
Cooler
Units
Operating
Spray
Pumps
Required
<3
23
15
0
![Page 43: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/43.jpg)
5.0
Radioactivity
Release
/Are
aRadiation
5.1
EffluentMonitors
5.1.1
Categol.
0Radioactivity
Release
Unusual
Event
[AUl]
5.0
Radioactivity
Release/
Area
Radiation
5.1
Effluent
Monitor.
5.1.4
Avalid
reading
on
anymonitors
Table
5.1
column
"HNUE"I
for>
60min.
unless
sample
analysis
can
confirm
release
rates
<2x
technical
specifications
within
this
time
period.
All
5.1.2
Alert
General
Emergency
[AGi
]
Avalid
reading
on
any
monitors
Table
5.1
column
"IGE
"Ifo
r>
15min.
unless
dose
assessment
can
confirm
releases
are
below
Table
5.2
column
"IGE
"Iwithin
this
time
period.
All.
[AA1)
Avalid
reading
on
anymonitorsTable
5.1
column
"Alert"
for
>15
min.
unless
dose
assessment
can
confirm
releases
are
below
Table
5.2
column
"Alert"within
this
time
period.
All
5.1.3
site
Area
Emergency
[AS1J
Avalid
reading
on
any
monitors
Table
5.1
column
"SAE"
for>
15min.
unless
dose
assessment
can
confirm
releases
are
below
Table
5.2
column
"SAE"
within
this
time
period.
All
5.0
Radioactivity
Release/Area
Radiation
![Page 44: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/44.jpg)
CategoW.
0Radioactivity
Release
5.2
Dose
Proj
ecti
ons/
Environmental
Measurements/
Rele
arse
Rate.
S.2.1
5.2
Dose
Projections/
Environmental
Measurements/
Relearse
Rate.
5.2.4
Unusual
Event
[AUl
]
Confirmed
sample
analyses
for
gaseous
or
liquid
release
rates
>2x
technical
specifications
limits
for
>60
min.
All
5.2.2
Alert
[AA1]
Confirmed
sample
analyses
for
gaseous
or
liquid
release
rates
>200
xtechnical
specifications
limits
for
>15
min.
All 5.2.3
Alert
[AA1]
site
Area
Emergency
[AS1
]
Dose
projections
orfield
surveys
resulting
from
actual
or
imminent
release
which
indicate
doses/
dose
rates
>Table
5.2
column
"SAE"
at
the
site
boundary
or
beyond.
All 5.2.5
General
Emergency
[AGi]
Dose
projections
orfield
surveys
resulting
from
actual
or
imminent
release
which
indicate
doses/
dose
rates
>Table
5.2column
"IGE
"Iat
the
site
boundary
or
beyond.
All
Dose
projections
or
field
surveys
resulting
from
actual
or
imminent
release
which
indicate
doses/
dose
rates
>Table
5.2
column
"Alert"
atthe
site
boundary
or
beyond.
All
5.0
Radioactivity
Release/Area
Radiation
5.0
Radioactivity
Release/Area
Radiation
![Page 45: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/45.jpg)
WCategoP.
0Radioactivity
Release
5.3
Area
Radiation
Levels
S.3.1
Unus
ual
Even
t[AU2]
Any
sustained
direct
ARM
readings
>10
0x
alarm
or
offscale
hiresulting
froman
uncontrolled
process
All
5.3.2
Alert
[AA3]
Sustained
area
radiation
levels
>15
mR/hr
ineither:
Control
Room
OR
Central
Alarm
Station
and
Secondary
Alarm
Station
All
S.3.3
Alert
[AA3
]
Sustained
abnormal
area
radiation
levels
>8
R/hrwithin
any
areas,
Table
5.3
AND
Access
isrequired
for
safe
operation
or
shutdown
All
![Page 46: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/46.jpg)
Catego~p.
Radioactivity
Release
Monitor
NUE
Alert
SAE
GE
R-27
7.2E4
gCi/se:
3.60
Ci/sec
36.0
Ci/sec
360
Ci/sec
B/UHRVntMon
N/A
N/A
N/A
N/A
R-14
150,000
cpm
N/A
N/A
N/A
R-19
9.50
MCi/cc
475
MCi/cc
N/A
N/A
Table
5.2
Dose
Projection
/Env
.Measurement
Classification
Thresholds
Alert
SAE
GE
TEDE
10mRem.
100
mRem
1000
mRem
CDE
Thyroid
N/A
500
niRem
5000
niRe
m
External
exposure
rate
10mRem/hr
100
mRem/hr
1000mRem/hr
Thyroid
exposure
rate
N/A
500
mRem/hr
5000
mnRe
m/hr
(for
1hr.
ofinhalaton)
_______
Table
5.3
Plant
Areas w0
Tabl
5.
Efluen
Moito
ClasifcatonTresold
0
![Page 47: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/47.jpg)
CategoqI5.0
Radioactivity
Release
oAuxiliary
Feedpump
BuildingU
oP.A.B.
oFuel
Storage
Building
oControl
Building
"ServiceWater
Pumps
oRefueling
Water
Tank
o.
Diesel
Fuel
Tanks.
"Vital
Area
Access
to
Containment
"AppendixR
Diesel
Generator
"Backup
Service
Water
![Page 48: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/48.jpg)
Categoq.
0Electrical
Failures
6.0
Electrical
Failures
6.1
Loss
of
AC
Paver
Sources
6.1.1
Unusual
Event
[SUl
)
Loss
ofpower
to
all
Station
Transformers
5,
2,
3,6
for>
15min.
from
all
ofthe
following
offsite
sources:
oUnit
Auxiliarytransformer
0Station
Auxiliary
transformer
013W92
and
13W93
feeders
All
6.1.2
Alert
[SAl
]
Loss
ofall
safeguard
bus
AC
power>
15
min.
cold
shutdown,
Refueling,
Defueled
6.1.3
Alert
[SA5
]
Available
safeguard
bus
ACpower
reduced
to
only
one
ofthe
following
for>
15
min.: "
480V
EDG
31
o480V
EDG
32
"480V
EDG
33
oAppendixR
Diesel
oUnit
Auxiliary
transformer
oStation
Auxiliary
transformer
"13
W92
and
13W9
3feeders
Power
operation,
hot
shutdown
6.0
Electrical
Failures
6.1
Loss
ofAC
Power
Sources
6.1.4
Site
Area
Emergency
[551]
Loss
ofall
safeguard
bus
AC
power
>15
min.
Power
operation,
hot
shutdown
6.1.5
General
Emergency
(SG1
]
Loss
ofall
safeguard
bus
AC
power
AND
either:
Power
restoration
to
any
emergency
bus
isnot
likely
in24
hrs.
OR
Actual
orimminent
entry
into
ORANGE
orRED
path
on
F-0.
2,"CORE
COOLING"
Power
operation,
hot
shutdown
6.0
Electrical
Failures
6.2
Loss
ofDC
Power
Sources
![Page 49: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/49.jpg)
IWCategoVIM.0
Electrical
Failures
6.2.1
Unusual
Event
[SU7]
<105
vdc
bus
voltage
indications
for>
15
min.
on
the
switchable
voltmeter
for
all
of
the
following
panels:
o31
o32
o33
'o34
Cold
Shutdown,
Refueling
6.2.2
Site
Area
Emergency
[SS3]
.<105
vdo
bus
voltage
indications
for
>15
min.
on
the
switchable
voltmeter
for
all
of
the
following
panels:
031
032
033
034
Power
operation,
hot
shutdown
*64
![Page 50: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/50.jpg)
7.0
Equipment
Failures
701
Technical
Specification\Requirements
7.1.1
Unusual
Event
[SU2
J
Plant
isnot
brought
to
required
operating
mode
within
Technical
Specifications
LCO
Action
Statement
Time.
Power
operation,
hot
shutdown
7.0
Equipment
Failures
egoq.
0MW
ent
Failures
7.2
System
Failures
or
Control
Room
Evacuation
7.2.1.
Unus
ual
Event
[HUl
l
Report
ofmain
turbine
failure
requiring
turbine
trip
resulting
in:
Damage
to
turbine
generator
seals
OR
Casing
penetration
PowerOperations
7.2.2
Alert
[HAl]
Turbine
failure
generated
missiles
which
causes
or
potentially
causes
any
required
safety
related
system
orstructure
to
become
inoperable
Power
Operations,
Hot
Shutdown
7.2.3
Alert
(HA5
]
Entr
yin
toONOP-FP-lA,
"Safe
Shut
down
From
Outside
the
Control
Room"
All
7.0
Equipment
Failures
7.2
System
Failures
or
Control
Room
Evacuation
0
![Page 51: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/51.jpg)
Categof7v7.0
Equipment
Failures
7.2.4
Alert
[SA3]
Reactor
coolant
temperature
cannot
be
maintained
<200
OF
Cold
Shutdown,
Refueling
7.2.S
Unplanned
loss
ofmost
safety
system
annunciators
or
indications
on
Control
Room
Panels,
Table
7.3
for
>15
min.
AND
Increased
surveillance
isrequired
for
safe
plant
operation
Poweroperation,
hot
shutdown
sitsArea
Emergency
[HS2]
Control
Room
evacuation
AND
Plant
control
cannot
beestablished
per
ONOP-FP-1A,
"Safe.Shutdown
FromOutside
the
Control
Room"
in2
15min.
All
7.3.2
Unusual
Event
(SU6]
Loss
ofall
communications
capability
affecting
the
ability
to
either:
Perform
routine
operations
(phones,
sound
powered
phone
systems,
page
party
system,
and
radios/walkie
talkies)
OR
Notify
offsite
agencies
orpersonnel
(ENS,
Bell
line
s,FAX
transmissions,
and
dedicated
phone
systems)
All
7.0
EquipmentFailures
7.0
EquipmentFailures
7.3
LossofIndications/Alarms
CommunicationCapability
7.3.1
7.3
LossofIndications/Alarms
CommunicationCapability
7.3.3
Unusual
Event
[SU3]
Alert
[SA4
1
Unplanned
loss
of
most
safety
system
annunciators
or
indications
onControl
Room
Panels,
Table
7.3
for
>15
min.
![Page 52: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/52.jpg)
wcategoIM.
Equipment
Failures
AND
Increased
surveillance
isrequired
for
safe
plant
operation
AND
either:
Asignificant
plant
transient
in
progress
OR
CFM4
Sand
QSPDS
are
unavailable
Power
operation,
hot
shutdown
7.3.4
site
Area
Emergency
CSS6
]
Loss
ofmost
safety
system
annunciators
or
indications
on
Control
Room
Panels,
Table
7.3 AND
Loss
of
CFMS,
QSPDS
and
other
control
room
indicators
needed
to
monitor
critical
safety
function
status
AND
Asignificant
plant
transient
inprogress
Power
operation,
hot
shutdown
Table
7.3
Vital
Control
Room
Panels
SAF
SBF-1
SBF-2
CD
EF
GH
J-K
LH
N
0FAF
FBF
FCF
FCF
--
--
74j
![Page 53: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/53.jpg)
catego"
.Hazards
8.0
Hazards
8.2.
Security
Threat.
8.1
securityThreat.
8.1.3
Unusual
Event
[HU4
]
Bomb
device
orother
indication
of
attempted
sabotage
discovered
within
plant
Protected
Area
but
outside
Plant
Vital
Areas,
Table
8.2.
OR
Any
security
event
which
represents
apotential
degradation
inthe
level
of
safety
ofthe
plant.
All 8.1.2
Alert
[HA4]
Intrusion
into
plant
ProtectedArea
by
an
adversary.
OR
Any
security
event
which
represents
an
actual
substantial
degradation
ofthe
level
ofsafety
ofthe
plant.
site
Area
Emergency
[HSl]
Intrusion
into
aplant
security
vital
area
by
an
adversary.
OR
Any
security
event
which
represents
Actual
or
likely
failures
ofplant
systems
needed
toprotect
the
public.
All
8.1.4
General
Emergency
[HG1]
Security
event
which
results
in:
Loss
ofplant
control
from
the
Control
Room
AND
Loss
ofremote
shutdown
capability
All
8.0
Hazards
8.0
Hazards
8.2
Fire
or
Explosion
w
8.1.1
All
![Page 54: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/54.jpg)
Catego.
Hazards
Unusual
Event
[HU2]
Confirmed
fire
inor
contiguous
to
any
plant
area,
Table
8.2
not
extinguished
in
215
min.
ofControl
Room
notification:
Vehicle
crash
into
or
projectile
which
impacts
plant
structures
or
systems
within
Protected
Area
boundary
All
8.3.2
Unusual
Event
[HU3]
8.2.2
Unusual
Event
[Hil
l]
Report
by
plant
personnel
of
an
explosion
within
Protected
Area
boundaryresulting
in
visible
damage
tonon-vital
permanent
structures
orequipment.
All
8.2.3
Alert
(HA2]
Fire
orexplosion
inany
plant
area,
Table
8.2,
which
causes
orpotentially
causes
any
required
safety
related
system
or
structure
to
become
inoperable
All
Report
or
detection
oftoxic
orflammable
gases
that
could
enter
or
have
entered
within
the
Protected
Area
boundary
in
amounts
that
could
affect
the
health
of
plant
personnel
orsafe
plant
operation
OR
Report
by
local,
county
or
state
officials,
orUnit
2,
for
potential
evacuation
ofsite
personnel
based
on,
offsite
event
All 8.3.3
Alert
(HAl
]
Vehicle
crash
or
projectile
impact
which
causes
orpotentially
causes
any
required
safety
related
system
or
structure
to
become
inoperable,
Table
8.2
All 8.0
Hazards
8.3
Man-Made
Events
8.3.1
Unusual
Event
[Hill]
8.3
Man-MadeEvents
8.3.4
Alert
846
8.2.1
All
8.0
Hazards
[HA3]
![Page 55: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/55.jpg)
Hazards
Report
or
detection
oftoxic
or
flammable
gases
within
aplant
area,
Table
8.2,
in
concentrations
that
will
be
life
threatening
to
plant
personnel
or
preclude
access
to
equipment
(evenwhen
using
personal
protective
equipment)
needed
for
safe
plant
operation
All
Earthquake
felt
inpiant
based
upon
aconsensus
ofControl
Roomoperators
on
duty
AND
either
Kinemetrics
StrongMotion
Accelographs
inthe
VC
produce
an
alarm
inthe
Control
Room
OR
At
least
one
amber
Peak
Shock
Annunciator
isli
t
All
8.4.2
Unusual
Event
[HUll
Report
by
plant
personnel
oftornado
within
plant
Protected
Area
boundary
All
8.4.3
Unusual
Event
[HUl)
River
level
314.51
(OMSL)
OR
Intake
structure
level<-4.5'
(OMSL)
All
8.0
Hazards
8.0
Hazards
8.4
Natural
Events
8.4.1
Unusual
Event
[HUl]
8.4
Natural
Events
18.4.4
Alert
[HAl
]
800
![Page 56: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/56.jpg)
catego
Hazards
Earthquake
felt
inplant
based
upon
aconsensus
of
Control
Room
operators
on
duty
AND
Kinemetrics
Strong
Motion
Accelographs
in
the
VC
produce
an
alarm
inthe
Control
Room
AND
Amber
and
red
Peak
ShockAnnunciators
indicate
seismic
activity
All
8.4.5
Alert
[HAl]
Sustained
winds
>90
mph
OR
Tornado
strikes
aplant
vital
area,
Table
8.2
All
8.4.6
Alert
[HAl]
Assessment
by
the
Control
Room
personnel
that
anatural
event
has
occurredwhich
causes
orpotentially
causes
any
required
safety
related
system
orstructureto
become
inoperable,
Table
8.2
River
leve
l3
I5'
(OMSL)
OR
Intake
structure
level
resulting
ina
loss
of
service
water
flow
All
All8.0
Hazards
8.4
NaturalEvents
8.4.7
Alert
[HAl]
.Q-
Table
8.2
Plant
Areas
"Auxiliary
Feedpump
Building
oP.A.B.
oCAS/SAS
oFuel
Storage
Building
"Control
Building
oControl
Room
"ServiceWater
Pumps
"Refueling
Water
Tank
oEDGRooms
oDiesel
Fuel
Tanks
oVital
Area
Access
to
Containment
o-Appendix
RDiesel
Generator
oBackup
Service
Water
![Page 57: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/57.jpg)
Categof7D.0
other
9.0
Other
9.1.01
Unusual
Event
Any
event,
asdetermined
by
the
Shift
Supervisor
or
Emergency
Director,
that
could
lead
to
or
has
led
to
apotential
degradation
ofthe
level
ofsafety
of
the
plant.
All
9.0Other
9.1.4
Alert
Any
event,
asdetermined
by
the
Shift
Supervisor
or
Emergency
Director,
that
could
lead
or
has
led
toa
loss
or
potential
loss
ofeither
fuel
clad
or
RCS
barrier,
AttachmentA.
Power
operation,
hot
shutdown
UnusualEvent
Any
event,
asdetermined
by
the
Shift
Supervisor
orEmergency
Director,
that
could
lead
to
or
has
led
to
aloss
or
potential
loss
of
containment,
Attachment
A.
Power
operation,
hot
shutdown
9.1.3
Alert
Any
event,
asdetermined
by
the
Shift
Supervisor
or
Emergency
Director,
that
could
cause
or
has
caused
actual
substantial
degradation
ofthe
level
of
safety
ofthe
plant.
All
9.1.5
Bite
Area
Emergency
As
determined
by
the
Shift
Supervisor
or
Emergency
Director,
events
are
inprogress
which
indicate
actual
or
likely
failures
of
plant
systems
needed
to
protect
the
public.
Any
releases
are
not
expected
to
result
inexposures
which
exceed
EPA
PAGs.
All
9.1.6
Site
Area
Emergency
Any
event,
asdetermined
by
the
Shift
Supervisor
or
Emergency
Director,
that
could
lead
or
has
led
to
either:
Loss
or
potential
loss
ofboth
fuel
clad
and
RCS
barrier,
Attachment
A.
OR
Loss
orpotential
loss
ofeither
fuel
clad
orRCS
barrier
inconjunction
with
aloss
ofcontainment,
Attachment
A.
9.1.2
![Page 58: ^ NewbrkF'bwer Authority William J. Cahill, Jr. Chief ...Bases, Revision 1, January 10, 1995, Operations Support Services, Inc., OSSI-92-402A-4-1P3 IV. Fission Product Barrier Evaluation,](https://reader033.vdocuments.us/reader033/viewer/2022050311/5f738384c73fea22fb64871b/html5/thumbnails/58.jpg)
Categaryw
Other
Power,operation,
hot
shutdown
9.0
Other
9.1.7
General
Emergency
As
determined
by
the
Shift
Supervisor
or
Emergency
Director,
events
are
inprogress
which
indicate
actual
or
imminent
core
damage
and
the
potential
for
alarge
release
ofradioactive
material
inexcess
of
EPA
PAGs
outside
the
site
boundary.
All
9.1.8
General
Emergency
Any
event,
asdetermined
by
the
Shift
Supervisor
orEmergency
Director,
that
could
lead
or
has
led
toa
loss
ofany
two
fission
product
barriers
and
loss
or
potential
loss
ofthe
third,
Attachment
A.
Power
operation,
hot
shutdown
'9.0