© abb group september 4, 2015 | slide 1 status, benefits and challenges of electrification by power...

29
© ABB Group March 27, 2022 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16, Bellona Seminar

Upload: nathan-newman

Post on 26-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 1

Status, benefits and challenges of Electrification by Power from Shore

Trygve Iversen, ABB AS – OGP, 2010-03-16, Bellona Seminar

Page 2: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 2

Electrification

Advocate and develop economical and HSE sensitive solutions for offshore installations

How

Studies /feasibility

Electrification (power from shore)

Automation

Remote Diagnostics/Condition based maintenance

Maximize technology utilization to minimize OPEX by moving the personnel on-shore

Page 3: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 3

Power from (to) Shore solutions

AC

HVDC

ACHVDC

HVDC

Page 4: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 4

“Classic” (Radial Feed) Power from (to) Shore

onshore

OnshoreSub Station

Oil PlatformHVDC

OnshoreConverter

Wind farm

offshore

HVAC

<150MW

<150km

Oil PlatformHVAC

HVDC

>50MW

>150km

HVDCStation

OnshoreConverter

HVDC

>200MW

>100km

Gjøa, Goliat, Halul, + +

Troll, Valhall, Luva, + +

E-On

Page 5: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 5

Offshore Grid Multi-terminal HVDC Light solutions (Ring Net)

onshore

PlatformDC

OnshoreConverter

PlatformDC

OnshoreConverter

PlatformDC

PlatformAC Platform

AC

Hosted on platform or buoy

Wind farm

Wind farmWave farm

Page 6: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 6

Technology Selection: GT vs. AC vs. DC

Power(MW)

Distance(miles)

AC

Tra

nsm

issi

on

DC Transmission

Gas Turbines

An Example ofEconomical Window ofOpportunity for Power From / To Shore

Page 7: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 7

Business Process – Early Involvement / Studies

Product suppliers responds to RFQ here

System approachearly start

Feasibility

Concept

Market Shift to system approach

Pre Feed Feed

Basic/

Detailed Design

/FAT

Installation/

CommissioningStart-up Operation

All Electricdecision

Products and services

MEV decision

The most critical decisions are made early

Secure best information for optimal decisions

Page 8: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 8

Power From ShoreDelivered

Statoil Troll, HVDC-Light Compressor drives, 2x40MW, ca. 80km

Statoil Gjøa, AC Power, 40MW, 100km, 90kV

Under Delivery

BP-Vallhall redevelopment, HVDC, 78MW, 292km (Revamp)

E.On Windpower hub, HVDC, 350MW, ca 200km incl onshore (power to shore!)

In pursuit

ENI-Goliat, 60-120MW, 90km, HVAC

Studies ABB has participated in recently:

Shell Draugen redevelopment, HVDC or AC, 60MW, 60km

Statoil & Others -Halten Banken electrification, HVDC and HVAC

In concept / feed

Conoco-Phillips Ekofisk –HVDC (Revamp)

Qatar Petroleum, PS4-platform, 25-30MW, 80km, 60-66kV (AC)

Qatar Petroleum, Halul Oil Terminal, 100-130MW, AC!

Saudi Aramco, Safaniyah

Statoil, Mariner & Bressney

Statoil, Gudrun (Platform to Platform, i.e. Sleipner to Gudrun)

Statoil, Sleipner (50/60Hz converter –Platform to platform)

(Statoil-Shell-Total, Norskehavet (to start end 2009) –Multi terminal HVDC and HVAC)

Statoil-Luva HVDC

Abu Dabi, Das Island

Page 9: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 9

Troll HVDC

Page 10: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 10

Off shore power supply .. Troll

Troll, HVDC-Light

Pre-Compressors

2x40MW, ca. 80km

In operation 2005

Page 11: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 11

Valhall HVDC

Page 12: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 12

Description One HVDC light station

off-shore and one on-shore

292 km HVDC Cable

Main data P = 78 MW

UDC = 150 kV

Status Onshore station in operation

Offshore module being installed

Commercial operation 2010

Valhall

Lista

Valhall

Page 13: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 13

TransformerTransformer ValvesValves

Phase ReactorsPhase Reactors

Valhall – PFS – Technical solution

Page 14: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 14

Eon NetzWind Power to Shore

Page 15: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 15

EON 2 off shore cluster

75 km land cable

128 km sea cable

400 MW off shoreconvertor

400 MW convertorIn opera

tion 2009 !!

Page 16: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 16

Gjøa HVAC

Page 17: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 17

Gjøa

High Voltage AC

40MW, 100km

In operation 2010

Similar projects underways

Goliat

Halul-Qatar

Al Mojan-Qatar

Safaniyah-Saudi

(Abu Dabi)

Page 18: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 18

Middle East -Electrification

Page 19: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 19

Cable Projects in Qatar

Halul IslandRas Lafan

PS 4(QP)25-30 MW

50/60 HZ

66kV

100 MW

HVAC

132 kV

80-90 km

100 km

Al-Morjan(Qxy)Existing Cable

PS 2

QP

PS 3

QP

Al-Khalij

Total

Future

Cables

Handled

by ABB NO OGP

as a system delivery

Page 20: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 20

Saudi Arabia -SafaniyahCustomer

EPC’s : McDermott, NPCC

End-user:

Consultant:

Overall Project Scope Meet the Crude Program production and

Maximum Sustainable Capacity (MSC) targets for the Safaniyah Field of 1,300 MCBD by 2013. Increase transportation capacities. Install new ESP’s

Project Location Safaniyah is located in the Northern Area of

Arabian Gulf

CLOUGH ZUHAIR FAYEZ PARTNERSHIP

Page 21: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 21

SFNY GOSP-1

TP-20TP-20

SA 115 kV

SA 115 kV

TP-18TP-18

SEC Maaden

SEC Maaden

SEC 230kV

SEC 230kV

TYTY

VSVS

230 kV

115kV

69 kV69 kV

15 kV

TL-11

115 kV O/H

230 kV O/H 380 kV O/H

Offshore

Onshore

PROJECT SCOPE

940930 348 470 646

656

910

Aux

243

275

TP-19TP-17

New Facilities

Upgrade & electrification

Electrification

GOSP 3

GOSP 4

ExistingCountry ; KSA

Safaniyah is the largest offshore oil field in the world.

Project name: Safaniyah Crude Gathering upgrade

Customer: EPC’s

End-User: Saudi Aramco

Safaniyah KSA

Page 22: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 22

Concept Krieger’s Flak

Page 23: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 23

Kriegers Flak, individual cables

Classic issue involving multiple countries

Page 24: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 24

Kriegers Flak, “Supergrid” concept

VSC

VSC

Bentwisch/Guestrow

KF 1, 330 MW

VSC1100 MW

1100 MW

1100 MW

KF 2, 640 MW

100

km

Baltic 150 MW11

(55)

+12

1 km

11+

60 k

m

Barsebäck

±300 kV DC

BWL

KF 3, X MW (Option)

Page 25: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 25

Concept Super Grid

Page 26: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 26

Supergrid concept (Vision) Main concept, combine:

Integration of renewable energy

Interconnections for trading

Security of supply

Benefits

Reduced investment

Increased trading capacity

Back-up power, e.g. hydro power can support wind power

Large geographic area gives more stable production

Page 27: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 27

WG Offshore grid

Vision 2020 – an offshore grid enabling

Offshore wind parks

Power supply to oil fields

Energy exchange between markets

Ancillary services (freq control ++)

Task

Describe technology status

Describe ambitions towards an off shore grid

Describe R&D challenges

Page 28: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,

© ABB Group April 19, 2023 | Slide 28

Opportunities and ChallengesOpportunities:

Technology is available, no significant technology gaps

More compact HVDC solutions possible (reduced installed costs, 2 years to develop)

Challenges:

Time (not long until 2020)

Projects take time, typically 5-8 years from concept to operation

Get started!!!

Production limits

Cables

Build additional production lines (3-5 years)

Engineering resources

Limited supply of qualified engineers

Shift resources from other areas (2-4 years)

Page 29: © ABB Group September 4, 2015 | Slide 1 Status, benefits and challenges of Electrification by Power from Shore Trygve Iversen, ABB AS – OGP, 2010-03-16,