© copyright 2013 by k&l gates llp. all rights reserved. u.s. natural gas pipelines: regulatory...
TRANSCRIPT
© Copyright 2013 by K&L Gates LLP. All rights reserved.
U.S. Natural Gas Pipelines: Regulatory and Policy Developments
University of Pittsburgh School of LawEnergy Law & Policy InstituteAugust 1, 2013
David L. Wochner, PartnerWashington, [email protected]
klgates.com 2
Overview FERC Regulation of Natural Gas
General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
Other Issues Supply Changes Environmental Commercial
klgates.com 3
FERC REGULATION OF NATURAL GAS
klgates.com 4
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 5
FERC Basics
Independent (non-political) agency 5 Commissioners
5-year terms Senate confirmed
3 from President’s political party 2 from the opposition party or Independent
klgates.com 6
FERC Organization
klgates.com 7
FERC General Regulation
FERC regulates: Transportation and sale of natural gas for resale in
interstate commerce Transportation of oil and products by pipeline in
interstate commerce Transmission and wholesale sale of electricity in
interstate commerce Other matters related to the operation of oil, natural
gas, electric, and hydro-projects
klgates.com 8
FERC Regulation of Natural Gas Natural Gas Pipelines and Storage Facilities
Rates (Pipelines and natural gas storage, not LNG) Regulates to ensure rates and terms of service are “just and reasonable” and
detailed in publicly available “tariffs”
Access Requires open and non-discriminatory access to interstate natural gas
facilities and services
Abandonment Regulates termination of service and abandonment of interstate facilities
Siting, Construction, Operation Approves location, construction and operation of facilities for liquefaction,
regasification, transportation and storage of interstate natural gas
Environmental Coordinates requirements relating to natural gas pipeline and LNG projects
klgates.com 9
Natural Gas Act of 1938
Section 3 Import/export of natural gas LNG facilities
Section 4 Pipeline and storage rate
filings Terms and conditions of
service “Just and reasonable” rates
Section 4A Market manipulation
Section 5 Complaint oversight
Section 7 Construction and operation
of facilities Section 21
General enforcement Section 23
Transparency Reporting requirements
Basis of FERC’s authority to regulate facilities used for the transportation and wholesale sale of natural gas in interstate commerce
klgates.com 10
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 11
To construct a natural gas pipeline, developer must first obtain from FERC a certificate of public convenience and necessity
FERC’s review addresses rate, terms and conditions of service, environmental and safety issues
FERC coordinates with multiple federal, state, and local government agencies who provide input to FERC regarding their respective areas of authority and influence
FERC Process
klgates.com 12
Phases to the traditional FERC certification process Applicant’s planning process FERC review procedure
Pre-filing process – Optional for natural gas pipelines Preparation of (draft and) final resource reports Formal application
Participation of interested parties Preparation of draft and final environmental impact
Statement (“EIS”) or environmental assessment (“EA”) consistent with the National Environmental Policy Act (“NEPA”)
FERC decision Construction process
FERC Process
klgates.com 13
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 14
Pre-Filing Process Under EPAct 2005, FERC was required to enact rules mandating FERC’s previously voluntary NEPA environmental
pre-filing process for LNG facility proposals FERC’s regulations made pre-filing voluntary for pipelines However, many new pipelines and expansion now utilize the pre-filing process
Regulations require that pre-filing procedures be initiated a minimum of 6 months prior to filing formal application FERC’s pre-filing process is an informal review process No ex parte rules apply so FERC Staff is free to have private, non-public conversations with the project proponent
During the pre-filing process FERC Staff works with the applicant to gather information about the proposed project Identify and resolve as many potential issues or obstacles in advance of the formal application when ex parte rules do apply
klgates.com 15
Pre-Filing Process
Source: http://www.ferc.gov
klgates.com 16
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 17
Formal Application
Source: http://www.ferc.gov
klgates.com 18
Formal Application Once a party files its formal application, FERC will issue
notice of the application and all interested parties may intervene and submit comments
FERC will prepare an EA or a draft/final EIS, which interested parties also may comment on
Detailed filings required, including rate analysis and justification for proposed cost-based rate, a draft tariff, engineering and design information, maps and diagrams, an environmental report, pro forma tariffs and initial rate services, as well as financial and operational information
Even an uncontested application can take between 8-12 months for FERC to review and issue decision
FERC approval process is elaborate and public
klgates.com 19
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 20
Environmental Review NEPA requires that federal agencies conduct an environmental analysis of proposed federal actions prior to
decision-making Approval or denial of an application to site, construct, or operate an interstate natural gas pipeline is a federal action FERC conducts comprehensive environmental assessment and coordinates with other agencies and with retained
third-party environmental contractor paid for by the applicant Environmental review is time consuming Must submit extensive environmental reports, including studies and consultations with federal, regional, state and
local agencies
klgates.com 21
Environmental Review FERC’s environmental review includes
The applicant’s receipt of environmental authorizations from other government bodies
The applicant’s preparation and submission of resource reports FERC’s preparation of an EA, and/or possibly an EIS
klgates.com 22
Environmental Authorizations from Other Agencies FERC’s final authorization is conditioned on satisfaction of statutory environmental requirements
Two primary federal environmental laws figure into FERC’s analysis Clean Air Act Clean Water Act
Authority to administer these federal laws is delegated to the states in which the proposed activities occur
These are federal laws and are of equal power and authority to FERC’s authority under the Natural Gas Act
If a state environmental agency determines that the proposed activities have not and cannot comply with one of these federal laws, it likely has the authority to stop a project
klgates.com 23
Resource Reports To implement NEPA, FERC’s regulations require an applicant to submit an Environmental Report
that consists of 13 resource reports The Environmental Report contains the applicant’s analysis of the environmental impact of the proposed
activity
The applicant submits draft versions of its resource reports during the pre-filing process The applicant submits the final version of its resource reports with its formal application
Cooperating federal and state agencies have the opportunity to comment on the draft resource reports
klgates.com 24
Report Description Required For
1 General project description All applications
2 Water use and quality All applications outside area of existing compressors, meters, and regulator stations
3 Fish, wildlife, and vegetation All applications outside improved area of existing compressors, meters, and regulator stations
4 Cultural resources All applications
5 Socioeconomics All applications involving aboveground facilities
6 Geological resources All applications outside the boundaries of existing aboveground facilities
7 Soils All applications involving soil disturbance
8 Land use, recreation, and aesthetics All applications
9 Air and noise quality New LNG facilities
10 Alternatives All applications
11 Reliability and safety New and recommissioned LNG facilities
12 PCB contamination Removal or abandonment of PCB pipe
13 Engineering and design material New and recommissioned LNG facilities
Resource Reports
klgates.com 25
EIS v. EA EAs serve three main purposes
To briefly provide sufficient evidence and analysis for determining whether to prepare an EIS To aid FERC’s compliance with NEPA when no EIS is necessary To facilitate preparation of an EIS when one is necessary
EAs are concise documents and must include a brief discussion of the proposal, alternatives, the environmental impacts of the proposal and alternatives, and a list of the agencies and persons consulted
EAs conclude either with a finding of no significant impact (“FONSI”) or a finding that an EIS is required
40 CFR § 1508.9
klgates.com 26
EIS v. EA By contrast, an EIS is a more robust and
comprehensive document The process for preparing an EIS is proscriptive
Publish notice of intent to prepare an EIS in the Federal Register (public notice)
Scoping Prepare and circulate draft EIS Receive comments from interested parties on draft EIS Issue final EIS Prepare and issue CPCN that adopts and sometimes
modifies the environmental conclusions and alternatives and mitigation measures recommended in the final EIS
klgates.com 27
FERC Regulation of Natural Gas General Agency Overview FERC Process Pre-Filing Process Formal Application Environmental Review FERC Decision
klgates.com 28
FERC Decision
Source: http://www.ferc.gov
klgates.com 29
FERC Decision No deadline for FERC to issue a decision on a new pipeline certificate project
If FERC approves a project, its order will contain a number of environmental mitigation measures
Once FERC issues a decision, the applicant and parties who intervened in the proceeding can file a request for rehearing within 30 days
FERC is then required under the NGA to answer that request within 30 days or the request is deemed denied
FERC may issue a tolling order
If FERC rejects a party’s request for rehearing, the party may file an appeal of the decision in U.S. federal appeals court within 60 days
If the project developer has satisfied all of the measures in FERC’s order, it will be able to continue construction of the project throughout any appeals process
klgates.com 30
CURRENT ISSUES
klgates.com 31
Current Issues – Supply Changes U.S. domestic gas picture has changed
Massive new technically and economically recoverable shale gas resources
Surplus has quelled concerns of many elected officials about adequacy of supply
Support of domestic natural gas production and use from White House … kind of Repeated statements by President Obama recognizing economic
and environmental benefits of natural gas Growth in manufacturing and petrochemical sectors Increased use as a transportation fuel
As a result, substantial increase in natural gas pipeline infrastructure
klgates.com 32
Current Issues – Environmental Keystone XL is a line in the sand for the U.S. environmental
movement Movement has now shifted to hydraulic fracturing and LNG
exports – Sierra Club is leading the opposition Quantifiable shift from previous position in first half of last decade Opposition is rooted in concerns over increased shale gas
production and hydraulic fracturing Asserts that FERC and DOE should look at the environmental
impacts of hydraulic fracturing since allowing exports necessarily will result in additional shale gas production
Argues that the environmental reviews are inadequate and do not satisfy NEPA
Indirect effects Reasonably foreseeable
klgates.com 33
Current Issues – Environmental April 2012 Sierra Club letter to White House Council on
Environmental Quality (CEQ) asserting the alleged harms of natural gas production and use in generation “Unconventionally sourced LNG is the very dirtiest form of a dirty
fuel.”
EPA regional inquiries in FERC pipeline certificate proceedings related to upstream production
Methane emissions from natural gas pipelines Questions about adequacy of technology Questions about pipelines’ ability to recover costs
klgates.com 34
Current Issues – Commercial Conversion of existing natural gas pipelines to
transport oil and oil products Existing customer protections
Substantial new pipeline capacity in previously less-served regions provide utilities and large industrials opportunities for new gas supply Become an “anchor shipper”
klgates.com 35
QUESTIONS?
36