costs are planned, measured, analyzed and controlled in terms of project activities. expenditure...
TRANSCRIPT
![Page 1: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/1.jpg)
Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly
over the duration of the activity. Budgeted cost of the activity is earned value. When activity is complete it is assumed to earn
value for project equivalent to its budgeted cost. Project progresses track is kept of actual value
earned and also actual cost.
![Page 2: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/2.jpg)
It is the % of the total cost budgeted against the total cost incurred
![Page 3: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/3.jpg)
In case Actual Expenditure incurred for completion of an activity exceeds its budgeted cost, the project does not earn any additional benefit since activity parameters are well specified. The variance indicated cost over-run
![Page 4: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/4.jpg)
![Page 5: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/5.jpg)
![Page 6: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/6.jpg)
![Page 7: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/7.jpg)
![Page 8: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/8.jpg)
![Page 9: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/9.jpg)
CV= ACWP – BCWP Cost Variance CPI = BCWP / ACWP Cost
Performance Index SV = BCWP – BCWS Schedule
Variance SPI = BCWP / BCWS Schedule
Performance Index TV = (Date of Review) – (Date on
which BCWP = BCWS) Time Variance ECP Index = BCTW /(ACWP + ACC)
Estimated cost of performance index
![Page 10: Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration](https://reader036.vdocuments.us/reader036/viewer/2022062620/551b486a5503465c7e8b5577/html5/thumbnails/10.jpg)
Cost over – run ->When the cost incurred is more than the value of work done.
Cost under – run -> When the cost incurred is less than the value of work done.
CV <1 = cost over run Time over-run -> project is behind schedule Time under-run -> project is ahead of
scheduleSV <1 = time over run