VISIONWALL Project Profile ® Featuring VISIONWALL High Performance Window and Curtain Wall Systems ® Location: Owner: Architect: General Contractor: St. Louis, Missouri, USA St. Louis Airport Authority Hellmuth Obata & Kassabaum McCarthy Brothers. VISIONWALL Representative: Technical Products Co. Inc. Product Information: ? ? ? ? ? ? ? VISIONWALL 3 Element, interior glazed, capped Curtain Wall and Window System 6mm clear (low-e) Heat Strengthened Interior lites 6mm GRN on PPG Solex Green (low-e) Heat Strengthened Duranar XL Silver and finish Exterior lites interior exterior Overall Window U-Value=0.21 Btu/hr-ft - f Shading Coefficient=0.30 Sound Transmission Class (STC)=36 20 ® International Airport Lambert St. Louis

Upload: dangdat

Post on 07-Jul-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

VISIONWALLProject Profile

®

Featuring VISIONWALL High Performance

Window and Curtain Wall Systems

®

Location:

Owner:

Architect:

General Contractor:

St. Louis, Missouri, USASt. Louis Airport Authority

Hellmuth Obata & KassabaumMcCarthy Brothers.

VISIONWALL Representative: TechnicalProducts Co. Inc.

Product Information:

���

VISIONWALL 3 Element, interior glazed,capped Curtain Wall and Window System6mm clear (low-e) Heat StrengthenedInterior lites6mm GRN on PPG Solex Green (low-e)Heat StrengthenedDuranar XL Silver andfinish

Exterior litesinterior exterior

Overall Window U-Value=0.21 Btu/hr-ft - fShading Coefficient=0.30Sound Transmission Class (STC)=36

2 0

®

International Airport

Lambert St. Louis

Lambert St. Louis International Airport

Visionwall Corporation17915 - 118 Avenue

Edmonton, Alberta, Canada T5S 1L6

Tel: 780-451-4000 Fax: 780-451-4745

E-Mail: [email protected]

WWW.VISIONWALL.COM

Your VISIONWALL contact is:

High Performance Curtain Wall Provides Big Savings

The life-cycle cost study was conducted by the consulting engineeringfirm of Ross & Baruzzini, Inc., who were the mechanical engineeringconsultants for the project. Their study indicated that at the end of the ten(10) year period being considered, the VISIONWALL system not onlymade up the cost differential to the conventional system, but saved theowner an additional $300,000+.

®

The use of the VISIONWALL high performance system had a dramaticimpact on the first cost of the mechanical system, saving over $350,000.Capital cost savings were realized in the following areas:

Reduced HVAC multi-zone system size.Elimination of hot water finned tube perimeter heating system inmany areas due to VISIONWALL’s high thermal efficiency.Reduced chilled water distribution system for cooling due toVISIONWALL’s improved shading coefficients.

Reduced plant energy consumption (as a result of the smaller HVACsystem) with the VISIONWALL system has resulted in operating costsavings of approximately $52,000/year since the completion of thisproject in 1996.

®

��

Please download our product catalogue from for the complete

case study on the Lambert St. Louis International Airport.

www.visionwall.com

The City of St. Louis wanted to build a 200,000

square foot, $6.1 million expansion of the EastTerminal at Lambert St. Louis International Airport.This expansion included 41,000 square feet ofcurtain wall.

A life-cycle costs analysis was done to compare thetrue costs of a VISIONWALL high performancecurtain wall system to a conventional double glazedcurtain wall system for use in the terminal expansionat Lambert St. Louis International airport. This studyconsidered the first cost of the two glazing systems,HVAC system capital cost reductions and operatingcost savings. The study was done at the request ofthe airport authority (owner) to verify the architect’sdesign decision to utilize the VISTONWALL curtainwall system.

®

®

J134 Printed in Canada 2004/11/29